11277 N CHIVERS AVE 91331

Certificate Information: 11277 N CHIVERS AVE 91331

Application / Permit
20010-10000-05140
Plan Check / Job No.
B20LA24334
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**eplan** PROPOSED DETACHED 2-STORY ACCESSORY DWELLING UNIT WITH AN ATTACHED 2-CAR GARAGE PER ORDINANCE.
Permit Issued
Issued on 12/3/2021
Issuing Office
Current Status
CofO Issued on 4/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 MICHAEL LOPEZ
Corrections Issued 2/8/2021 MICHAEL LOPEZ
Quality Review Completed 2/21/2021 HERNAN ARREOLA
Applicant returned to address corrections 4/13/2021 MICHAEL LOPEZ
Applicant returned to address corrections 10/28/2021 MICHAEL LOPEZ
Applicant returned to address corrections 11/19/2021 MICHAEL LOPEZ
Plan Check Approved 11/29/2021 MICHAEL LOPEZ
Issued 12/3/2021 APPLICANT
CofO in Progress 4/19/2023 MICHEL ABAJAN
Permit Finaled 4/19/2023 MICHAEL SMITH
CofO Issued 4/19/2023 MICHAEL SMITH
Permit Finaled 4/19/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/24/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 2/24/2021 GABRIEL ROBLES
Sewer availability Cleared 2/24/2021 GABRIEL ROBLES
ZI Cleared 2/25/2021 MIGUEL GAMBOA
Hydrant and Access approval Cleared 4/23/2021 JOHN CONNEALLY
Low Impact Development Cleared 10/7/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/7/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng David; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/14/2022 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 1/25/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Partial Approval MICHEL ABAJAN
Deputy Wood Construction 6/27/2022 Conditional Approval MICHAEL SMITH
ELECTRICAL-Rough 6/29/2022 Corrections Issued CALEB MEISTER
HVAC-Rough 6/29/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 6/29/2022 Corrections Issued CALEB MEISTER
ELECTRICAL-Rough 7/5/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 7/5/2022 Partial Approval JACK KARGODORIAN
HVAC-Rough 7/5/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 7/5/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 7/11/2022 Approved MICHEL ABAJAN
Green Building Rough 7/11/2022 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 7/11/2022 Approved MICHEL ABAJAN
Insulation 8/18/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/18/2022 Approved MICHEL ABAJAN
Drywall Nailing 8/31/2022 Conditional Approval MISAEL ESPARZA
Drywall Nailing 9/1/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/28/2023 Not Ready for Inspection MICHEL ABAJAN
Final 3/28/2023 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 3/28/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 3/28/2023 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Final 3/28/2023 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/28/2023 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 3/28/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 3/28/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/6/2023 Approved MICHEL ABAJAN
Final 4/6/2023 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 4/6/2023 Approved MICHEL ABAJAN
HVAC-Final 4/6/2023 Approved MICHEL ABAJAN
PLUMBING-Final 4/6/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/6/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 4/6/2023 Approved MICHEL ABAJAN
Final 4/18/2023 OK to Issue CofO MICHEL ABAJAN