5846 N IRVINE AVE 91601

Certificate Information: 5846 N IRVINE AVE 91601

Application / Permit
20010-20000-00334
Plan Check / Job No.
B20VN01691
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
35'-2" X 22'-9" ADDITION TO (E) DETACHED GARAGE FOR CREATION OF 2-STORY ACCESSORY DWELLING UNIT. (E) GARAGE TO REMAIN.
Permit Issued
Issued on 8/19/2020
Issuing Office
Current Status
CofO Issued on 8/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2020 APPLICANT
Green Plans Picked Up 3/5/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 SERGIO MUNIZ
Corrections Issued 3/18/2020 SERGIO MUNIZ
Quality Review Completed 3/23/2020 OMID HEDAYAT
Building Plans Picked Up 3/24/2020 APPLICANT
Applicant returned to address corrections 5/15/2020 SERGIO MUNIZ
Applicant returned to address corrections 6/19/2020 SERGIO MUNIZ
Plan Check Approved 8/3/2020 SERGIO MUNIZ
Issued 8/19/2020 APPLICANT
CofO in Progress 7/1/2021 THOMAS FINNILA
Permit Finaled 8/25/2022 DANIEL ORRANTE
CofO Issued 8/25/2022 DANIEL ORRANTE
Permit Finaled 8/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/19/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 3/19/2020 GUILLERMO PETRA
Sewer availability Cleared 3/19/2020 GUILLERMO PETRA
Green Code Cleared 5/18/2020 DAVID MATSON
Disturb/Remove Protected Trees Cleared 7/8/2020 STEPHEN DUPREY
Low Impact Development Cleared 7/23/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/24/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Eden,, Joseph Taki; Lic. No.: C39955 14412 FRIAR ST      VAN NUYS, CA 91401

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/24/2020 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 8/26/2020 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 8/28/2020 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/8/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Underground Mechanical 10/8/2020 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 10/13/2020 Partial Approval THOMAS FINNILA
Green Building Rough 10/13/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 10/14/2020 Approved THOMAS FINNILA
ELECTRICAL-Rough 10/15/2020 Approved THOMAS FINNILA
HVAC-Rough 10/15/2020 Partial Inspection THOMAS FINNILA
Shower Pan 10/16/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 10/19/2020 Not Ready for Inspection THOMAS FINNILA
Wood Frame 10/19/2020 Approved THOMAS FINNILA
Insulation 10/20/2020 Not Ready for Inspection THOMAS FINNILA
Insulation 10/21/2020 Approved MICHAEL SMITH
BUILDING-Rough-Frame 10/23/2020 Approved THOMAS FINNILA
Drywall Nailing 10/23/2020 Approved THOMAS FINNILA
Green Building Rough 10/23/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 10/29/2020 Not Ready for Inspection BEAU COLLINS
Interior/Exterior Lathing 11/16/2020 Approved THOMAS FINNILA
Gas Test 12/1/2020 Approved THOMAS FINNILA
ELECTRICAL-Final 12/4/2020 Approved THOMAS FINNILA
PLUMBING-Final 12/4/2020 Approved THOMAS FINNILA
HVAC-Final 12/21/2020 Corrections Issued THOMAS FINNILA
Final 6/1/2021 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 6/1/2021 Approved THOMAS FINNILA
Green Building Final 6/1/2021 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 6/1/2021 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 6/1/2021 Not Ready for Inspection THOMAS FINNILA
Final 6/2/2021 Partial Approval THOMAS FINNILA
Green Building Final 6/2/2021 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 6/2/2021 SGSOV Approved THOMAS FINNILA
Smoke Detectors 6/2/2021 Approved THOMAS FINNILA
Final 7/1/2021 OK to Issue CofO THOMAS FINNILA
Service/Power Release 7/1/2021 Approved THOMAS FINNILA