5932 E ECHO ST 90042

Certificate Information: 5932 E ECHO ST 90042

Application / Permit
20010-20000-00182
Plan Check / Job No.
B20VN00814
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 15'-0" x 24'-0" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 1/24/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2020 APPLICANT
Green Plans Picked Up 2/19/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 SARKIS HARABEDIAN
Corrections Issued 3/9/2020 SARKIS HARABEDIAN
Quality Review Completed 3/12/2020 GUANG MIN TUNG
Building Plans Picked Up 3/13/2020 APPLICANT
Applicant returned to address corrections 7/10/2020 SARKIS HARABEDIAN
Applicant returned to address corrections 7/31/2020 SARKIS HARABEDIAN
Applicant returned to address corrections 11/16/2020 SARKIS HARABEDIAN
Plan Check Approved 6/2/2021 SARKIS HARABEDIAN
No Progress 1/20/2023 SARKIS HARABEDIAN
Plan Check Approved 1/20/2023 SARKIS HARABEDIAN
Issued 1/24/2023 APPLICANT
CofO in Progress 5/13/2025 LILIANA PORTILLO
Permit Finaled 5/15/2025 DEROLD HAUFF
CofO Issued 5/15/2025 DEROLD HAUFF
Permit Finaled 5/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/14/2020 JUAN ASHTON
Roof/Waste drainage to street Cleared 4/21/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 4/23/2020 JUAN ASHTON
Sewer availability Cleared 4/23/2020 JUAN ASHTON
Green Code Cleared 6/17/2020 DAVID MATSON
HPOZ Cleared 7/30/2020 KATIE DEBIASE
Miscellaneous Cleared 7/30/2020 KATIE DEBIASE
Construction near power lines Cleared 7/31/2020 OSCAR CASTRO
Hydrant and Access approval Cleared 10/21/2020 KURT CORRAL
Grading Pre-Inspection Cleared 11/16/2020 SARKIS HARABEDIAN
Specific Plan Cleared 12/15/2020 ADRINEH MELKONIAN
Low Impact Development Cleared 5/16/2021 MARTIN FRAGOSO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/30/2025 Approved LILIANA PORTILLO
Drywall Nailing 1/30/2025 Approved LILIANA PORTILLO
Final 1/30/2025 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 1/30/2025 Approved LILIANA PORTILLO
Green Building Final 1/30/2025 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 1/30/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/30/2025 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 1/30/2025 Approved LILIANA PORTILLO
Smoke Detectors 1/30/2025 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 1/30/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 2/6/2025 Approved LILIANA PORTILLO
Final 2/6/2025 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 2/6/2025 Approved LILIANA PORTILLO
HVAC-Final 2/6/2025 Approved LILIANA PORTILLO
PLUMBING-Final 2/6/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 2/6/2025 SGSOV Approved LILIANA PORTILLO
Final 5/12/2025 OK to Issue CofO LILIANA PORTILLO