15334 W ARCHWOOD ST 91406
Certificate Information: 15334 W ARCHWOOD ST 91406
- Application / Permit
- 20010-20000-00299
- Plan Check / Job No.
- B20VN01455
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED DETACHED ACCESSORY DWELLING UNIT AT REAR OF THE LOT PER WOOD FRAME PRESCRIPTIVE PROVISION (1200 SF MAX PER ORDINANCE)
- Permit Issued
- Issued on 8/14/2020
- Issuing Office
- Current Status
- CofO Issued on 7/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2020 | APPLICANT |
| Green Plans Picked Up | 2/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | AUNG SOE |
| Corrections Issued | 3/9/2020 | AUNG SOE |
| Quality Review Completed | 3/10/2020 | QUAN NGHIEM |
| Applicant returned to address corrections | 7/23/2020 | AUNG SOE |
| Building Plans Picked Up | 7/28/2020 | APPLICANT |
| Plan Check Approved | 8/4/2020 | AUNG SOE |
| Issued | 8/14/2020 | APPLICANT |
| CofO in Progress | 7/6/2021 | MICHAEL TEMPLE |
| Permit Finaled | 7/10/2021 | MICHAEL SMITH |
| CofO Issued | 7/10/2021 | MICHAEL SMITH |
| Permit Finaled | 7/10/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2020 | JOHN TRIANTAFYLLOS |
| Certificate of Compliance | Cleared | 3/17/2020 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/17/2020 | JOHN TRIANTAFYLLOS |
| ZI | Cleared | 3/17/2020 | MIGUEL GAMBOA |
| Green Code | Cleared | 3/25/2020 | AARON COSTA |
| Hydrant and Access approval | Cleared | 5/14/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 7/2/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/30/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/17/2020 | Corrections Issued | MICHAEL TEMPLE |
| PLUMBING-Rough | 8/17/2020 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 8/28/2020 | Corrections Issued | WILLIAM KUEHN |
| Footing/Foundation/Slab | 9/3/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 9/8/2020 | No Access for Inspection | DAVID MATSON |
| Footing/Foundation/Slab | 9/15/2020 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 9/15/2020 | Partial Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2020 | Partial Inspection | WILLIAM KUEHN |
| Green Building Rough | 9/24/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 9/24/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 9/30/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 9/30/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 9/30/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 9/30/2020 | Partial Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 9/30/2020 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 9/30/2020 | Approved | WILLIAM KUEHN |
| Insulation | 10/2/2020 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 10/6/2020 | Approved | WILLIAM KUEHN |
| Shower Pan | 10/6/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 10/9/2020 | Partial Inspection | WILLIAM KUEHN |
| Final | 12/24/2020 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 12/24/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 12/24/2020 | SGSOV Not Ready | MICHAEL TEMPLE |
| Service/Power Release | 12/24/2020 | Corrections Issued | MICHAEL TEMPLE |
| Smoke Detectors | 12/24/2020 | Approved | MICHAEL TEMPLE |
| Final | 12/29/2020 | Partial Approval | ARTHUR SARGSYAN |
| Gas Test | 12/29/2020 | Approved | ARTHUR SARGSYAN |
| Green Building Final | 12/29/2020 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 12/29/2020 | SGSOV Approved | ARTHUR SARGSYAN |
| Service/Power Release | 12/29/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 2/26/2021 | Partial Inspection | MICHAEL TEMPLE |
| Special/Order Compliance | 3/4/2021 | Corrections Issued | MICHAEL TEMPLE |
| Final | 7/6/2021 | OK to Issue CofO | MICHAEL TEMPLE |
| Service/Power Release | 7/6/2021 | Approved | MICHAEL TEMPLE |
| Service/Power Release | 7/7/2021 | No Access for Inspection | CHRISTOPHE COCHRAN |