7903 N FARRALONE AVE 91304
Certificate Information: 7903 N FARRALONE AVE 91304
- Application / Permit
- 20010-20000-00201
- Plan Check / Job No.
- B20VN00909
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1-STORY 25' X 48' ACCESSORY DWELLING UNIT WITH ATTACHED 5' X 3' 2" PATIO COVER. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 10/1/2020
- Issuing Office
- Current Status
- CofO Issued on 4/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2020 | APPLICANT |
| Green Plans Picked Up | 2/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 3/7/2020 | GURUNATH NESARAJAH |
| Quality Review Completed | 3/11/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 3/18/2020 | APPLICANT |
| Plan Check Approved | 9/17/2020 | GURUNATH NESARAJAH |
| Issued | 10/1/2020 | APPLICANT |
| CofO in Progress | 4/5/2021 | DAVID STEPANYAN |
| Permit Finaled | 4/8/2021 | JOHN JANSON |
| CofO Issued | 4/8/2021 | JOHN JANSON |
| Permit Finaled | 4/8/2021 | JOHN JANSON |
Permit Application Clearance Information
| Green Code | Cleared | 3/25/2020 | MICHAEL AYERS |
| Address approval | Cleared | 4/22/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/23/2020 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 5/26/2020 | ANDRES COVARRUBIAS |
| Hydrant and Access approval | Cleared | 6/22/2020 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 6/29/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/8/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/20/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 10/20/2020 | Partial Approval | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2020 | Partial Approval | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2020 | Partial Approval | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 11/16/2020 | Corrections Issued | DAVID STEPANYAN |
| Interior/Exterior Lathing | 11/16/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 11/16/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 12/1/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 12/1/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 12/1/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 12/1/2020 | Approved | DAVID STEPANYAN |
| Insulation | 12/1/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 12/7/2020 | Approved | DAVID STEPANYAN |
| Shower Pan | 12/7/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 12/15/2020 | Approved | DAVID STEPANYAN |
| Sewer | 12/23/2020 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 12/23/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 2/3/2021 | Corrections Issued | DAVID STEPANYAN |
| Final | 2/3/2021 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 2/3/2021 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Final | 2/3/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Final | 2/3/2021 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2021 | SGSOV Approved | DAVID STEPANYAN |
| Service/Power Release | 2/3/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Smoke Detectors | 2/3/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 3/18/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Final | 3/18/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Final | 3/18/2021 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Final | 3/18/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Service/Power Release | 3/18/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Final | 3/26/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 3/26/2021 | Not Ready for Inspection | STEVEN BACK |
| Service/Power Release | 3/26/2021 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Final | 4/5/2021 | Approved | DAVID STEPANYAN |
| Final | 4/5/2021 | OK to Issue CofO | DAVID STEPANYAN |
| Green Building Final | 4/5/2021 | Approved | DAVID STEPANYAN |
| HVAC-Final | 4/5/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 4/5/2021 | Approved | DAVID STEPANYAN |
| Service/Power Release | 4/5/2021 | Approved | DAVID STEPANYAN |