12731 W BLOOMFIELD ST 91604

Certificate Information: 12731 W BLOOMFIELD ST 91604

Application / Permit
20010-20000-00233
Plan Check / Job No.
B20VN01122
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 87' 6" X 42' 6" 2-STORY IRR.-SHAPED 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 21' 6" X 20' 2-CAR GARAGE AND 18' 6" X 8' 5" IRR.-SHAPED PATIO COVER. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 4/30/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2020 APPLICANT
Green Plans Picked Up 2/6/2020 APPLICANT
Assigned to Plan Check Engineer 2/14/2020 GURUNATH NESARAJAH
Corrections Issued 2/16/2020 GURUNATH NESARAJAH
Quality Review Completed 2/21/2020 GUANG MIN TUNG
Building Plans Picked Up 3/5/2020 APPLICANT
Plan Check Approved 3/20/2020 GURUNATH NESARAJAH
Issued 4/30/2020 LADBS
CofO in Progress 12/30/2020 ARAM AVEDISIAN
Permit Finaled 2/9/2021 MICHAEL SMITH
CofO Issued 2/9/2021 MICHAEL SMITH
Permit Finaled 2/9/2021 MICHAEL SMITH

Permit Application Clearance Information

Trees in Parkway Cleared 2/28/2020 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 3/2/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 3/2/2020 GEORGE SUCHAND
Permit Cleared 3/2/2020 LEE GUILBEAUX
Sewer availability Cleared 3/2/2020 LEE GUILBEAUX
Green Code Cleared 3/10/2020 MICHAEL AYERS
ZI Cleared 4/3/2020 LAUREN PADICK
Low Impact Development Cleared 4/7/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/8/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/27/2020 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 5/29/2020 Approved TROY SANDERS
Excavation/Setback/Form/Re-Bar 6/5/2020 Approved ARAM AVEDISIAN
Structural Steel Frame 6/5/2020 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Approval BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 7/27/2020 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 7/31/2020 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/31/2020 Approved ARAM AVEDISIAN
HVAC-Rough 7/31/2020 Approved ARAM AVEDISIAN
PLUMBING-Rough 7/31/2020 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 8/10/2020 Approved DANIEL DREW
Green Building Rough 8/10/2020 Approved DANIEL DREW
Verify Sprinkler Sign Off 8/10/2020 Approved DANIEL DREW
Shower Pan 8/13/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 8/18/2020 Partial Approval KATHRYN BUTTERWORTH
Insulation 8/20/2020 Approved CHARLES POWELL
Interior/Exterior Lathing 8/20/2020 Approved CHARLES POWELL
Drywall Nailing 8/31/2020 Not Ready for Inspection ARAM AVEDISIAN
Drywall Nailing 9/2/2020 Approved ARAM AVEDISIAN
Gas Test 11/24/2020 Approved ARAM AVEDISIAN
ELECTRICAL-Final 12/11/2020 Approved ARAM AVEDISIAN
Final 12/11/2020 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 12/11/2020 Approved ARAM AVEDISIAN
Green Building Final 12/11/2020 Approved ARAM AVEDISIAN
HVAC-Final 12/11/2020 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Final 12/11/2020 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 12/11/2020 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 12/11/2020 Approved ARAM AVEDISIAN
Smoke Detectors 12/11/2020 Approved ARAM AVEDISIAN
Final 12/30/2020 OK to Issue CofO ARAM AVEDISIAN