18010 W ROSITA ST 91316
Certificate Information: 18010 W ROSITA ST 91316
- Application / Permit
- 20010-20000-00244
- Plan Check / Job No.
- B20VN01194
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILLY DWELLING.
- Permit Issued
- Issued on 7/23/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2020 | APPLICANT |
| Green Plans Picked Up | 2/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | RACHEL BEYENE |
| Corrections Issued | 3/9/2020 | RACHEL BEYENE |
| Quality Review Completed | 3/14/2020 | STANLEY RAAP |
| Building Plans Picked Up | 3/16/2020 | APPLICANT |
| Applicant returned to address corrections | 7/15/2020 | RACHEL BEYENE |
| Plan Check Approved | 7/17/2020 | RAHEL BEYENE |
| Issued | 7/23/2020 | APPLICANT |
| CofO in Progress | 12/7/2021 | DAVID SANDOVAL |
| CofO Issued | 12/8/2021 | MICHAEL SMITH |
| Permit Finaled | 12/8/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 5/18/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 5/26/2020 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 6/8/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/24/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/6/2020 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 7/17/2020 | RAHEL BEYENE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
| Engineer | Yadegari,, Shahriar; Lic. No.: C64591 | 267 S SAN PEDRO ST 124 LOS ANGELES, CA 90012 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/28/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Pre-Inspection | 7/28/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 9/24/2020 | Partial Approval | SEAN WIRCH |
| Underground Mechanical | 9/24/2020 | Corrections Issued | SEAN WIRCH |
| Underground Mechanical | 9/28/2020 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 9/30/2020 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/2/2020 | Partial Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/8/2020 | Approved | RONALD COWAN |
| Deputy Steel/Welding | 10/23/2020 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2020 | Partial Approval | STEVEN BACK |
| Deputy Wood Construction | 10/28/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 11/5/2020 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2020 | Corrections Issued | HENRY KIM |
| Green Building Rough | 11/5/2020 | Not Ready for Inspection | HENRY KIM |
| Verify Sprinkler Sign Off | 11/5/2020 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2020 | Approved | RONALD COWAN |
| HVAC-Rough | 1/7/2021 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 1/20/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 2/8/2021 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2021 | Approved | DAVID SANDOVAL |
| Insulation | 2/17/2021 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 3/15/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 3/15/2021 | Approved | DAVID SANDOVAL |
| Insulation | 3/15/2021 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 3/15/2021 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 3/22/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 3/22/2021 | Partial Approval | DAVID SANDOVAL |
| Shower Pan | 4/12/2021 | Corrections Issued | DAVID SANDOVAL |
| Interior/Exterior Lathing | 4/13/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Interior/Exterior Lathing | 4/19/2021 | Approved | DAVID SANDOVAL |
| Shower Pan | 4/19/2021 | Approved | DAVID SANDOVAL |
| Shower Pan | 7/26/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Underground Mechanical | 7/26/2021 | Corrections Issued | DAVID SANDOVAL |
| Underground Mechanical | 7/28/2021 | Partial Approval | DAVID SANDOVAL |
| Shower Pan | 8/2/2021 | Approved | DAVID SANDOVAL |
| Final | 9/28/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Final | 9/28/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 9/28/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| Service/Power Release | 9/28/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Smoke Detectors | 9/28/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Gas Test | 10/21/2021 | Approved | DAVID SANDOVAL |
| HVAC-Final | 10/21/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 10/21/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 10/28/2021 | Approved | DAVID SANDOVAL |
| Final | 11/19/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 11/19/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 11/19/2021 | SGSOV Approved | DAVID SANDOVAL |
| Service/Power Release | 11/19/2021 | Approved | DAVID SANDOVAL |
| Smoke Detectors | 11/19/2021 | Approved | DAVID SANDOVAL |
| Final | 12/7/2021 | OK to Issue CofO | DAVID SANDOVAL |