17603 W CAPRINO PL 91406
Certificate Information: 17603 W CAPRINO PL 91406
- Application / Permit
- 20010-20000-00059
- Plan Check / Job No.
- B20VN00475
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 42' X 28'-6"1-STORY ACCESSORY DWELLING UNIT PER WOOD FRAME PRESCRIPTIVE PROVISION.
- Permit Issued
- Issued on 4/6/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/26/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2020 | APPLICANT |
| Green Plans Picked Up | 2/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | SERGIO MUNIZ |
| Corrections Issued | 3/2/2020 | SERGIO MUNIZ |
| Quality Review Completed | 3/9/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 3/9/2020 | APPLICANT |
| Plan Check Approved | 4/1/2020 | SERGIO MUNIZ |
| Issued | 4/6/2020 | LADBS |
| CofO in Progress | 12/14/2020 | ARTHUR SARGSYAN |
| CofO in Progress | 12/14/2020 | ARTHUR SARGSYAN |
| Permit Finaled | 12/26/2020 | MICHAEL SMITH |
| CofO Issued | 12/26/2020 | MICHAEL SMITH |
| Permit Finaled | 12/26/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 2/20/2020 | AARON COSTA |
| Address approval | Cleared | 3/5/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/9/2020 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 3/10/2020 | GEORGE SUCHAND |
| Construction near power lines | Cleared | 3/16/2020 | TORI CHEN |
| Low Impact Development | Cleared | 3/16/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/16/2020 | JOHN LIN |
Contact Information
| Contractor | Aspen Custom Millworks Inc; Lic. No.: 980047-B | 16147 COHASSET ST VAN NUYS, CA 91406 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/16/2020 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 4/27/2020 | Approved | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2020 | Partial Approval | BEAU COLLINS |
| BUILDING-Rough-Frame | 6/10/2020 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 6/10/2020 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 6/10/2020 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 6/10/2020 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 6/15/2020 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 6/15/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 6/15/2020 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/17/2020 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/17/2020 | Approved | MISAEL ESPARZA |
| Green Building Rough | 6/17/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/23/2020 | Approved | WILLIAM KUEHN |
| HVAC-Rough | 6/23/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 6/23/2020 | Partial Inspection | WILLIAM KUEHN |
| Insulation | 6/24/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 6/30/2020 | Approved | ROBERT MINASSIANS |
| Green Building Rough | 6/30/2020 | Approved | ROBERT MINASSIANS |
| Interior/Exterior Lathing | 6/30/2020 | Approved | ROBERT MINASSIANS |
| Underground Mechanical | 6/30/2020 | Approved | ROBERT MINASSIANS |
| Service/Power Release | 7/31/2020 | Approved | DANIEL DREW |
| Underground Mechanical | 7/31/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 8/12/2020 | Approved | MICHEL ABAJAN |
| HVAC-Final | 8/12/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 11/2/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/2/2020 | Approved | JENNIFER RABUCHIN |
| Gas Test | 11/2/2020 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 11/2/2020 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 11/2/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/2/2020 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/2/2020 | SGSOV Approved | JENNIFER RABUCHIN |
| Sewer | 11/2/2020 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 11/2/2020 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 11/2/2020 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 11/13/2020 | Approved | ARTHUR SARGSYAN |
| Final | 12/11/2020 | OK to Issue CofO | ARTHUR SARGSYAN |