27510 S EDGEMONT DR 90732
Certificate Information: 27510 S EDGEMONT DR 90732
- Application / Permit
- 20010-20000-00123
- Plan Check / Job No.
- B20VN00737
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT) [Small lot subdivision pursuant to Tentative Tract Map No. 71886-04. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded]
- Permit Issued
- Issued on 2/10/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2020 | APPLICANT |
| Green Plans Picked Up | 2/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/18/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/19/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 2/20/2020 | APPLICANT |
| Applicant returned to address corrections | 3/27/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/11/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 1/24/2021 | NILOOFAR MEHRAIN |
| Issued | 2/10/2021 | APPLICANT |
| CofO in Progress | 10/21/2021 | ANSON MAGLASANG |
| Permit Finaled | 10/23/2021 | DEROLD HAUFF |
| Permit Finaled | 10/23/2021 | DEROLD HAUFF |
| CofO Issued | 10/23/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 2/18/2020 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 2/18/2020 | NILOOFAR MEHRAIN |
| Low Impact Development | Cleared | 3/31/2020 | AMMAR ELTAWIL |
| CPC | Cleared | 4/10/2020 | ERIN STRELICH |
| ZA Case | Cleared | 4/12/2020 | ERIN STRELICH |
| ZA Case | Cleared | 4/12/2020 | ERIN STRELICH |
| Miscellaneous | Cleared | 5/26/2020 | SARAHI ORTEGA |
| Miscellaneous | Cleared | 5/26/2020 | SARAHI ORTEGA |
| Miscellaneous | Cleared | 5/26/2020 | SARAHI ORTEGA |
| Tract Map conditions | Cleared | 5/26/2020 | SARAHI ORTEGA |
| Tract Map conditions | Cleared | 5/26/2020 | SARAHI ORTEGA |
| Address approval | Cleared | 6/1/2020 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2020 | JENSON LEE |
| Permit | Cleared | 6/1/2020 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 6/1/2020 | JENSON LEE |
| Sewer availability | Cleared | 6/1/2020 | JENSON LEE |
| Disturb/Remove Protected Trees | Cleared | 6/4/2020 | ADRIAN SANCHEZ |
| Trees in Parkway | Cleared | 6/10/2020 | JOHN KIM |
| Green Code | Cleared | 6/15/2020 | NILOOFAR MEHRAIN |
| Miscellaneous | Cleared | 9/21/2020 | JENSON LEE |
| CPC | Cleared | 12/30/2020 | JASON CHAN |
| Miscellaneous | Cleared | 12/30/2020 | JASON CHAN |
| Specific Plan | Cleared | 12/30/2020 | JASON CHAN |
| ZI | Cleared | 12/30/2020 | JASON CHAN |
| Hydrant and Access approval | Cleared | 1/26/2021 | ROBERT DUFF |
Contact Information
| Architect | Cunningham,, Gary Lynn; Lic. No.: C29285 | 18162 LILLIAN WAY TUSTIN, CA 92780 |
| Contractor | D R Horton Ven Inc; Lic. No.: 765023-B | 2280 WARDLOW CIRCLE SUITE 100 CORONA, CA 92880 |
| Engineer | Deihimi,, Amir Hossein; Lic. No.: C78194 | 23172 PLAZA POINTE DR STE 145 LAGUNA HILLS, CA 92653 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/1/2021 | Approved | JOHN KLARIN |
| Underground Mechanical | 3/1/2021 | Partial Approval | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 3/30/2021 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/30/2021 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 3/30/2021 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 3/30/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2021 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2021 | Corrections Issued | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2021 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/12/2021 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 7/12/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 7/12/2021 | Approved | JOHN KLARIN |
| HVAC-Rough | 7/12/2021 | Approved | JOHN KLARIN |
| METHANE-Rough | 7/12/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/12/2021 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 7/12/2021 | Approved | JOHN KLARIN |
| Insulation | 7/20/2021 | Partial Approval | JOHN KLARIN |
| Drywall Nailing | 7/28/2021 | Corrections Issued | JOHN KLARIN |
| Drywall Nailing | 8/2/2021 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 8/5/2021 | Partial Approval | ANSON MAGLASANG |
| Gas Test | 9/17/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 9/17/2021 | SGSOV Not Ready | ANSON MAGLASANG |
| Service/Power Release | 9/17/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Gas Test | 9/29/2021 | Approved | ANSON MAGLASANG |
| Service/Power Release | 9/29/2021 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 10/13/2021 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 10/13/2021 | Approved | ANSON MAGLASANG |
| Final | 10/13/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Final | 10/13/2021 | Approved | ANSON MAGLASANG |
| HVAC-Final | 10/13/2021 | Approved | ANSON MAGLASANG |
| PLUMBING-Final | 10/13/2021 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 10/13/2021 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 10/13/2021 | Approved | ANSON MAGLASANG |
| Final | 10/15/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 10/18/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 10/21/2021 | OK to Issue CofO | ANSON MAGLASANG |