18010 W ROSITA ST 91316

Certificate Information: 18010 W ROSITA ST 91316

Application / Permit
20010-20000-00244
Plan Check / Job No.
B20VN01194
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILLY DWELLING.
Permit Issued
Issued on 7/23/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2020 APPLICANT
Green Plans Picked Up 2/21/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 RACHEL BEYENE
Corrections Issued 3/9/2020 RACHEL BEYENE
Quality Review Completed 3/14/2020 STANLEY RAAP
Building Plans Picked Up 3/16/2020 APPLICANT
Applicant returned to address corrections 7/15/2020 RACHEL BEYENE
Plan Check Approved 7/17/2020 RAHEL BEYENE
Issued 7/23/2020 APPLICANT
CofO in Progress 12/7/2021 DAVID SANDOVAL
CofO Issued 12/8/2021 MICHAEL SMITH
Permit Finaled 12/8/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/18/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 5/18/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 5/26/2020 DAVID MATSON
Hydrant and Access approval Cleared 6/8/2020 MATTHEW CRAIG
Low Impact Development Cleared 6/24/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 7/6/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 7/17/2020 RAHEL BEYENE

Contact Information

Contractor Owner-Builder       ,
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406
Engineer Yadegari,, Shahriar; Lic. No.: C64591 267 S SAN PEDRO ST 124      LOS ANGELES, CA 90012

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/28/2020 Not Ready for Inspection DAVID SANDOVAL
Pre-Inspection 7/28/2020 Not Ready for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 9/24/2020 Partial Approval SEAN WIRCH
Underground Mechanical 9/24/2020 Corrections Issued SEAN WIRCH
Underground Mechanical 9/28/2020 Approved DAVID SANDOVAL
Footing/Foundation/Slab 9/30/2020 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 10/2/2020 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 10/8/2020 Approved RONALD COWAN
Deputy Steel/Welding 10/23/2020 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 Partial Approval STEVEN BACK
Deputy Wood Construction 10/28/2020 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 11/5/2020 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 11/5/2020 Corrections Issued HENRY KIM
Green Building Rough 11/5/2020 Not Ready for Inspection HENRY KIM
Verify Sprinkler Sign Off 11/5/2020 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 12/3/2020 Approved RONALD COWAN
HVAC-Rough 1/7/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 1/20/2021 Approved DAVID SANDOVAL
ELECTRICAL-Rough 2/8/2021 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 2/17/2021 Approved DAVID SANDOVAL
Insulation 2/17/2021 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 3/15/2021 Approved DAVID SANDOVAL
Green Building Rough 3/15/2021 Approved DAVID SANDOVAL
Insulation 3/15/2021 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 3/15/2021 Approved DAVID SANDOVAL
Drywall Nailing 3/22/2021 Approved DAVID SANDOVAL
Interior/Exterior Lathing 3/22/2021 Partial Approval DAVID SANDOVAL
Shower Pan 4/12/2021 Corrections Issued DAVID SANDOVAL
Interior/Exterior Lathing 4/13/2021 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 4/19/2021 Approved DAVID SANDOVAL
Shower Pan 4/19/2021 Approved DAVID SANDOVAL
Shower Pan 7/26/2021 Not Ready for Inspection DAVID SANDOVAL
Underground Mechanical 7/26/2021 Corrections Issued DAVID SANDOVAL
Underground Mechanical 7/28/2021 Partial Approval DAVID SANDOVAL
Shower Pan 8/2/2021 Approved DAVID SANDOVAL
Final 9/28/2021 Not Ready for Inspection DAVID SANDOVAL
Green Building Final 9/28/2021 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 9/28/2021 SGSOV Not Ready DAVID SANDOVAL
Service/Power Release 9/28/2021 Not Ready for Inspection DAVID SANDOVAL
Smoke Detectors 9/28/2021 Not Ready for Inspection DAVID SANDOVAL
Gas Test 10/21/2021 Approved DAVID SANDOVAL
HVAC-Final 10/21/2021 Approved DAVID SANDOVAL
PLUMBING-Final 10/21/2021 Approved DAVID SANDOVAL
ELECTRICAL-Final 10/28/2021 Approved DAVID SANDOVAL
Final 11/19/2021 Corrections Issued DAVID SANDOVAL
Green Building Final 11/19/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 11/19/2021 SGSOV Approved DAVID SANDOVAL
Service/Power Release 11/19/2021 Approved DAVID SANDOVAL
Smoke Detectors 11/19/2021 Approved DAVID SANDOVAL
Final 12/7/2021 OK to Issue CofO DAVID SANDOVAL