8358 N OSO AVE 91306
Certificate Information: 8358 N OSO AVE 91306
- Application / Permit
- 20010-20000-00251
- Plan Check / Job No.
- B20VN01207
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 51'-4 1/4" X 27' - 8 1/2" ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 9/22/2020
- Issuing Office
- Current Status
- CofO Issued on 11/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2020 | APPLICANT |
| Green Plans Picked Up | 2/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 3/13/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 3/17/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 3/17/2020 | APPLICANT |
| Plan Check Approved | 9/15/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 9/22/2020 | APPLICANT |
| CofO in Progress | 11/20/2021 | DAVID STEPANYAN |
| Permit Finaled | 11/22/2021 | MICHAEL SMITH |
| CofO Issued | 11/22/2021 | MICHAEL SMITH |
| Permit Finaled | 11/22/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/10/2020 | KATHLEEN HUGHEY |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 4/14/2020 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 7/21/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 8/19/2020 | ROBIN YAMADA |
| Green Code | Cleared | 8/27/2020 | AARON COSTA |
| Roof/Waste drainage to street | Cleared | 8/27/2020 | KATHLEEN LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/23/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 10/23/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 10/29/2020 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2020 | Approved | DAVID STEPANYAN |
| Footing/Foundation/Slab | 11/19/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 12/10/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 12/10/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 12/10/2020 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Rough | 12/10/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 12/10/2020 | Approved | DAVID STEPANYAN |
| Shower Pan | 12/10/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Verify Sprinkler Sign Off | 12/10/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 12/17/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 12/17/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 12/17/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 12/17/2020 | Approved | DAVID STEPANYAN |
| Shower Pan | 12/17/2020 | Approved | DAVID STEPANYAN |
| Insulation | 12/21/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 12/28/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 12/28/2020 | Partial Approval | DAVID STEPANYAN |
| Interior/Exterior Lathing | 12/30/2020 | Approved | MARK JOHNSON |
| Gas Test | 1/19/2021 | Approved | TROY SANDERS |
| Sewer | 1/19/2021 | Approved | TROY SANDERS |
| Green Building Final | 7/15/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Final | 11/19/2021 | Approved | DAVID STEPANYAN |
| Final | 11/19/2021 | OK to Issue CofO | DAVID STEPANYAN |
| Green Building Final | 11/19/2021 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 11/19/2021 | SGSOV Approved | DAVID STEPANYAN |
| Service/Power Release | 11/19/2021 | Approved | DAVID STEPANYAN |
| Smoke Detectors | 11/19/2021 | Approved | DAVID STEPANYAN |