1309 N TALMADGE ST 90027
Certificate Information: 1309 N TALMADGE ST 90027
- Application / Permit
- 20010-20000-00173
- Plan Check / Job No.
- B20VN00755
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (d)
- Permit Issued
- Issued on 11/4/2020
- Issuing Office
- Current Status
- CofO Issued on 4/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2020 | APPLICANT |
| Green Plans Picked Up | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/2/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/2/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 3/9/2020 | APPLICANT |
| Plan Check Approved | 10/8/2020 | NILOOFAR MEHRAIN |
| Issued | 11/4/2020 | APPLICANT |
| CofO in Progress | 4/14/2021 | JOSEPH MCGARRY |
| Permit Finaled | 4/27/2021 | DEROLD HAUFF |
| CofO Issued | 4/27/2021 | DEROLD HAUFF |
| Permit Finaled | 4/27/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2020 | LEE GUILBEAUX |
| Permit | Cleared | 3/16/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/16/2020 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 3/18/2020 | GEORGE SUCHAND |
| Grading Pre-Inspection | Cleared | 7/7/2020 | BRIAN MILLER |
| Trees in Parkway | Cleared | 7/14/2020 | JOHN KIM |
| Low Impact Development | Cleared | 9/14/2020 | MARTIN FRAGOSO |
| Green Code | Cleared | 10/1/2020 | MICHAEL AYERS |
| GPI Written Notices | Cleared | 10/8/2020 | NILOOFAR MEHRAIN |
| Roof/Waste drainage to street | Cleared | 10/20/2020 | MIKE KOUYOUMDJIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/24/2020 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 12/7/2020 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 12/7/2020 | Conditional Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 12/15/2020 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 12/15/2020 | Approved | JOSEPH MCGARRY |
| Piling/Pier/Caisson | 12/15/2020 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2020 | Conditional Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/14/2021 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 1/14/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 1/14/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2021 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 1/14/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 1/14/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 1/14/2021 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 1/14/2021 | Approved | JOSEPH MCGARRY |
| Deputy Wood Construction | 1/15/2021 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 1/22/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 1/22/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 1/22/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 1/22/2021 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 1/22/2021 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 1/22/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 1/22/2021 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 1/28/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 1/28/2021 | Approved | JOSEPH MCGARRY |
| Gas Test | 3/12/2021 | Approved | JOSEPH MCGARRY |
| Sewer | 3/12/2021 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 3/12/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 3/26/2021 | Corrections Issued | JOSEPH MCGARRY |
| Final | 3/26/2021 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 3/26/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 3/26/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 3/26/2021 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/26/2021 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 3/26/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Smoke Detectors | 3/26/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 4/13/2021 | Approved | JOSEPH MCGARRY |
| Final | 4/13/2021 | OK to Issue CofO | JOSEPH MCGARRY |
| HVAC-Final | 4/13/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 4/13/2021 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 4/13/2021 | Approved | JOSEPH MCGARRY |
| Smoke Detectors | 4/13/2021 | Approved | JOSEPH MCGARRY |