5261 N HERMOSA AVE 90041

Certificate Information: 5261 N HERMOSA AVE 90041

Application / Permit
20010-20000-00002
Plan Check / Job No.
B20VN00003
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story sfd w/att. garage. <sprinklers req'd throughout>
Permit Issued
Issued on 11/16/2020
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 ABDUL CHEGENI
Corrections Issued 2/18/2020 ABDUL CHEGENI
Quality Review Completed 2/21/2020 STEVEN KIM
Building Plans Picked Up 2/28/2020 APPLICANT
Green Plans Picked Up 2/28/2020 APPLICANT
Applicant returned to address corrections 6/29/2020 MOHAMMAD ESMAILI
Plan Check Approved 11/16/2020 MOHAMMAD ESMAILI
Issued 11/16/2020 APPLICANT
CofO in Progress 10/27/2021 CRAIG VAUGHAN
Permit Finaled 3/11/2022 DEROLD HAUFF
CofO Issued 3/11/2022 DEROLD HAUFF
Permit Finaled 3/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/13/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 3/13/2020 GABRIEL ROBLES
Permit Cleared 4/27/2020 CELINA MORENO
Tenant Habitability Plan Cleared 7/7/2020 MICHAEL GREGERSON
ZA Case Cleared 8/5/2020 HERMINIGILDO AGUSTIN
Hydrant and Access approval Cleared 8/10/2020 MATTHEW CRAIG
Low Impact Development Cleared 8/11/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/19/2020 CELINA MORENO
Sewer availability Cleared 8/19/2020 CELINA MORENO
GPI Written Notices Cleared 11/16/2020 ABDUL CHEGENI
Grading Pre-Inspection Cleared 11/16/2020 ABDUL CHEGENI

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/23/2020 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 12/3/2020 Corrections Issued CRAIG VAUGHAN
Special/Order Compliance 12/3/2020 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 12/8/2020 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 12/15/2020 Approved CRAIG VAUGHAN
Deputy Steel/Welding 1/11/2021 No Access for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 1/22/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 4/23/2021 Partial Approval CRAIG VAUGHAN
Green Building Rough 4/23/2021 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 4/23/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 4/26/2021 Partial Approval CRAIG VAUGHAN
HVAC-Rough 4/26/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 4/26/2021 Approved CRAIG VAUGHAN
Shower Pan 4/26/2021 Approved CRAIG VAUGHAN
Wood Frame 4/26/2021 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 4/29/2021 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/13/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 5/13/2021 Off-Hour Fees Due
ELECTRICAL-Rough 5/13/2021 Off-Hour Fees Due
ELECTRICAL-Rough 5/13/2021 Partial Approval CRAIG VAUGHAN
Green Building Rough 5/13/2021 Approved CRAIG VAUGHAN
Green Building Rough 5/13/2021 Off-Hour Fees Due
HVAC-Rough 5/13/2021 Approved CRAIG VAUGHAN
HVAC-Rough 5/13/2021 Off-Hour Fees Due
PLUMBING-Rough 5/13/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/13/2021 Off-Hour Fees Due
Insulation 5/19/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 5/26/2021 Partial Approval CRAIG VAUGHAN
Drywall Nailing 5/28/2021 Approved SCOTT FINNILA
Interior/Exterior Lathing 6/3/2021 Approved CRAIG VAUGHAN
Gas Test 9/8/2021 Approved ROBERT VORHIS
PLUMBING-Final 9/8/2021 Approved ROBERT VORHIS
ELECTRICAL-Final 10/20/2021 Partial Approval CRAIG VAUGHAN
HVAC-Final 10/20/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 10/20/2021 Approved CRAIG VAUGHAN
Final 10/21/2021 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 10/21/2021 Approved CRAIG VAUGHAN
Green Building Final 10/21/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/21/2021 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 10/21/2021 Approved CRAIG VAUGHAN
Smoke Detectors 10/21/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 10/26/2021 Approved CRAIG VAUGHAN
Final 10/26/2021 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 10/26/2021 Approved CRAIG VAUGHAN