27535 S UPTON TER 90732
Certificate Information: 27535 S UPTON TER 90732
- Application / Permit
- 20010-20000-00140
- Plan Check / Job No.
- B20VN00737
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT) [Small lot subdivision pursuant to Tentative Tract Map No. 71886-04. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded]
- Permit Issued
- Issued on 4/22/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2020 | APPLICANT |
| Green Plans Picked Up | 2/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/18/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/19/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 2/20/2020 | APPLICANT |
| Applicant returned to address corrections | 3/27/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/11/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/6/2021 | NILOOFAR MEHRAIN |
| Issued | 4/22/2021 | APPLICANT |
| CofO in Progress | 3/21/2022 | ANSON MAGLASANG |
| CofO in Progress | 3/21/2022 | ANSON MAGLASANG |
| CofO in Progress | 3/23/2022 | ANSON MAGLASANG |
| Permit Finaled | 3/23/2022 | DEROLD HAUFF |
| CofO Issued | 3/23/2022 | DEROLD HAUFF |
| Permit Finaled | 3/23/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 3/31/2020 | AMMAR ELTAWIL |
| CPC | Cleared | 4/12/2020 | ERIN STRELICH |
| ZA Case | Cleared | 4/12/2020 | ERIN STRELICH |
| ZA Case | Cleared | 4/12/2020 | ERIN STRELICH |
| Address approval | Cleared | 6/3/2020 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2020 | JENSON LEE |
| Permit | Cleared | 6/3/2020 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 6/3/2020 | JENSON LEE |
| Sewer availability | Cleared | 6/3/2020 | JENSON LEE |
| Disturb/Remove Protected Trees | Cleared | 6/4/2020 | ADRIAN SANCHEZ |
| Trees in Parkway | Cleared | 6/10/2020 | JOHN KIM |
| Green Code | Cleared | 6/15/2020 | NILOOFAR MEHRAIN |
| GPI Written Notices | Cleared | 6/16/2020 | KIRK LINKLATER |
| Grading Pre-Inspection | Cleared | 6/16/2020 | KIRK LINKLATER |
| Miscellaneous | Cleared | 9/21/2020 | JENSON LEE |
| Hydrant and Access approval | Cleared | 1/26/2021 | ROBERT DUFF |
| CPC | Cleared | 2/19/2021 | MINDY NGUYEN |
| Miscellaneous | Cleared | 2/19/2021 | MINDY NGUYEN |
| Miscellaneous | Cleared | 2/19/2021 | MINDY NGUYEN |
| Miscellaneous | Cleared | 2/19/2021 | MINDY NGUYEN |
| Miscellaneous | Cleared | 2/19/2021 | MINDY NGUYEN |
| Miscellaneous | Cleared | 2/19/2021 | MINDY NGUYEN |
| Specific Plan | Cleared | 2/19/2021 | MINDY NGUYEN |
| Tract Map conditions | Cleared | 2/19/2021 | MINDY NGUYEN |
| Tract Map conditions | Cleared | 2/19/2021 | MINDY NGUYEN |
| ZI | Cleared | 2/19/2021 | MINDY NGUYEN |
Contact Information
| Architect | Cunningham,, Gary Lynn; Lic. No.: C29285 | 18162 LILLIAN WAY TUSTIN, CA 92780 |
| Contractor | D R Horton America'S Builder; Lic. No.: 765023-B | 2280 WARDLOW CIRCLE SUITE 100 CORONA, CA 92880 |
| Engineer | Deihimi,, Amir Hossein; Lic. No.: C78194 | 23172 PLAZA POINTE DR STE 145 LAGUNA HILLS, CA 92653 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/14/2021 | Approved | JOHN KLARIN |
| Underground Mechanical | 7/14/2021 | Partial Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 8/3/2021 | Approved | JOHN KLARIN |
| METHANE-Barrier | 8/3/2021 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 8/3/2021 | Approved | JOHN KLARIN |
| Deputy Reinf. Concrete | 8/4/2021 | Conditional Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2021 | Partial Approval | ANSON MAGLASANG |
| Rough-Elec/Plmb/HVAC | 12/7/2021 | Approved | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2021 | Partial Approval | JOHN KLARIN |
| Insulation | 1/5/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 1/5/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Drywall Nailing | 1/13/2022 | Approved | ANSON MAGLASANG |
| Green Building Rough | 1/13/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 1/13/2022 | Approved | ANSON MAGLASANG |
| Service/Power Release | 2/23/2022 | Corrections Issued | ANSON MAGLASANG |
| Service/Power Release | 3/1/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Approved | ANSON MAGLASANG |
| Service/Power Release | 3/4/2022 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 3/17/2022 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 3/17/2022 | Approved | ANSON MAGLASANG |
| Final | 3/17/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Final | 3/17/2022 | Approved | ANSON MAGLASANG |
| HVAC-Final | 3/17/2022 | Approved | ANSON MAGLASANG |
| METHANE-Final | 3/17/2022 | Approved | ANSON MAGLASANG |
| METHANE-Rough | 3/17/2022 | Approved | ANSON MAGLASANG |
| PLUMBING-Final | 3/17/2022 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 3/17/2022 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 3/17/2022 | Approved | ANSON MAGLASANG |
| Verify Sprinkler Sign Off | 3/17/2022 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 3/21/2022 | Approved | ANSON MAGLASANG |
| Final | 3/21/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| HVAC-Final | 3/21/2022 | Approved | ANSON MAGLASANG |
| PLUMBING-Final | 3/21/2022 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 3/23/2022 | Approved | ANSON MAGLASANG |
| Final | 3/23/2022 | OK to Issue CofO | ANSON MAGLASANG |
| HVAC-Final | 3/23/2022 | Approved | ANSON MAGLASANG |
| PLUMBING-Final | 3/23/2022 | Approved | ANSON MAGLASANG |