5846 N IRVINE AVE 91601
Certificate Information: 5846 N IRVINE AVE 91601
- Application / Permit
- 20010-20000-00334
- Plan Check / Job No.
- B20VN01691
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 35'-2" X 22'-9" ADDITION TO (E) DETACHED GARAGE FOR CREATION OF 2-STORY ACCESSORY DWELLING UNIT. (E) GARAGE TO REMAIN.
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2020 | APPLICANT |
| Green Plans Picked Up | 3/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | SERGIO MUNIZ |
| Corrections Issued | 3/18/2020 | SERGIO MUNIZ |
| Quality Review Completed | 3/23/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 3/24/2020 | APPLICANT |
| Applicant returned to address corrections | 5/15/2020 | SERGIO MUNIZ |
| Applicant returned to address corrections | 6/19/2020 | SERGIO MUNIZ |
| Plan Check Approved | 8/3/2020 | SERGIO MUNIZ |
| Issued | 8/19/2020 | APPLICANT |
| CofO in Progress | 7/1/2021 | THOMAS FINNILA |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
| CofO Issued | 8/25/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/19/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/19/2020 | GUILLERMO PETRA |
| Green Code | Cleared | 5/18/2020 | DAVID MATSON |
| Disturb/Remove Protected Trees | Cleared | 7/8/2020 | STEPHEN DUPREY |
| Low Impact Development | Cleared | 7/23/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/24/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Eden,, Joseph Taki; Lic. No.: C39955 | 14412 FRIAR ST VAN NUYS, CA 91401 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/24/2020 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 8/26/2020 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 8/28/2020 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Underground Mechanical | 10/8/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 10/13/2020 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 10/13/2020 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 10/14/2020 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/15/2020 | Approved | THOMAS FINNILA |
| HVAC-Rough | 10/15/2020 | Partial Inspection | THOMAS FINNILA |
| Shower Pan | 10/16/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/19/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 10/19/2020 | Approved | THOMAS FINNILA |
| Insulation | 10/20/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 10/21/2020 | Approved | MICHAEL SMITH |
| BUILDING-Rough-Frame | 10/23/2020 | Approved | THOMAS FINNILA |
| Drywall Nailing | 10/23/2020 | Approved | THOMAS FINNILA |
| Green Building Rough | 10/23/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/29/2020 | Not Ready for Inspection | BEAU COLLINS |
| Interior/Exterior Lathing | 11/16/2020 | Approved | THOMAS FINNILA |
| Gas Test | 12/1/2020 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 12/4/2020 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 12/4/2020 | Approved | THOMAS FINNILA |
| HVAC-Final | 12/21/2020 | Corrections Issued | THOMAS FINNILA |
| Final | 6/1/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/1/2021 | Approved | THOMAS FINNILA |
| Green Building Final | 6/1/2021 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 6/1/2021 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 6/1/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 6/2/2021 | Partial Approval | THOMAS FINNILA |
| Green Building Final | 6/2/2021 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 6/2/2021 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 6/2/2021 | Approved | THOMAS FINNILA |
| Final | 7/1/2021 | OK to Issue CofO | THOMAS FINNILA |
| Service/Power Release | 7/1/2021 | Approved | THOMAS FINNILA |