7505 N HESPERIA AVE 91335

Certificate Information: 7505 N HESPERIA AVE 91335

Application / Permit
20010-20000-00052
Plan Check / Job No.
B20VN00449
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
(N) 1-STORY ACCESSORY LIVING QUARTERS (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 2/16/2021
Issuing Office
Valley
Current Status
CofO Issued on 6/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 NILOOFAR MEHRAIN
Corrections Issued 2/27/2020 NILOOFAR MEHRAIN
Quality Review Completed 2/27/2020 GUANG MIN TUNG
Building Plans Picked Up 3/2/2020 APPLICANT
Green Plans Picked Up 3/2/2020 APPLICANT
Plan Check Approved 5/5/2020 NILOOFAR MEHRAIN
Issued 2/16/2021 APPLICANT
CofO in Progress 6/7/2022 VINCENT HANLEY
Permit Finaled 6/22/2022 MICHAEL SMITH
CofO Issued 6/22/2022 MICHAEL SMITH
Permit Finaled 6/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/6/2020 ROBERT DUFF
Eng Process Fee Ord 176,300 Cleared 3/10/2020 GUILLERMO PETRA
Sewer availability Cleared 3/10/2020 GUILLERMO PETRA
Green Code Cleared 3/19/2020 DAVID MATSON
Low Impact Development Cleared 4/24/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 4/29/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/5/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/15/2021 Partial Approval VINCENT HANLEY
PLUMBING-Rough 3/15/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/19/2021 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/25/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 4/9/2021 Approved VINCENT HANLEY
PLUMBING-Rough 4/9/2021 Approved VINCENT HANLEY
Sewer 4/9/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/23/2021 Approved VINCENT HANLEY
Green Building Rough 7/23/2021 Approved VINCENT HANLEY
Insulation 7/23/2021 Approved VINCENT HANLEY
Shower Pan 7/23/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 7/23/2021 Approved VINCENT HANLEY
Drywall Nailing 9/20/2021 Approved VINCENT HANLEY
Final 9/20/2021 Not Ready for Inspection VINCENT HANLEY
Interior/Exterior Lathing 9/20/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/20/2021 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 9/20/2021 Not Ready for Inspection VINCENT HANLEY
Final 4/28/2022 Corrections Issued VINCENT HANLEY
Green Building Final 4/28/2022 Approved VINCENT HANLEY
HVAC-Final 4/28/2022 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/28/2022 SGSOV Approved VINCENT HANLEY
Service/Power Release 4/28/2022 Corrections Issued VINCENT HANLEY
Smoke Detectors 4/28/2022 Approved VINCENT HANLEY
Final 5/23/2022 Not Ready for Inspection VINCENT HANLEY
Service/Power Release 5/23/2022 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 6/7/2022 Approved VINCENT HANLEY
Final 6/7/2022 OK to Issue CofO VINCENT HANLEY
HVAC-Final 6/7/2022 Approved VINCENT HANLEY
PLUMBING-Final 6/7/2022 Approved VINCENT HANLEY
Service/Power Release 6/7/2022 Approved VINCENT HANLEY