1533 N RONAN AVE 90744
Certificate Information: 1533 N RONAN AVE 90744
- Application / Permit
- 20010-10000-05129
- Plan Check / Job No.
- B20LA24281
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** PROPOSED DETACHED ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(B).
- Permit Issued
- Issued on 10/27/2021
- Issuing Office
- Current Status
- CofO Issued on 10/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | MICHAEL LOPEZ |
| Corrections Issued | 2/22/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 3/5/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/30/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 5/13/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/25/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 7/26/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 10/19/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 10/20/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 10/22/2021 | MICHAEL LOPEZ |
| Issued | 10/27/2021 | APPLICANT |
| CofO in Progress | 8/30/2022 | EUGENE CASSIDY |
| Permit Finaled | 10/29/2022 | DEROLD HAUFF |
| CofO Issued | 10/29/2022 | DEROLD HAUFF |
| Permit Finaled | 10/29/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 3/11/2021 | ERIK BEASLEY |
| CPC | Cleared | 4/20/2021 | MAXFIELD VERMY |
| CPC | Cleared | 4/20/2021 | MAXFIELD VERMY |
| ZA Case | Cleared | 4/20/2021 | MAXFIELD VERMY |
| ZA Case | Cleared | 4/20/2021 | MAXFIELD VERMY |
| ZI | Cleared | 4/20/2021 | MAXFIELD VERMY |
| Hydrant and Access approval | Cleared | 4/24/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/9/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/13/2021 | ERIK BEASLEY |
| Clean Up Green Up | Cleared | 9/14/2021 | MAXFIELD VERMY |
Contact Information
| Contractor | J M E Construction; Lic. No.: 921816-B | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/8/2021 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 12/8/2021 | Approved | JOHN KLARIN |
| METHANE-Barrier | 12/8/2021 | Approved | JOHN KLARIN |
| METHANE-Rough | 12/8/2021 | Partial Approval | JOHN KLARIN |
| METHANE-Subgrade | 12/8/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 12/8/2021 | Partial Approval | JOHN KLARIN |
| Underground Mechanical | 12/8/2021 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2022 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 1/31/2022 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 1/31/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 1/31/2022 | Approved | EUGENE CASSIDY |
| Wood Frame | 1/31/2022 | Approved | EUGENE CASSIDY |
| Insulation | 2/8/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 2/8/2022 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 2/16/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 2/16/2022 | Approved | EUGENE CASSIDY |
| Shower Pan | 2/16/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 5/25/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 5/25/2022 | Approved | EUGENE CASSIDY |
| Green Building Rough | 5/25/2022 | Approved | EUGENE CASSIDY |
| METHANE-Final | 5/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 5/25/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/25/2022 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 5/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 5/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 5/25/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/31/2022 | Approved | EUGENE CASSIDY |
| Final | 5/31/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Final | 5/31/2022 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 5/31/2022 | Approved | EUGENE CASSIDY |
| Service/Power Release | 5/31/2022 | Not Required | EUGENE CASSIDY |
| Smoke Detectors | 5/31/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 8/29/2022 | Approved | EUGENE CASSIDY |
| Final | 8/29/2022 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 8/29/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 8/29/2022 | Approved | EUGENE CASSIDY |