15820 W ROYAL OAK ROAD 91436
Certificate Information: 15820 W ROYAL OAK ROAD 91436
- Application / Permit
- 20010-20000-00241
- Plan Check / Job No.
- B20VN01160
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (67' X 145'-11") IRREGULA SHAPED 2-STORY SFD W/ 3-CAR GARAGE. NFPA 13D SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 1/15/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2020 | APPLICANT |
| Green Plans Picked Up | 2/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2020 | RAPHAEL ROSAS |
| Corrections Issued | 2/18/2020 | RAPHAEL ROSAS |
| Quality Review Completed | 3/6/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/9/2020 | APPLICANT |
| Applicant returned to address corrections | 10/6/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 11/23/2020 | RAPHAEL ROSAS |
| Issued | 1/15/2021 | APPLICANT |
| CofO in Progress | 1/10/2024 | VINCENT HANLEY |
| Permit Finaled | 1/30/2024 | JOHN JANSON |
| CofO Issued | 1/30/2024 | JOHN JANSON |
| Permit Finaled | 1/30/2024 | JOHN JANSON |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 2/28/2020 | ADRIAN SANCHEZ |
| Address approval | Cleared | 3/5/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 3/5/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 3/5/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 3/5/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2020 | ADRIAN CASTRO |
| Permit | Cleared | 3/5/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/5/2020 | ADRIAN CASTRO |
| Distance to fire station | Cleared | 5/13/2020 | KURT CORRAL |
| Hydrant and Access approval | Cleared | 5/13/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 6/17/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/22/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 6/25/2020 | MICHAEL AYERS |
| Certificate of Compliance | Cleared | 8/4/2020 | SHEILA GERSHON |
| GPI Written Notices | Cleared | 11/13/2020 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 11/13/2020 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
| Geologist | Bovenizer,, Ernest; Lic. No.: EG2515 | 7622 GODDARD AVENUE LOS ANGELES, CA 90045 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/9/2021 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 7/9/2021 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 7/9/2021 | Approved | RONALD COWAN |
| Deputy Steel/Welding | 7/26/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2021 | Partial Approval | RONALD COWAN |
| PLUMBING-Rough | 11/5/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2021 | No Access for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2021 | Partial Approval | DAVID SANDOVAL |
| HVAC-Rough | 12/16/2021 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 3/17/2022 | Approved | PETER FOLLING |
| Deputy Wood Construction | 5/3/2022 | Conditional Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Approved | PETER FOLLING |
| Green Building Rough | 5/5/2022 | Not Ready for Inspection | PETER FOLLING |
| Shower Pan | 5/5/2022 | Not Ready for Inspection | PETER FOLLING |
| Verify Sprinkler Sign Off | 5/5/2022 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 5/10/2022 | Approved | PETER FOLLING |
| Green Building Rough | 5/10/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 5/10/2022 | Partial Approval | PETER FOLLING |
| Verify Sprinkler Sign Off | 5/10/2022 | Approved | PETER FOLLING |
| Insulation | 5/18/2022 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 5/18/2022 | Approved | ROBERT GOLD |
| Shower Pan | 5/18/2022 | Approved | ROBERT GOLD |
| Drywall Nailing | 6/9/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 6/12/2023 | Partial Approval | VINCENT HANLEY |
| Final | 6/12/2023 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 6/12/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 6/12/2023 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 6/12/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 6/12/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Smoke Detectors | 6/12/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2023 | No Access for Inspection | VINCENT HANLEY |
| Service/Power Release | 10/11/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 1/3/2024 | Approved | VINCENT HANLEY |
| Final | 1/3/2024 | Partial Approval | VINCENT HANLEY |
| Green Building Final | 1/3/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/3/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 1/3/2024 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 1/3/2024 | Approved | VINCENT HANLEY |
| Final | 1/10/2024 | OK to Issue CofO | VINCENT HANLEY |