20122 W VANOWEN ST 91306

Certificate Information: 20122 W VANOWEN ST 91306

Application / Permit
20010-20000-00225
Plan Check / Job No.
B20VN01037
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(7) Garage - Private
Work Description
(N) (30' X 86') 7-CAR PRIVATE GARAGE AS REQ'D PARKING SPACES FOR SITE, AND RESTRIPE PARKING LOT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 10/7/2020
Issuing Office
Current Status
CofO Issued on 3/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 ABDUL CHEGENI
Disabled Access Plans Picked Up 3/11/2020 APPLICANT
Green Plans Picked Up 3/11/2020 APPLICANT
Corrections Issued 3/23/2020 ABDUL CHEGENI
Quality Review Completed 3/26/2020 STEVEN KIM
Building Plans Picked Up 3/27/2020 APPLICANT
Applicant returned to address corrections 6/24/2020 RARES BODEA
Applicant returned to address corrections 8/18/2020 RARES BODEA
Plan Check Approved 10/5/2020 RARES BODEA
Issued 10/7/2020 APPLICANT
CofO in Progress 2/23/2024 CAMERON CHABAN
Permit Finaled 3/19/2024 RICKEY JACKSON
CofO Issued 3/19/2024 RICKEY JACKSON
Permit Finaled 3/19/2024 RICKEY JACKSON

Permit Application Clearance Information

Construction near power lines Cleared 4/5/2020 RIDWAN HARDY
Construction within easement Cleared 4/5/2020 RIDWAN HARDY
Green Code Cleared 5/27/2020 MICHAEL AYERS
DAS Clearance Cleared 6/25/2020 ABDUL CHEGENI
"Q" conditions Cleared 7/14/2020 LAUREN PADICK
"T" removal Cleared 7/14/2020 LAUREN PADICK
Low Impact Development Cleared 7/14/2020 ANDRES COVARRUBIAS
ZA Case Cleared 7/14/2020 LAUREN PADICK
Address approval Cleared 7/20/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/20/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/20/2020 LEE GUILBEAUX
Comm Cor/Mini-Mall Cleared 7/28/2020 LAUREN PADICK
ZI Cleared 7/28/2020 LAUREN PADICK
Automotive Use Cleared 8/21/2020 LAUREN PADICK
Comm Cor/Mini-Mall Cleared 8/21/2020 LAUREN PADICK

Contact Information

Contractor Gelb Enterprises; Lic. No.: 493783-B 6200 CANOGA AVE # 201      WOODLAND HILLS, CA 91367
Engineer Canterberry,, Larry Glen; Lic. No.: L8776 5210 MOLISE COURT      BAKERSFIELD, CA 93308
Engineer Dermendjian,, Raffi Hrag; Lic. No.: C88261 9325 SHOSHONE AVENUE      NORTHRIDGE, CA 91325
Engineer Mayer,, Robert; Lic. No.: S1991 5109 BELLAIRE AVENUE      N HOLLYWOOD, CA 91607
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/14/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/26/2020 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 10/28/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 11/2/2020 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 11/4/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 11/5/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 11/6/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 11/9/2020 Approved HAMID PISHEHVAR
Masonry Wall/Backfill 11/10/2020 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Masonry 11/12/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 11/13/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 11/17/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 11/19/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 11/20/2020 Approved HAMID PISHEHVAR
Masonry Wall/Backfill 11/20/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 11/24/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 11/25/2020 Approved JOHN KITCKO
Masonry Wall/Backfill 12/3/2020 Partial Approval HAMID PISHEHVAR
Deputy Wood Construction 1/7/2021 Approved ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Approved ROBERT DAVIS
Green Building Rough 1/7/2021 Approved ROBERT DAVIS
Wood Frame 1/7/2021 Approved ROBERT DAVIS
Interior/Exterior Lathing 1/26/2021 Approved CAMERON CHABAN
Deputy Steel/Welding 1/28/2021 Conditional Approval CAMERON CHABAN
Drywall Nailing 7/9/2021 Approved CAMERON CHABAN
Final 7/9/2021 Partial Inspection CAMERON CHABAN
Footing/Foundation/Slab 7/9/2021 Approved CAMERON CHABAN
Green Building Final 7/9/2021 Not Ready for Inspection CAMERON CHABAN
Reinforced Masonry Frame 7/9/2021 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 7/9/2021 SGSOV Not Ready CAMERON CHABAN
Smoke Detectors 7/9/2021 Approved CAMERON CHABAN
Structural Steel Frame 7/9/2021 Partial Inspection CAMERON CHABAN
Final 1/21/2022 Partial Inspection CAMERON CHABAN
Green Building Final 1/21/2022 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 1/21/2022 SGSOV Approved CAMERON CHABAN
Structural Steel Frame 1/21/2022 Approved CAMERON CHABAN
Final 2/21/2023 Partial Inspection CAMERON CHABAN
Green Building Final 2/21/2023 Partial Inspection CAMERON CHABAN
Final 3/6/2023 Conditional Approval CAMERON CHABAN
Green Building Final 3/6/2023 Approved CAMERON CHABAN
Final 3/8/2023 Conditional Approval CAMERON CHABAN
Final 2/23/2024 OK to Issue CofO CAMERON CHABAN