1516 N STONE CANYON ROAD 90077
Certificate Information: 1516 N STONE CANYON ROAD 90077
- Application / Permit
- 20010-10001-02076
- Plan Check / Job No.
- B20LA17205
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- SUPPLEMENTAL TO PERMIT # 20010-10000-02076 GRADING FOR SFD
- Permit Issued
- Issued on 6/24/2021
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 3/23/2025
Permit Application Status History
| Submitted | 9/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 9/29/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 10/7/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 10/8/2020 | APPLICANT |
| Applicant returned to address corrections | 1/29/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 4/16/2021 | SERGIO GUTIERREZ |
| Issued | 6/24/2021 | APPLICANT |
| Permit Finaled | 3/21/2025 | MATTHEW JENKINS |
Permit Application Clearance Information
| Stormwater Pollution Mitigatn | Cleared | 11/24/2020 | JORGE MEJIA LEMUS |
| Miscellaneous | Cleared | 12/21/2020 | ANNA VIDAL |
| Excavation more than 5-ft deep | Cleared | 4/16/2021 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 4/16/2021 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 4/16/2021 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Mc Coy Peter Construction; Lic. No.: 493592-B | 9777 WILSHIRE BLVD #902 BEVERLY HILLS, CA 90212 |
| Engineer | Fiorelli,, Diane Marie; Lic. No.: GE3042 | 318 N WINNIPEG PLACE LONG BEACH, CA 90814 |
| Engineer | Hodson,, Donald Joseph; Lic. No.: C78817 | 288 TAMARIND LANE DANVILLE, CA 94526 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 7/2/2021 | Not Ready for Inspection | AL GAMBLE |
| Initial Grading | 7/12/2021 | Approved | BRIAN OLSON |
| Deputy Grading | 7/16/2021 | Approved | JONATHAN HOM |
| Excavation | 7/21/2021 | Corrections Issued | MATTHEW JENKINS |
| Deputy Grading | 7/22/2021 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 7/23/2021 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 7/26/2021 | Partial Inspection | MATTHEW JENKINS |
| Deputy Grading | 7/27/2021 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 7/28/2021 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 7/29/2021 | Partial Approval | MATTHEW JENKINS |
| Deputy Grading | 7/30/2021 | Partial Approval | MATTHEW JENKINS |
| Excavation | 8/2/2021 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 8/11/2021 | Approved | VASIL MIHALEV |
| Excavation | 8/16/2021 | Partial Approval | JONATHAN HOM |
| Fill/Backfill | 8/16/2021 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 8/16/2021 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 8/19/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Sub-Drain | 8/24/2021 | Partial Approval | BRIAN OLSON |
| Fill/Backfill | 9/2/2021 | Partial Approval | JONATHAN HOM |
| Excavation | 10/13/2021 | Partial Approval | JONATHAN HOM |
| Excavation | 10/18/2021 | Not Ready for Inspection | CHARLES POWELL |
| Bottom/Toe | 10/19/2021 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 11/4/2021 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 11/19/2021 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 12/21/2021 | Partial Approval | CHARLES POWELL |
| Deputy Other (see comments) | 12/28/2021 | Partial Approval | CHARLES POWELL |
| Rough | 12/28/2021 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 1/12/2022 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 1/18/2022 | Not Ready for Inspection | MATTHEW JENKINS |
| Bottom/Toe | 1/24/2022 | Partial Approval | CHARLES POWELL |
| Excavation | 2/1/2022 | Partial Approval | CHARLES POWELL |
| Excavation | 2/3/2022 | Partial Approval | CHARLES POWELL |
| Excavation | 2/9/2022 | Partial Approval | CHARLES POWELL |
| Approved Compaction Report | 2/28/2022 | Partial Approval | CHARLES POWELL |
| Fill/Backfill | 3/8/2022 | Not Ready for Inspection | CHARLES POWELL |
| Sub-Drain | 3/8/2022 | Partial Approval | CHARLES POWELL |
| Fill/Backfill | 4/15/2022 | Not Ready for Inspection | CHARLES POWELL |
| Sub-Drain | 5/24/2022 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 6/8/2022 | Partial Approval | CHARLES POWELL |
| Excavation | 6/13/2022 | Partial Approval | CHARLES POWELL |
| Approved Compaction Report | 6/16/2022 | Partial Approval | CHARLES POWELL |
| Excavation | 6/16/2022 | Partial Approval | CHARLES POWELL |
| Special/Order Compliance | 6/16/2022 | Partial Inspection | MICHAEL TEMPLE |
| Drainage Devices/Catch Basin | 6/22/2022 | Partial Approval | MICHAEL TEMPLE |
| Excavation | 6/30/2022 | Partial Approval | ALEXANDER HELFER |
| Approved Compaction Report | 7/6/2022 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 8/2/2022 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 8/11/2022 | Partial Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 8/11/2022 | Approved | CHARLES POWELL |
| Sub-Drain | 9/26/2022 | Partial Approval | CHARLES POWELL |
| Special/Order Compliance | 10/5/2022 | Partial Inspection | TIMOTHY POWELL |
| Bottom/Toe | 2/9/2023 | Not Ready for Inspection | CHARLES POWELL |
| FLOOD-Proofing Certificate | 2/16/2023 | Not Ready for Inspection | CHARLES POWELL |
| Rough | 2/16/2023 | Partial Approval | CHARLES POWELL |
| Sub-Drain | 4/11/2023 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 10/16/2023 | Approved | CHARLES POWELL |
| FLOOD-Proofing Certificate | 10/16/2023 | Not Ready for Inspection | CHARLES POWELL |
| Final | 10/16/2023 | Not Ready for Inspection | CHARLES POWELL |
| Rough | 10/16/2023 | Not Ready for Inspection | CHARLES POWELL |
| Approved Compaction Report | 2/5/2025 | Corrections Issued | MATTHEW JENKINS |
| Approved Compaction Report | 3/3/2025 | Approved | MATTHEW JENKINS |
| Final | 3/21/2025 | Permit Finaled | MATTHEW JENKINS |
| Rough | 3/21/2025 | Approved | MATTHEW JENKINS |