1666 W JEFFERSON BLVD 90018

Certificate Information: 1666 W JEFFERSON BLVD 90018

Application / Permit
20010-20000-00010
Plan Check / Job No.
B20VN00052
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 30' X 20'-6" ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
Permit Issued
Issued on 12/22/2021
Issuing Office
Valley
Current Status
CofO Issued on 5/31/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2020 APPLICANT
Green Plans Picked Up 2/7/2020 APPLICANT
Assigned to Plan Check Engineer 2/14/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 2/18/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 2/26/2020 OMID HEDAYAT
Building Plans Picked Up 3/18/2020 APPLICANT
Applicant returned to address corrections 11/15/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 12/21/2021 SEWADA ZADOORAN MILAGARDI
Issued 12/22/2021 APPLICANT
CofO in Progress 5/30/2026 SABAS ALONSO
Permit Finaled 5/31/2026 DEROLD HAUFF
CofO Issued 5/31/2026 DEROLD HAUFF
Permit Finaled 5/31/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/25/2020 JEANIE LAM
Sewer availability Cleared 7/8/2020 WALLIE JONG
Highway dedication Cleared 8/19/2020 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 8/26/2020 WALLIE JONG
Construction near power lines Cleared 10/13/2020 RIDWAN HARDY
Hydrant and Access approval Cleared 11/16/2020 MATTHEW CRAIG
Low Impact Development Cleared 5/28/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/28/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Stewart,, Carl William; Lic. No.: C86681 8811 GENTLE WIND DR      CORONA, CA 92883

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/11/2022 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 4/11/2022 Conditional Approval JOAQUIN GREENOUGH
METHANE-Barrier 4/11/2022 Approved JOAQUIN GREENOUGH
METHANE-Subgrade 4/11/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 5/2/2022 Partial Approval SABAS ALONSO
Sewer 5/2/2022 Approved SABAS ALONSO
Wood Frame 5/2/2022 Partial Approval SABAS ALONSO
Wood Frame 5/10/2022 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/13/2022 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 6/23/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Partial Inspection SABAS ALONSO
Green Building Rough 6/23/2022 Corrections Issued SABAS ALONSO
HVAC-Rough 6/23/2022 Approved SABAS ALONSO
PLUMBING-Rough 6/23/2022 Corrections Issued SABAS ALONSO
Underground Mechanical 6/23/2022 Partial Approval SABAS ALONSO
Wood Frame 6/23/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 6/29/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/29/2022 Approved SABAS ALONSO
Green Building Rough 6/29/2022 Approved SABAS ALONSO
METHANE-Rough 6/29/2022 Approved SABAS ALONSO
PLUMBING-Rough 6/29/2022 Approved SABAS ALONSO
Verify Sprinkler Sign Off 6/29/2022 Approved SABAS ALONSO
Insulation 7/7/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 7/7/2022 Partial Approval SABAS ALONSO
Drywall Nailing 7/13/2022 Approved LILIANA PORTILLO
Shower Pan 7/13/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 8/3/2022 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 8/8/2022 Approved SABAS ALONSO
Service/Power Release 8/16/2022 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 9/26/2022 Not Ready for Inspection SABAS ALONSO
PLUMBING-Final 9/26/2022 Approved SABAS ALONSO
Final 10/24/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 10/24/2022 Approved SABAS ALONSO
Green Building Final 10/24/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/24/2022 SGSOV Approved SABAS ALONSO
Service/Power Release 10/24/2022 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 10/24/2022 Not Ready for Inspection SABAS ALONSO
Service/Power Release 11/1/2022 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 11/29/2022 Approved SABAS ALONSO
Final 3/15/2023 Corrections Issued SABAS ALONSO
Final 3/22/2023 Not Ready for Inspection ENRIQUE MIRELES
Service/Power Release 3/22/2023 Not Required ENRIQUE MIRELES
Smoke Detectors 3/22/2023 Approved ENRIQUE MIRELES
Final 5/15/2023 Not Ready for Inspection SABAS ALONSO
Sewer 9/3/2025 Partial Inspection RONNIE MEDINA
Final 5/27/2026 OK to Issue CofO SABAS ALONSO