11277 N CHIVERS AVE 91331
Certificate Information: 11277 N CHIVERS AVE 91331
- Application / Permit
- 20010-10000-05140
- Plan Check / Job No.
- B20LA24334
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **eplan** PROPOSED DETACHED 2-STORY ACCESSORY DWELLING UNIT WITH AN ATTACHED 2-CAR GARAGE PER ORDINANCE.
- Permit Issued
- Issued on 12/3/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | MICHAEL LOPEZ |
| Corrections Issued | 2/8/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 2/21/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/13/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 10/28/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/19/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 11/29/2021 | MICHAEL LOPEZ |
| Issued | 12/3/2021 | APPLICANT |
| CofO in Progress | 4/19/2023 | MICHEL ABAJAN |
| Permit Finaled | 4/19/2023 | MICHAEL SMITH |
| CofO Issued | 4/19/2023 | MICHAEL SMITH |
| Permit Finaled | 4/19/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/24/2021 | GABRIEL ROBLES |
| ZI | Cleared | 2/25/2021 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 4/23/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 10/7/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/14/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/25/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2022 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 6/27/2022 | Conditional Approval | MICHAEL SMITH |
| ELECTRICAL-Rough | 6/29/2022 | Corrections Issued | CALEB MEISTER |
| HVAC-Rough | 6/29/2022 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 6/29/2022 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Rough | 7/5/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2022 | Partial Approval | JACK KARGODORIAN |
| HVAC-Rough | 7/5/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 7/5/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 7/11/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/11/2022 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 7/11/2022 | Approved | MICHEL ABAJAN |
| Insulation | 8/18/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 8/18/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 8/31/2022 | Conditional Approval | MISAEL ESPARZA |
| Drywall Nailing | 9/1/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 3/28/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 3/28/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 3/28/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 3/28/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 3/28/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/28/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 3/28/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 3/28/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/6/2023 | Approved | MICHEL ABAJAN |
| Final | 4/6/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 4/6/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 4/6/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/6/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/6/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 4/6/2023 | Approved | MICHEL ABAJAN |
| Final | 4/18/2023 | OK to Issue CofO | MICHEL ABAJAN |