701 W 164TH ST 90247
Certificate Information: 701 W 164TH ST 90247
- Application / Permit
- 20010-10000-05132
- Plan Check / Job No.
- B20LA24286
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NFPA 13D FIRE SPRINKLERS REQUIRED. NEW DETACHED ACCESSORY DWELLING UNIT AT REAR PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 3/24/2022
- Issuing Office
- Current Status
- CofO in Progress on 8/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | KEVIN MORALES |
| Corrections Issued | 2/16/2021 | KEVIN MORALES |
| Quality Review Completed | 2/19/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 12/29/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 1/12/2022 | KEVIN MORALES |
| Plan Check Approved | 3/1/2022 | KEVIN MORALES |
| Issued | 3/24/2022 | APPLICANT |
| CofO in Progress | 8/15/2025 | BEN MOLSTAD |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2021 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2021 | CHINH DINH |
| Sewer availability | Cleared | 5/18/2021 | CHINH DINH |
| Hydrant and Access approval | Cleared | 10/13/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/3/2021 | LONDY ALVARADO |
| Low Impact Development | Cleared | 12/3/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 12/14/2021 | JOSE HERNANDEZ |
Contact Information
| Contractor | Adu Guys.Com Inc The; Lic. No.: 1071442-B | 512 N AVALON BLVD WILMINGTON, CA 90744 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/11/2022 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 7/8/2022 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 7/8/2022 | Approved | JOHN KLARIN |
| Sewer | 7/8/2022 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 8/9/2022 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 8/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 8/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Rough | 8/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 8/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Sewer | 8/9/2022 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 8/9/2022 | Partial Approval | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 8/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/17/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 10/17/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Rough | 10/17/2022 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 10/17/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 10/17/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/27/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 10/27/2022 | Approved | JOHN KLARIN |
| Insulation | 11/4/2022 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 11/4/2022 | Approved | JOHN KLARIN |
| Special/Order Compliance | 11/4/2022 | Approved | JOHN KLARIN |
| Insulation | 11/9/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/16/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 11/16/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 2/3/2023 | Approved | JAMES CHAVEZ |
| Shower Pan | 2/3/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 12/29/2023 | Corrections Issued | JOHN KLARIN |
| Final | 12/29/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 12/29/2023 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 12/29/2023 | Approved | JOHN KLARIN |
| MERV13>=Final | 12/29/2023 | Approved | JOHN KLARIN |
| PLUMBING-Final | 12/29/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/29/2023 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 12/29/2023 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 12/29/2023 | Corrections Issued | JOHN KLARIN |
| Final | 4/11/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 4/11/2025 | Approved | BEN MOLSTAD |
| Service/Power Release | 4/11/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 4/11/2025 | Approved | BEN MOLSTAD |
| Final | 6/20/2025 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 6/20/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 8/7/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Service/Power Release | 8/7/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 8/12/2025 | Approved | BEN MOLSTAD |
| Final | 8/12/2025 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 8/12/2025 | Approved | BEN MOLSTAD |
| Final | 8/15/2025 | OK to Issue CofO | BEN MOLSTAD |
| Special/Order Compliance | 8/19/2025 | Corrections Issued | BEN MOLSTAD |