11969 W NEENACH ST 91352

Certificate Information: 11969 W NEENACH ST 91352

Application / Permit
20010-20000-00055
Plan Check / Job No.
B20VN00469
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 8/18/2020
Issuing Office
Current Status
CofO Issued on 5/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 RODNEY SAMIIAN
Corrections Issued 2/25/2020 RODNEY SAMIIAN
Quality Review Completed 2/26/2020 ABDUL CHEGENI
Building Plans Picked Up 2/28/2020 APPLICANT
Green Plans Picked Up 2/28/2020 APPLICANT
Applicant returned to address corrections 5/13/2020 RODNEY SAMIIAN
Plan Check Approved 7/23/2020 RODNEY SAMIIAN
Issued 8/18/2020 APPLICANT
CofO in Progress 2/20/2021 JOHN HAYES
Permit Finaled 5/8/2021 MICHAEL SMITH
CofO Issued 5/8/2021 MICHAEL SMITH
Permit Finaled 5/8/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/28/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 2/28/2020 GABRIEL ROBLES
Sewer availability Cleared 2/28/2020 GABRIEL ROBLES
ZI Cleared 2/28/2020 DANG NGUYEN
Green Code Cleared 3/6/2020 MICHAEL AYERS
Construction near power lines Cleared 5/13/2020 RIDWAN HARDY
Hydrant and Access approval Cleared 6/17/2020 MATTHEW CRAIG
Low Impact Development Cleared 7/16/2020 MITESH PATEL
Permit Cleared 7/21/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 7/21/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/19/2020 Approved BEAU COLLINS
Pre-Inspection 8/19/2020 Approved BEAU COLLINS
Excavation/Setback/Form/Re-Bar 8/20/2020 Approved MATTHEW NELSON
Footing/Foundation/Slab 8/20/2020 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 8/28/2020 Conditional Approval BEAU COLLINS
PLUMBING-Rough 8/28/2020 Not Ready for Inspection BEAU COLLINS
Wood Frame 8/28/2020 Partial Approval BEAU COLLINS
HVAC-Rough 8/31/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 8/31/2020 Approved MATTHEW NELSON
ELECTRICAL-Rough 9/3/2020 Approved MATTHEW NELSON
PLUMBING-Rough 9/3/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 9/4/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 9/4/2020 Approved JENNIFER RABUCHIN
Green Building Rough 9/4/2020 Approved JENNIFER RABUCHIN
HVAC-Rough 9/4/2020 Approved JENNIFER RABUCHIN
Insulation 9/4/2020 Approved JENNIFER RABUCHIN
MERV13>=Rough 9/4/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 9/4/2020 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 9/4/2020 Approved JENNIFER RABUCHIN
Wood Frame 9/4/2020 Approved JENNIFER RABUCHIN
Drywall Nailing 9/8/2020 Approved DAVID MATSON
Gas Test 9/8/2020 Not Ready for Inspection DAVID MATSON
Interior/Exterior Lathing 9/8/2020 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Final 2/3/2021 Not Ready for Inspection JOHN HAYES
Final 2/3/2021 Corrections Issued JOHN HAYES
Green Building Final 2/3/2021 Not Ready for Inspection JOHN HAYES
HVAC-Final 2/3/2021 Not Ready for Inspection JOHN HAYES
MERV13>=Final 2/3/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 2/3/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/3/2021 SGSOV Not Ready JOHN HAYES
Service/Power Release 2/3/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 2/3/2021 Not Ready for Inspection JOHN HAYES
Final 2/11/2021 Corrections Issued JOHN HAYES
Gas Test 2/11/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 2/11/2021 Not Ready for Inspection JOHN HAYES
MERV13>=Final 2/11/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/11/2021 SGSOV Not Ready JOHN HAYES
Service/Power Release 2/11/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 2/11/2021 Not Ready for Inspection JOHN HAYES
Final 2/19/2021 OK to Issue CofO JOHN HAYES
Green Building Final 2/19/2021 Approved JOHN HAYES
MERV13>=Final 2/19/2021 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/19/2021 SGSOV Approved JOHN HAYES
Service/Power Release 2/19/2021 Approved JOHN HAYES
Smoke Detectors 2/19/2021 Approved JOHN HAYES