3655 S BARRINGTON AVE 90066
Certificate Information: 3655 S BARRINGTON AVE 90066
- Application / Permit
- 20010-20000-00207
- Plan Check / Job No.
- B20VN00935
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE 71'X74'-4" TWO STORY SFD WITH BASEMENT, ATTACHED 5 CAR- GARAGE, COVERED PATIO AND OPEN TRELLIS ARE REAR _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D [SEE COMMENTS].
- Permit Issued
- Issued on 4/7/2022
- Issuing Office
- Valley
- Current Status
- Issued on 4/7/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/21/2020 | APPLICANT |
| Green Plans Picked Up | 2/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | DAWN MC NULTY |
| Corrections Issued | 3/25/2020 | DAWN MC NULTY |
| Quality Review Completed | 3/31/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 4/23/2020 | APPLICANT |
| Applicant returned to address corrections | 4/9/2021 | DAWN MC NULTY |
| Applicant returned to address corrections | 9/29/2021 | DAWN MC NULTY |
| Applicant returned to address corrections | 2/17/2022 | DAWN MC NULTY |
| Plan Check Approved | 3/9/2022 | DAWN MC NULTY |
| Issued | 4/7/2022 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 5/18/2020 | PABLO ESTRADA |
| CPC | Cleared | 5/18/2020 | PABLO ESTRADA |
| CPC | Cleared | 5/18/2020 | PABLO ESTRADA |
| Address approval | Cleared | 5/21/2020 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 5/21/2020 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 5/21/2020 | HISASHI KOBAYAKAWA |
| Work Adjacent to Public Way | Cleared | 5/21/2020 | HISASHI KOBAYAKAWA |
| Green Code | Cleared | 5/22/2020 | AARON COSTA |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2020 | HISASHI KOBAYAKAWA |
| Frnt yard landscape/Water mgmt | Cleared | 6/16/2020 | PABLO ESTRADA |
| Hydrant and Access approval | Cleared | 7/6/2020 | ROBERT DUFF |
| Excavation more than 5-ft deep | Cleared | 8/17/2020 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 10/6/2020 | MARTIN FRAGOSO |
| GPI Written Notices | Cleared | 3/1/2021 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 3/1/2021 | DAWN MC NULTY |
| Miscellaneous | Cleared | 3/1/2021 | DAWN MC NULTY |
| Roof/Waste drainage to street | Cleared | 3/12/2021 | DINAH GARIN |
| Trees in Parkway | Cleared | 4/27/2021 | JOHN KIM |
Contact Information
| Architect | Bannick,, Arthur Joseph; Lic. No.: C17986 | BANNICK ARCHITECTS 7141 VALJEAN AVE. STE. 100 VAN NUYS, CA 91406 |
| Architect | Goodarzi,, Morteza; Lic. No.: C23941 | 45 W YALE LOOP IRVINE, CA 92604 |
| Contractor | Areio Inc; Lic. No.: 997015-B | 73 NIGHTHAWK IRVINE, CA 92604 |
| Engineer | Eftekhari,, Hossein; Lic. No.: C50121 | 5945 SETTLER COURT ANAHEIM, CA 92807 |
| Engineer | Gorbin,, James D; Lic. No.: S5859 | 210 S JUANITA AVE A REDONDO BEACH, CA 90277 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| ELECTRICAL-Final | 6/10/2026 |
| Final | 6/10/2026 |
| PLUMBING-Final | 6/10/2026 |
| HVAC-Final | 6/10/2026 |
Inspection Request History
| Piling/Pier/Caisson | 5/25/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 9/12/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 9/14/2022 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 10/24/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/28/2022 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 10/31/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/7/2022 | Partial Approval | EVAN COOPER |
| Deputy Shotcrete | 11/16/2022 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 11/18/2022 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 12/29/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 12/30/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Partial Approval | EVAN COOPER |
| Green Building Rough | 2/8/2023 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 2/8/2023 | Not Ready for Inspection | EVAN COOPER |
| Deputy Steel/Welding | 2/17/2023 | Conditional Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/26/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 5/26/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 5/26/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Partial Approval | JESUS PINEDA |
| Green Building Rough | 8/10/2023 | Not Ready for Inspection | JESUS PINEDA |
| Verify Sprinkler Sign Off | 8/10/2023 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 9/14/2023 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 9/14/2023 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 10/3/2023 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Rough | 10/3/2023 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 10/12/2023 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Approved | JESUS PINEDA |
| HVAC-Rough | 10/17/2023 | Approved | JESUS PINEDA |
| Special/Order Compliance | 10/17/2023 | Partial Inspection | RICHARD STEINBACH |
| Interior/Exterior Lathing | 10/30/2023 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/2/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 11/2/2023 | Approved | JESUS PINEDA |
| Shower Pan | 11/2/2023 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 11/2/2023 | Approved | JESUS PINEDA |
| Insulation | 11/7/2023 | Corrections Issued | JESUS PINEDA |
| Insulation | 11/13/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 12/1/2023 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 6/20/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 6/27/2024 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 7/9/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 7/9/2024 | Approved | JESUS PINEDA |
| Underground Mechanical | 7/9/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 10/25/2024 | Corrections Issued | DANIEL VERA |
| ELECTRICAL-Final | 12/5/2024 | Approved | DANIEL VERA |
| PLUMBING-Final | 12/5/2024 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 12/9/2024 | Corrections Issued | DANIEL VERA |
| HVAC-Rough | 12/9/2024 | Approved | DANIEL VERA |
| Final | 12/23/2024 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Final | 12/23/2024 | Approved | DANIEL VERA |
| Final | 8/4/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 8/4/2025 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Not Ready | KIRK SANDERS |
| Service/Power Release | 8/4/2025 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 8/4/2025 | Approved | KIRK SANDERS |
| Final | 12/5/2025 | Not Ready for Inspection | KIRK SANDERS |
| Gas Test | 1/6/2026 | Approved | KIRK SANDERS |
| PLUMBING-Final | 1/6/2026 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 1/6/2026 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 3/20/2026 | Approved | ANDREW NAVE |