16102 W SEPTO ST 91343
Certificate Information: 16102 W SEPTO ST 91343
- Application / Permit
- 20010-20000-00215
- Plan Check / Job No.
- B20VN00961
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (20'-0"x 32'-8") DETACHED 2 STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 3/2/2021
- Issuing Office
- Current Status
- CofO Issued on 10/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2020 | APPLICANT |
| Green Plans Picked Up | 2/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | TROY DEGUZMAN |
| Corrections Issued | 3/8/2020 | TROY DEGUZMAN |
| Quality Review Completed | 3/12/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/16/2020 | APPLICANT |
| Plan Check Approved | 2/25/2021 | TROY DEGUZMAN |
| Issued | 3/2/2021 | APPLICANT |
| CofO in Progress | 9/29/2022 | JAVIER RAMOS JR |
| Permit Finaled | 10/12/2022 | MICHAEL SMITH |
| CofO Issued | 10/12/2022 | MICHAEL SMITH |
| Permit Finaled | 10/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 3/16/2020 | GEORGE SUCHAND |
| Permit | Cleared | 3/16/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/16/2020 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 9/29/2020 | BRIAN MILLER |
| Low Impact Development | Cleared | 10/15/2020 | SARAH YOUSSEF |
| Green Code | Cleared | 11/4/2020 | AARON COSTA |
| Trees in Parkway | Cleared | 12/30/2020 | JOHN KIM |
| Roof/Waste drainage to street | Cleared | 1/20/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/16/2021 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 8/25/2021 | Corrections Issued | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 8/27/2021 | Approved | MARK JOHNSON |
| Footing/Foundation/Slab | 8/27/2021 | Approved | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2021 | Partial Approval | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Partial Inspection | MARK JOHNSON |
| BUILDING-Rough-Frame | 10/27/2021 | Corrections Issued | MARK JOHNSON |
| ELECTRICAL-Rough | 10/27/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 10/27/2021 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 10/27/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 10/27/2021 | Corrections Issued | MARK JOHNSON |
| Verify Sprinkler Sign Off | 10/27/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 11/2/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 11/2/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 11/2/2021 | Not Ready for Inspection | MARK JOHNSON |
| BUILDING-Rough-Frame | 11/9/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 11/9/2021 | Partial Approval | MARK JOHNSON |
| PLUMBING-Rough | 11/9/2021 | Approved | MARK JOHNSON |
| Wood Frame | 11/9/2021 | Approved | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | No Access for Inspection | MARK JOHNSON |
| Interior/Exterior Lathing | 11/15/2021 | No Access for Inspection | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/18/2021 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 11/29/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 11/29/2021 | Approved | MARK JOHNSON |
| Shower Pan | 11/29/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 12/10/2021 | Approved | MARK JOHNSON |
| Drywall Nailing | 12/10/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 12/10/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 1/10/2022 | Partial Approval | MARK JOHNSON |
| Sewer | 1/10/2022 | Approved | MARK JOHNSON |
| Underground Mechanical | 1/10/2022 | Approved | MARK JOHNSON |
| Final | 6/6/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 6/6/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 6/6/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 6/6/2022 | Approved | JAVIER RAMOS JR |
| Final | 9/12/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 9/12/2022 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 9/12/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 9/29/2022 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 9/29/2022 | Approved | JAVIER RAMOS JR |