360 N FULLER AVE 90036

Certificate Information: 360 N FULLER AVE 90036

Application / Permit
20010-20000-00308
Plan Check / Job No.
B20VN01500
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW DETACHED GARAGE WITH ATTACHED TRELLIS
Permit Issued
Issued on 11/5/2021
Issuing Office
Current Status
Issued on 11/5/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/29/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 AMIR DANAI
Corrections Issued 3/12/2020 AMIR DANAI
Quality Review Completed 3/25/2020 ARMEN JIVALAGIAN
Building Plans Picked Up 4/9/2020 APPLICANT
Green Plans Picked Up 4/27/2020 APPLICANT
Applicant returned to address corrections 11/19/2020 AMIR DANAI
Plan Check Approved 12/8/2020 AMIR DANAI
No Progress 6/15/2021 MONICA RAMIREZ
Plan Check Approved 10/28/2021 MONICA RAMIREZ
Issued 11/5/2021 APPLICANT

Permit Application Clearance Information

Construction within easement Cleared 4/27/2020 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 5/4/2020 EMIL KYUPELYAN
Abandoned oil well Cleared 6/3/2020 KURT CORRAL
Abandoned oil well approval Cleared 6/3/2020 KURT CORRAL
Hydrant and Access approval Cleared 6/3/2020 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 9/14/2020 CELINA MORENO
Green Code Cleared 10/22/2020 MICHAEL AYERS

Contact Information

Contractor Aspen Construction And Development Inc; Lic. No.: 827956-B P O BOX 48146      LOS ANGELES, CA 900480146
Engineer Jahani,, Fereidoun; Lic. No.: C62875 3720 BLANCHE ST      PASADENA, CA 91107
Engineer Mansuri,, Mehran; Lic. No.: C78614 14944 HESBY ST      SHERMAN OAKS, CA 91403
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803
Geologist Minas,, Shant; Lic. No.: GEO8859 566 RIVERDALE DRIVE      GLENDALE, CA 91204

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 3/7/2022 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/25/2022 Corrections Issued JOSEPH MCGARRY
METHANE-Barrier 7/25/2022 Not Ready for Inspection JOSEPH MCGARRY
METHANE-Subgrade 7/25/2022 Not Ready for Inspection JOSEPH MCGARRY
METHANE-Subgrade 8/1/2022 Approved JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 8/5/2022 Conditional Approval JOSEPH MCGARRY
METHANE-Barrier 8/5/2022 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 9/22/2022 Partial Approval MICHAEL LEWIS
Wood Frame 9/30/2022 Approved MICHAEL LEWIS
Wood Frame 10/7/2022 Partial Inspection MICHAEL LEWIS
METHANE-Rough 10/19/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 10/26/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/6/2022 Approved MICHAEL LEWIS
Final 12/6/2022 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 12/6/2022 Approved MICHAEL LEWIS
Green Building Final 12/6/2022 Approved MICHAEL LEWIS
Green Building Rough 12/6/2022 Approved MICHAEL LEWIS
METHANE-Final 12/6/2022 Approved MICHAEL LEWIS
METHANE-Rough 12/6/2022 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Approved MICHAEL LEWIS
Service/Power Release 12/6/2022 Approved MICHAEL LEWIS
Smoke Detectors 12/6/2022 Approved MICHAEL LEWIS
ELECTRICAL-Rough 3/29/2024 Partial Inspection AMIR NAZARIAN
PLUMBING-Rough 3/29/2024 Corrections Issued AMIR NAZARIAN
Final 6/20/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 6/20/2024 Not Ready for Inspection AMIR NAZARIAN
Wood Frame 5/19/2025 Corrections Issued JOSE MACIAS
Final 3/17/2026 Not Ready for Inspection JOSH MEISTER
Final 3/25/2026 Not Ready for Inspection JOSH MEISTER
Service/Power Release 3/25/2026 Not Ready for Inspection JOSH MEISTER