6117 N SYLVIA AVE 91335
Certificate Information: 6117 N SYLVIA AVE 91335
- Application / Permit
- 20010-20000-00087
- Plan Check / Job No.
- B20VN00675
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 27'-7" X 49'-4" 1-STORY ACCESOSSRY DWELLING UNIT .
- Permit Issued
- Issued on 11/2/2020
- Issuing Office
- Current Status
- CofO Issued on 11/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | SERGIO MUNIZ |
| Green Plans Picked Up | 2/27/2020 | APPLICANT |
| Corrections Issued | 3/4/2020 | SERGIO MUNIZ |
| Quality Review Completed | 3/11/2020 | STEVEN KIM |
| Building Plans Picked Up | 3/12/2020 | APPLICANT |
| Applicant returned to address corrections | 5/15/2020 | SERGIO MUNIZ |
| Applicant returned to address corrections | 9/25/2020 | SERGIO MUNIZ |
| Plan Check Approved | 10/19/2020 | SERGIO MUNIZ |
| Issued | 11/2/2020 | APPLICANT |
| Permit Closed-Status Void | 10/18/2021 | SEAN HAUPT |
| Re-Activate Permit | 11/10/2021 | SEAN HAUPT |
| CofO in Progress | 11/10/2021 | ROBERT GOLD |
| Permit Finaled | 11/17/2021 | MICHAEL SMITH |
| CofO Issued | 11/17/2021 | MICHAEL SMITH |
| Permit Finaled | 11/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2020 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2020 | JOHN LIN |
| Sewer availability | Cleared | 3/16/2020 | JOHN LIN |
| Metro Rail approval | Cleared | 4/7/2020 | SERGIO MUNIZ |
| Construction near power lines | Cleared | 5/17/2020 | RIDWAN HARDY |
| ZI | Cleared | 6/19/2020 | HERMINIGILDO AGUSTIN |
| Low Impact Development | Cleared | 8/25/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/1/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 9/4/2020 | AARON COSTA |
| Hydrant and Access approval | Cleared | 9/16/2020 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/30/2020 | Partial Inspection | PAUL CHOPP |
| Underground Mechanical | 12/30/2020 | Corrections Issued | PAUL CHOPP |
| PLUMBING-Rough | 1/11/2021 | Partial Approval | VINCENT HANLEY |
| Sewer | 1/11/2021 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 1/21/2021 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 1/21/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2021 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 2/10/2021 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 2/10/2021 | Approved | STEVEN BACK |
| Green Building Rough | 2/10/2021 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 2/10/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 2/10/2021 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 2/10/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 3/22/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 3/22/2021 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 3/31/2021 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 3/31/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 3/31/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 3/31/2021 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 4/7/2021 | Approved | STEVEN BACK |
| HVAC-Final | 4/7/2021 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 4/7/2021 | Approved | STEVEN BACK |
| Insulation | 4/13/2021 | Corrections Issued | STEVEN BACK |
| Drywall Nailing | 4/28/2021 | Corrections Issued | STEVEN BACK |
| Insulation | 4/28/2021 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 4/28/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 5/4/2021 | Approved | STEVEN BACK |
| Final | 5/4/2021 | Corrections Issued | STEVEN BACK |
| Insulation | 5/4/2021 | Approved | STEVEN BACK |
| Underground Mechanical | 5/4/2021 | Approved | STEVEN BACK |
| Final | 7/27/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 7/27/2021 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 7/27/2021 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 7/27/2021 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 7/27/2021 | Approved | STEVEN BACK |
| Final | 8/20/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 8/20/2021 | Approved | STEVEN BACK |
| Service/Power Release | 8/20/2021 | Not Ready for Inspection | STEVEN BACK |
| Final | 10/18/2021 | OK to Issue CofO | SEAN HAUPT |
| Service/Power Release | 10/18/2021 | Approved | SEAN HAUPT |