27616 S SUNCREST RD 90732

Certificate Information: 27616 S SUNCREST RD 90732

Application / Permit
20010-20000-00131
Plan Check / Job No.
B20VN00737
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINLERS THROUGHOUT) [Small lot subdivision pursuant to Tentative Tract Map No. 71886-04. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded]
Permit Issued
Issued on 8/25/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2020 APPLICANT
Green Plans Picked Up 2/4/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 NILOOFAR MEHRAIN
Corrections Issued 2/18/2020 NILOOFAR MEHRAIN
Quality Review Completed 2/19/2020 GUANG MIN TUNG
Building Plans Picked Up 2/20/2020 APPLICANT
Applicant returned to address corrections 3/27/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/11/2020 NILOOFAR MEHRAIN
Plan Check Approved 8/11/2020 NILOOFAR MEHRAIN
Issued 8/25/2020 APPLICANT
CofO in Progress 6/9/2022 ANSON MAGLASANG
Permit Finaled 6/9/2022 DEROLD HAUFF
CofO Issued 6/9/2022 DEROLD HAUFF
Permit Finaled 6/9/2022 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 3/31/2020 AMMAR ELTAWIL
CPC Cleared 4/12/2020 ERIN STRELICH
ZA Case Cleared 4/12/2020 ERIN STRELICH
ZA Case Cleared 4/12/2020 ERIN STRELICH
Miscellaneous Cleared 5/26/2020 SARAHI ORTEGA
Miscellaneous Cleared 5/26/2020 SARAHI ORTEGA
Miscellaneous Cleared 5/26/2020 SARAHI ORTEGA
Tract Map conditions Cleared 5/26/2020 SARAHI ORTEGA
Tract Map conditions Cleared 5/26/2020 SARAHI ORTEGA
Address approval Cleared 6/2/2020 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 6/2/2020 JENSON LEE
Permit Cleared 6/2/2020 JENSON LEE
Roof/Waste drainage to street Cleared 6/2/2020 JENSON LEE
Sewer availability Cleared 6/2/2020 JENSON LEE
Hydrant and Access approval Cleared 6/8/2020 MATTHEW CRAIG
Trees in Parkway Cleared 6/10/2020 JOHN KIM
Green Code Cleared 6/15/2020 NILOOFAR MEHRAIN
Disturb/Remove Protected Trees Cleared 6/16/2020 ADRIAN SANCHEZ
GPI Written Notices Cleared 6/16/2020 KIRK LINKLATER
Grading Pre-Inspection Cleared 6/16/2020 KIRK LINKLATER
CPC Cleared 8/4/2020 JASON CHAN
Miscellaneous Cleared 8/4/2020 JASON CHAN
Miscellaneous Cleared 8/4/2020 JASON CHAN
Specific Plan Cleared 8/4/2020 JASON CHAN
ZI Cleared 8/4/2020 JASON CHAN
Miscellaneous Cleared 8/5/2020 JASON CHAN
Miscellaneous Cleared 8/6/2020 JENSON LEE

Contact Information

Architect Cunningham,, Gary Lynn; Lic. No.: C29285 18162 LILLIAN WAY      TUSTIN, CA 92780
Contractor D R Horton America'S Builder; Lic. No.: 765023-B 2280 WARDLOW CIRCLE SUITE 100      CORONA, CA 92880
Engineer Deihimi,, Amir Hossein; Lic. No.: C78194 23172 PLAZA POINTE DR STE 145      LAGUNA HILLS, CA 92653

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/1/2020 Approved JOHN KLARIN
Sewer 9/1/2020 Approved JOHN KLARIN
Underground Mechanical 9/1/2020 Partial Approval JOHN KLARIN
Deputy Pre-Stress Concrete 9/9/2020 Approved JOHN KLARIN
Footing/Foundation/Slab 9/10/2020 Partial Inspection JOHN KLARIN
METHANE-Barrier 9/10/2020 Partial Inspection JOHN KLARIN
METHANE-Subgrade 9/10/2020 Partial Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 9/18/2020 Partial Inspection JOHN KLARIN
Deputy Wood Construction 10/7/2020 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 10/21/2020 Corrections Issued JOHN KLARIN
Green Building Rough 10/21/2020 Not Ready for Inspection JOHN KLARIN
METHANE-Rough 10/21/2020 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 10/21/2020 Approved JOHN KLARIN
Insulation 10/28/2020 Conditional Approval JOHN KLARIN
Drywall Nailing 11/2/2020 Approved JOHN KLARIN
ELECTRICAL-Rough 11/2/2020 Conditional Approval JOHN KLARIN
Green Building Rough 11/2/2020 Approved JOHN KLARIN
HVAC-Rough 11/2/2020 Conditional Approval JOHN KLARIN
Interior/Exterior Lathing 11/2/2020 Approved JOHN KLARIN
PLUMBING-Rough 11/2/2020 Approved JOHN KLARIN
Gas Test 1/4/2021 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 1/5/2021 SGSOV Approved JOHN KLARIN
ELECTRICAL-Final 4/5/2021 Approved JOHN KLARIN
HVAC-Final 4/5/2021 Corrections Issued JOHN KLARIN
ELECTRICAL-Final 4/6/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 4/7/2021 Conditional Approval JOHN KLARIN
ELECTRICAL-Final 4/7/2021 Approved JOHN KLARIN
Final 4/7/2021 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 4/7/2021 Approved JOHN KLARIN
Green Building Final 4/7/2021 Corrections Issued JOHN KLARIN
HVAC-Final 4/7/2021 Corrections Issued JOHN KLARIN
METHANE-Barrier 4/7/2021 Approved JOHN KLARIN
METHANE-Final 4/7/2021 Approved JOHN KLARIN
METHANE-Rough 4/7/2021 Approved JOHN KLARIN
METHANE-Subgrade 4/7/2021 Approved JOHN KLARIN
PLUMBING-Final 4/7/2021 Approved JOHN KLARIN
Service/Power Release 4/7/2021 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 4/7/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 4/30/2021 Approved JOHN KLARIN
Final 4/30/2021 Corrections Issued JOHN KLARIN
Gas Test 4/30/2021 Approved ANSON MAGLASANG
Green Building Final 4/30/2021 Approved JOHN KLARIN
Service/Power Release 4/30/2021 Approved ANSON MAGLASANG
Service/Power Release 4/30/2021 Approved JOHN KLARIN
Special/Order Compliance 4/13/2022 Partial Inspection ANSON MAGLASANG
ELECTRICAL-Final 6/3/2022 Approved EUGENE CASSIDY
Final 6/3/2022 Corrections Issued EUGENE CASSIDY
HVAC-Final 6/3/2022 Approved EUGENE CASSIDY
PLUMBING-Final 6/3/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 6/9/2022 Approved ANSON MAGLASANG
Final 6/9/2022 OK to Issue CofO ANSON MAGLASANG
HVAC-Final 6/9/2022 Approved ANSON MAGLASANG
PLUMBING-Final 6/9/2022 Approved ANSON MAGLASANG