Permit Issued
Issued on 11/2/2020
Issuing Office
Current Status
CofO Issued on 11/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 SERGIO MUNIZ
Green Plans Picked Up 2/27/2020 APPLICANT
Corrections Issued 3/4/2020 SERGIO MUNIZ
Quality Review Completed 3/11/2020 STEVEN KIM
Building Plans Picked Up 3/12/2020 APPLICANT
Applicant returned to address corrections 5/15/2020 SERGIO MUNIZ
Applicant returned to address corrections 9/25/2020 SERGIO MUNIZ
Plan Check Approved 10/19/2020 SERGIO MUNIZ
Issued 11/2/2020 APPLICANT
Permit Closed-Status Void 10/18/2021 SEAN HAUPT
Re-Activate Permit 11/10/2021 SEAN HAUPT
CofO in Progress 11/10/2021 ROBERT GOLD
Permit Finaled 11/17/2021 MICHAEL SMITH
CofO Issued 11/17/2021 MICHAEL SMITH
Permit Finaled 11/17/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/16/2020 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 3/16/2020 JOHN LIN
Sewer availability Cleared 3/16/2020 JOHN LIN
Metro Rail approval Cleared 4/7/2020 SERGIO MUNIZ
Construction near power lines Cleared 5/17/2020 RIDWAN HARDY
ZI Cleared 6/19/2020 HERMINIGILDO AGUSTIN
Low Impact Development Cleared 8/25/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/1/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 9/4/2020 AARON COSTA
Hydrant and Access approval Cleared 9/16/2020 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/30/2020 Partial Inspection PAUL CHOPP
Underground Mechanical 12/30/2020 Corrections Issued PAUL CHOPP
PLUMBING-Rough 1/11/2021 Partial Approval VINCENT HANLEY
Sewer 1/11/2021 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 1/21/2021 Approved VINCENT HANLEY
Footing/Foundation/Slab 1/21/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/2/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 2/10/2021 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 2/10/2021 Approved STEVEN BACK
Green Building Rough 2/10/2021 Not Ready for Inspection STEVEN BACK
HVAC-Rough 2/10/2021 Corrections Issued STEVEN BACK
PLUMBING-Rough 2/10/2021 Approved STEVEN BACK
Verify Sprinkler Sign Off 2/10/2021 Approved STEVEN BACK
ELECTRICAL-Rough 3/22/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/22/2021 Approved STEVEN BACK
HVAC-Rough 3/22/2021 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 3/31/2021 Not Ready for Inspection STEVEN BACK
Green Building Rough 3/31/2021 Approved STEVEN BACK
HVAC-Rough 3/31/2021 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 3/31/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 4/7/2021 Approved STEVEN BACK
HVAC-Final 4/7/2021 Corrections Issued STEVEN BACK
HVAC-Rough 4/7/2021 Approved STEVEN BACK
Insulation 4/13/2021 Corrections Issued STEVEN BACK
Drywall Nailing 4/28/2021 Corrections Issued STEVEN BACK
Insulation 4/28/2021 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 4/28/2021 Approved STEVEN BACK
Drywall Nailing 5/4/2021 Approved STEVEN BACK
Final 5/4/2021 Corrections Issued STEVEN BACK
Insulation 5/4/2021 Approved STEVEN BACK
Underground Mechanical 5/4/2021 Approved STEVEN BACK
Final 7/27/2021 Corrections Issued STEVEN BACK
Green Building Final 7/27/2021 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 7/27/2021 SGSOV Approved STEVEN BACK
Service/Power Release 7/27/2021 Not Ready for Inspection STEVEN BACK
Smoke Detectors 7/27/2021 Approved STEVEN BACK
Final 8/20/2021 Corrections Issued STEVEN BACK
Green Building Final 8/20/2021 Approved STEVEN BACK
Service/Power Release 8/20/2021 Not Ready for Inspection STEVEN BACK
Final 10/18/2021 OK to Issue CofO SEAN HAUPT
Service/Power Release 10/18/2021 Approved SEAN HAUPT