13309 W TERRA BELLA ST 91331

Certificate Information: 13309 W TERRA BELLA ST 91331

Application / Permit
20010-20000-00058
Plan Check / Job No.
B20VN00471
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW, TWO STORY DETACHED ACCESSORY DWELLING UNIT [FIRST STORY: 21' x 36'-8", 2ND STORY: 21' x 23'] PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 1/7/2021
Issuing Office
Current Status
CofO Issued on 6/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2020 APPLICANT
Green Plans Picked Up 2/21/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 SEAN SHAHMIRI
Corrections Issued 2/28/2020 SEAN SHAHMIRI
Quality Review Completed 3/11/2020 OMID HEDAYAT
Building Plans Picked Up 3/11/2020 APPLICANT
Applicant returned to address corrections 12/7/2020 SEAN SHAHMIRI
Applicant returned to address corrections 12/30/2020 SEAN SHAHMIRI
Plan Check Approved 12/30/2020 SEAN SHAHMIRI
Issued 1/7/2021 APPLICANT
CofO in Progress 6/13/2023 MICHEL ABAJAN
CofO Issued 6/21/2023 MICHAEL SMITH
Permit Finaled 6/21/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/16/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/16/2020 LEE GUILBEAUX
Sewer availability Cleared 3/16/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 4/29/2020 GEORGE SUCHAND
Low Impact Development Cleared 10/20/2020 SARAH YOUSSEF
Green Code Cleared 11/5/2020 MICHAEL AYERS
Roof/Waste drainage to street Cleared 12/16/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/24/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 3/24/2022 Approved MICHEL ABAJAN
METHANE-Barrier 3/24/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 3/24/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/1/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 4/1/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/12/2022 Partial Approval MICHEL ABAJAN
Deputy Wood Construction 4/29/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/2/2022 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 5/31/2022 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 5/31/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/23/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 6/23/2022 Approved MICHEL ABAJAN
Green Building Rough 6/23/2022 Approved MICHEL ABAJAN
HVAC-Rough 6/23/2022 Approved MICHEL ABAJAN
METHANE-Rough 6/23/2022 Approved MICHEL ABAJAN
Underground Mechanical 6/23/2022 Partial Approval MICHEL ABAJAN
Verify Sprinkler Sign Off 6/23/2022 Approved MICHEL ABAJAN
Insulation 6/28/2022 Approved GREGG CUMMINGS
Drywall Nailing 7/8/2022 Approved MICHEL ABAJAN
Shower Pan 9/15/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/2/2023 Corrections Issued MICHEL ABAJAN
Final 3/2/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 3/2/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 3/2/2023 Approved MICHEL ABAJAN
PLUMBING-Final 3/2/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/2/2023 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 3/2/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 3/2/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/1/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 6/1/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 6/1/2023 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Service/Power Release 6/1/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 6/13/2023 Approved MICHEL ABAJAN
Final 6/13/2023 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/13/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 6/13/2023 Approved MICHEL ABAJAN