910 1/2 W 62ND ST 90044
Certificate Information: 910 1/2 W 62ND ST 90044
- Application / Permit
- 20010-20000-00078
- Plan Check / Job No.
- B20VN00622
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT (26'-5" X 30') PER GCS 65852.2(e)(1)(B) & LAMC 12.22 A.33(c),(d),(g) AND WFPP
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2020 | APPLICANT |
| Green Plans Picked Up | 2/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 3/9/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/11/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 3/13/2020 | APPLICANT |
| Plan Check Approved | 10/22/2020 | NILOOFAR MEHRAIN |
| Issued | 12/23/2020 | APPLICANT |
| CofO in Progress | 9/3/2021 | JOAQUIN GREENOUGH |
| Permit Finaled | 9/25/2021 | DEROLD HAUFF |
| CofO Issued | 9/25/2021 | DEROLD HAUFF |
| Permit Finaled | 9/25/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 4/1/2020 | MICHAEL AYERS |
| Community Plan Implem. Overlay | Cleared | 5/18/2020 | HELEN JADALI |
| ZI | Cleared | 5/18/2020 | HELEN JADALI |
| Address approval | Cleared | 7/13/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 7/13/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2020 | JEANIE LAM |
| Sewer availability | Cleared | 7/15/2020 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 7/16/2020 | SAM NAVID |
| Low Impact Development | Cleared | 10/1/2020 | ORVAL HERNANDEZ-MARCI |
| Permit | Cleared | 10/2/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 10/2/2020 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/29/2020 | Partial Approval | ROBERT MCDOWELL |
| Sewer | 12/29/2020 | Approved | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 1/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 1/7/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 1/15/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 2/9/2021 | Conditional Approval | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 2/9/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 2/9/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| HVAC-Rough | 2/9/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 2/9/2021 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 2/9/2021 | Conditional Approval | ROBERT MCDOWELL |
| Insulation | 2/18/2021 | Partial Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/18/2021 | Conditional Approval | FREDDIE RIVERA |
| Drywall Nailing | 2/25/2021 | Approved | ROBERT MCDOWELL |
| Gas Test | 3/22/2021 | Not Ready for Inspection | DAVID FEILER |
| Service/Power Release | 3/22/2021 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 4/8/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Final | 4/8/2021 | Corrections Issued | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Green Building Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 4/8/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 4/8/2021 | SGSOV Not Ready | ROBERT MCDOWELL |
| Service/Power Release | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Final | 5/4/2021 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 5/4/2021 | SGSOV Approved | FREDDIE RIVERA |
| Final | 8/13/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 8/24/2021 | Corrections Issued | DAVID FEILER |
| Final | 8/31/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 9/2/2021 | OK to Issue CofO | JOAQUIN GREENOUGH |