10953 W ELINDA PL 91352
Certificate Information: 10953 W ELINDA PL 91352
- Application / Permit
- 20010-20000-00237
- Plan Check / Job No.
- B20VN01134
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 43'-7" x 34'-3" IRREGULAR SHAPED DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); AUTOMATIC SPRINKLER SYSTEM IS REQUIRED.
- Permit Issued
- Issued on 6/21/2021
- Issuing Office
- Current Status
- CofO Issued on 1/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2020 | APPLICANT |
| Green Plans Picked Up | 2/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | SEAN SHAHMIRI |
| Corrections Issued | 3/9/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 3/12/2020 | STEVEN KIM |
| Building Plans Picked Up | 3/16/2020 | APPLICANT |
| Applicant returned to address corrections | 11/23/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 2/3/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 2/26/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 3/19/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 6/14/2021 | SEAN SHAHMIRI |
| Issued | 6/21/2021 | APPLICANT |
| CofO in Progress | 11/24/2022 | DAVID ANDERSON |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
| CofO Issued | 1/14/2023 | MICHAEL SMITH |
| Permit Finaled | 1/14/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| ZI | Cleared | 7/7/2020 | VINCENT QUITORIANO |
| Address approval | Cleared | 7/23/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/23/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 8/7/2020 | AARON COSTA |
| ZI | Cleared | 8/12/2020 | PEGGY MALONE-BROWN |
| Hydrant and Access approval | Cleared | 9/16/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/20/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/27/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Urbane Builders Inc; Lic. No.: 1046293-B | 8619 RESEDA BLVD STE 304B NORTHRIDGE, CA 91324 |
| Engineer | Azarbin,, Hamid Reza; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/28/2021 | Partial Inspection | WILLIAM KUEHN |
| Excavation/Setback/Form/Re-Bar | 8/9/2021 | Approved | WILLIAM KUEHN |
| Footing/Foundation/Slab | 8/9/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| METHANE-Barrier | 8/9/2021 | Approved | WILLIAM KUEHN |
| METHANE-Subgrade | 8/9/2021 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 9/20/2021 | Partial Inspection | WILLIAM KUEHN |
| Sewer | 9/20/2021 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2021 | Partial Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 1/11/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 1/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 1/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 1/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| METHANE-Rough | 1/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 1/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Wood Frame | 1/11/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 1/24/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 1/24/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 1/24/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 1/24/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 1/24/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/31/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 2/3/2022 | Corrections Issued | WILLIAM WREN |
| Insulation | 2/7/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 2/14/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/21/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 11/14/2022 | Corrections Issued | DAVID ANDERSON |
| Final | 11/14/2022 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/14/2022 | Approved | DAVID ANDERSON |
| Green Building Final | 11/14/2022 | Approved | DAVID ANDERSON |
| HVAC-Final | 11/14/2022 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Final | 11/14/2022 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 11/14/2022 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 11/14/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 11/14/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 11/23/2022 | Approved | DAVID ANDERSON |
| Final | 11/23/2022 | OK to Issue CofO | DAVID ANDERSON |
| HVAC-Final | 11/23/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 11/23/2022 | Approved | DAVID ANDERSON |
| Service/Power Release | 11/23/2022 | Approved | DAVID ANDERSON |