9500 W CHEROKEE LANE 90210

Certificate Information: 9500 W CHEROKEE LANE 90210

Application / Permit
20010-20000-00035
Plan Check / Job No.
B20VN00321
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage Building
Work Description
NEW 6' X 6'-10" STORAGE SHED PER ZA-2019-3607-ZAA
Permit Issued
Issued on 9/10/2020
Issuing Office
Current Status
CofO Issued on 4/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2020 APPLICANT
Assigned to Plan Check Engineer 1/8/2020 ROSENDO MEDINA
Corrections Issued 1/8/2020 ROSENDO MEDINA
Applicant returned to address corrections 8/21/2020 LUIS RINCON
Plan Check Approved 9/10/2020 YAQUB MIRZA
Issued 9/10/2020 APPLICANT
CofO in Progress 3/19/2021 RAUL BARAJAS
Permit Finaled 4/14/2021 DEROLD HAUFF
Permit Finaled 4/14/2021 DEROLD HAUFF
CofO Issued 4/14/2021 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 2/20/2020 SARAH GOLDMAN
ZA Case Cleared 2/20/2020 SARAH GOLDMAN
Eng Process Fee Ord 176,300 Cleared 2/21/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 2/21/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 8/31/2020 PATRICK MISCHLICH

Contact Information

Architect Soler,, Jeffrey Robert; Lic. No.: C30180 619 N KILKEA DRIVE      LOS ANGELES, CA 90048
Contractor Streamline Construction; Lic. No.: 923202-B 7819 LAUREL CANYON BLVD      NORTH HOLLYWOOD, CA 91605

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/18/2020 Not Ready for Inspection BRAD BESCOS
Footing/Foundation/Slab 9/28/2020 Not Ready for Inspection COREY HUPP
Excavation/Setback/Form/Re-Bar 10/2/2020 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 10/2/2020 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 10/19/2020 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 10/29/2020 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/29/2020 Approved RAUL BARAJAS
Green Building Rough 10/29/2020 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 10/29/2020 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 10/30/2020 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 2/5/2021 SGSOV Not Ready RAUL BARAJAS
Special/Order Compliance 2/19/2021 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 3/18/2021 Approved RAUL BARAJAS
Drywall Nailing 3/18/2021 Approved RAUL BARAJAS
Final 3/18/2021 OK to Issue CofO RAUL BARAJAS
Footing/Foundation/Slab 3/18/2021 Approved RAUL BARAJAS
Green Building Final 3/18/2021 Approved RAUL BARAJAS
Green Building Rough 3/18/2021 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/18/2021 SGSOV Approved RAUL BARAJAS
Service/Power Release 3/18/2021 Approved RAUL BARAJAS
Smoke Detectors 3/18/2021 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 3/18/2021 Approved RAUL BARAJAS