9737 N BURNET AVE 91343
Certificate Information: 9737 N BURNET AVE 91343
- Application / Permit
- 20010-20000-00026
- Plan Check / Job No.
- B20VN00261
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- New 16' x 31' 1-story NFPA13-D sprinkler throughout Accessory Living Quarters per WFPP
- Permit Issued
- Issued on 1/13/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/19/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2020 | ANGELICA DAVE |
| Corrections Issued | 1/8/2020 | ANGELICA DAVE |
| Plan Check Approved | 1/13/2020 | ALDOUS CHIC |
| Issued | 1/13/2020 | LADBS |
| CofO in Progress | 7/13/2020 | JENNIFER RABUCHIN |
| Permit Finaled | 8/19/2020 | MICHAEL SMITH |
| CofO Issued | 8/19/2020 | MICHAEL SMITH |
| Permit Finaled | 8/19/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/8/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/8/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/8/2020 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 1/8/2020 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 1/13/2020 | GEORGE SUCHAND |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/27/2020 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/4/2020 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2020 | Partial Approval | ROBERT MINASSIANS |
| ELECTRICAL-Rough | 3/5/2020 | Approved | RAYMOND KEHOE |
| HVAC-Rough | 3/5/2020 | Approved | RAYMOND KEHOE |
| PLUMBING-Rough | 3/5/2020 | Approved | RAYMOND KEHOE |
| BUILDING-Rough-Frame | 4/17/2020 | Partial Approval | JENNIFER RABUCHIN |
| Gas Test | 4/17/2020 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 4/17/2020 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/17/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/17/2020 | Partial Approval | JENNIFER RABUCHIN |
| MERV13>=Rough | 4/17/2020 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 4/30/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/30/2020 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/3/2020 | Partial Approval | MATTHEW NUCKOLLS |
| Final | 7/3/2020 | Corrections Issued | MATTHEW NUCKOLLS |
| Footing/Foundation/Slab | 7/3/2020 | Approved | MATTHEW NUCKOLLS |
| Green Building Final | 7/3/2020 | Approved | MATTHEW NUCKOLLS |
| SGSOV-Seismic Gas S/O Valve | 7/3/2020 | SGSOV Approved | MATTHEW NUCKOLLS |
| Service/Power Release | 7/3/2020 | Approved | MATTHEW NUCKOLLS |
| Smoke Detectors | 7/3/2020 | Approved | MATTHEW NUCKOLLS |
| Verify Sprinkler Sign Off | 7/3/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| BUILDING-Rough-Frame | 7/13/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/13/2020 | Approved | JENNIFER RABUCHIN |
| Final | 7/13/2020 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 7/13/2020 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 7/13/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/13/2020 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 7/13/2020 | Approved | JENNIFER RABUCHIN |