5129 N SHEARIN AVE 90041
Certificate Information: 5129 N SHEARIN AVE 90041
- Application / Permit
- 20010-20000-00179
- Plan Check / Job No.
- B20VN00785
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ( 24'-6"x 42'-3", 1,198 SQ. FT.) TWO-STORY DETACHED ACCESSORY DWELLING UNIT WITH 2-CAR ATTACHED GARAGE. WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/18/2021
- Issuing Office
- Current Status
- CofO Issued on 6/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2020 | APPLICANT |
| Green Plans Picked Up | 2/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | TROY DEGUZMAN |
| Corrections Issued | 3/1/2020 | TROY DEGUZMAN |
| Quality Review Completed | 3/6/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/6/2020 | APPLICANT |
| Applicant returned to address corrections | 4/10/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 2/4/2021 | COLIN LOREDO |
| Plan Check Approved | 2/18/2021 | COLIN LOREDO |
| Issued | 2/18/2021 | APPLICANT |
| CofO in Progress | 6/7/2022 | CRAIG VAUGHAN |
| CofO in Progress | 6/11/2022 | CRAIG VAUGHAN |
| Permit Finaled | 6/14/2022 | DEROLD HAUFF |
| CofO Issued | 6/14/2022 | DEROLD HAUFF |
| Permit Finaled | 6/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 3/17/2020 | GEORGE SUCHAND |
| Sewer availability | Cleared | 3/17/2020 | JEANIE LAM |
| Green Code | Cleared | 3/25/2020 | AARON COSTA |
| GPI Written Notices | Cleared | 4/10/2020 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 4/10/2020 | TROY DEGUZMAN |
| Low Impact Development | Cleared | 12/8/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/21/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 4/8/2021 | Conditional Approval | SCOTT FINNILA |
| PLUMBING-Rough | 4/13/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Special/Order Compliance | 4/13/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/20/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2021 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 6/17/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/28/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 6/28/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 6/28/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 6/28/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/6/2021 | Not Ready for Inspection | COREY HUPP |
| HVAC-Rough | 7/6/2021 | Corrections Issued | COREY HUPP |
| PLUMBING-Rough | 7/6/2021 | Partial Approval | COREY HUPP |
| Wood Frame | 7/6/2021 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 7/8/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/8/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/8/2021 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 7/8/2021 | Partial Inspection | ALAN MORELOS |
| Wood Frame | 7/8/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/27/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 7/27/2021 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 7/27/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 7/27/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 8/4/2021 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 8/13/2021 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 8/13/2021 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 8/19/2021 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 9/16/2021 | Partial Approval | CRAIG VAUGHAN |
| Special/Order Compliance | 10/21/2021 | Approved | HECTOR ALIKHAN |
| Special/Order Compliance | 11/23/2021 | Partial Inspection | AMY COLIN |
| ELECTRICAL-Rough | 1/22/2022 | Off-Hour Fees Due | |
| Underground Mechanical | 1/22/2022 | Partial Approval | AMY COLIN |
| Gas Test | 2/11/2022 | Approved | HAMIK HARTOUNIAN |
| Gas Test | 2/11/2022 | Off-Hour Fees Due | |
| Pre-Inspection | 2/11/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| Sewer | 2/11/2022 | Approved | HAMIK HARTOUNIAN |
| Sewer | 2/11/2022 | Off-Hour Fees Due | |
| PLUMBING-Rough | 2/16/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/18/2022 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/18/2022 | No Access for Inspection | JOSEPH MCGARRY |
| Final | 3/18/2022 | No Access for Inspection | JOSEPH MCGARRY |
| Green Building Final | 3/18/2022 | No Access for Inspection | JOSEPH MCGARRY |
| HVAC-Final | 3/18/2022 | No Access for Inspection | JOSEPH MCGARRY |
| PLUMBING-Final | 3/18/2022 | No Access for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/18/2022 | SGSOV Not Ready | JOSEPH MCGARRY |
| Service/Power Release | 3/18/2022 | Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 3/18/2022 | No Access for Inspection | JOSEPH MCGARRY |
| Pre-Inspection | 3/22/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 3/30/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 3/30/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 3/30/2022 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 3/30/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 3/30/2022 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 4/6/2022 | Approved | CRAIG VAUGHAN |
| Final | 4/19/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 4/19/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/19/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Special/Order Compliance | 4/27/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 6/6/2022 | Approved | CRAIG VAUGHAN |
| Final | 6/6/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Approved | CRAIG VAUGHAN |