15820 W ROYAL OAK ROAD 91436

Certificate Information: 15820 W ROYAL OAK ROAD 91436

Application / Permit
20010-20000-00241
Plan Check / Job No.
B20VN01160
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (67' X 145'-11") IRREGULA SHAPED 2-STORY SFD W/ 3-CAR GARAGE. NFPA 13D SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 1/15/2021
Issuing Office
Valley
Current Status
CofO Issued on 1/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2020 APPLICANT
Green Plans Picked Up 2/6/2020 APPLICANT
Assigned to Plan Check Engineer 2/14/2020 RAPHAEL ROSAS
Corrections Issued 2/18/2020 RAPHAEL ROSAS
Quality Review Completed 3/6/2020 CHON CHIO KUO
Building Plans Picked Up 3/9/2020 APPLICANT
Applicant returned to address corrections 10/6/2020 RAPHAEL ROSAS
Plan Check Approved 11/23/2020 RAPHAEL ROSAS
Issued 1/15/2021 APPLICANT
CofO in Progress 1/10/2024 VINCENT HANLEY
Permit Finaled 1/30/2024 JOHN JANSON
CofO Issued 1/30/2024 JOHN JANSON
Permit Finaled 1/30/2024 JOHN JANSON

Permit Application Clearance Information

Trees in Parkway Cleared 2/28/2020 ADRIAN SANCHEZ
Address approval Cleared 3/5/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 3/5/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 3/5/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 3/5/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/5/2020 ADRIAN CASTRO
Permit Cleared 3/5/2020 ADRIAN CASTRO
Sewer availability Cleared 3/5/2020 ADRIAN CASTRO
Distance to fire station Cleared 5/13/2020 KURT CORRAL
Hydrant and Access approval Cleared 5/13/2020 KURT CORRAL
Low Impact Development Cleared 6/17/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/22/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 6/25/2020 MICHAEL AYERS
Certificate of Compliance Cleared 8/4/2020 SHEILA GERSHON
GPI Written Notices Cleared 11/13/2020 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 11/13/2020 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Vidal,, Juan Alonso; Lic. No.: GE861 7438 SHIRLEY AVE      RESEDA, CA 91335
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302
Geologist Bovenizer,, Ernest; Lic. No.: EG2515 7622 GODDARD AVENUE      LOS ANGELES, CA 90045

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/9/2021 Approved RONALD COWAN
Deputy Reinf. Concrete 7/9/2021 Approved RONALD COWAN
Footing/Foundation/Slab 7/9/2021 Approved RONALD COWAN
Deputy Steel/Welding 7/26/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Partial Approval RONALD COWAN
PLUMBING-Rough 11/5/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 12/9/2021 No Access for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Partial Approval DAVID SANDOVAL
HVAC-Rough 12/16/2021 Approved SEAN HAUPT
ELECTRICAL-Rough 3/17/2022 Approved PETER FOLLING
Deputy Wood Construction 5/3/2022 Conditional Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Approved PETER FOLLING
Green Building Rough 5/5/2022 Not Ready for Inspection PETER FOLLING
Shower Pan 5/5/2022 Not Ready for Inspection PETER FOLLING
Verify Sprinkler Sign Off 5/5/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 5/10/2022 Approved PETER FOLLING
Green Building Rough 5/10/2022 Approved PETER FOLLING
Interior/Exterior Lathing 5/10/2022 Partial Approval PETER FOLLING
Verify Sprinkler Sign Off 5/10/2022 Approved PETER FOLLING
Insulation 5/18/2022 Approved ROBERT GOLD
Interior/Exterior Lathing 5/18/2022 Approved ROBERT GOLD
Shower Pan 5/18/2022 Approved ROBERT GOLD
Drywall Nailing 6/9/2022 Approved MORRIS JACKSON
ELECTRICAL-Final 6/12/2023 Partial Approval VINCENT HANLEY
Final 6/12/2023 Corrections Issued VINCENT HANLEY
Green Building Final 6/12/2023 Approved VINCENT HANLEY
HVAC-Final 6/12/2023 Corrections Issued VINCENT HANLEY
PLUMBING-Final 6/12/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/12/2023 SGSOV Approved VINCENT HANLEY
Service/Power Release 6/12/2023 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 6/12/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 No Access for Inspection VINCENT HANLEY
Service/Power Release 10/11/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 1/3/2024 Approved VINCENT HANLEY
Final 1/3/2024 Partial Approval VINCENT HANLEY
Green Building Final 1/3/2024 Approved VINCENT HANLEY
Green Building Rough 1/3/2024 Approved VINCENT HANLEY
HVAC-Final 1/3/2024 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 1/3/2024 Approved VINCENT HANLEY
Final 1/10/2024 OK to Issue CofO VINCENT HANLEY