5335 1/4-1/2 E MONTE VISTA ST 90042
Certificate Information: 5335 1/4-1/2 E MONTE VISTA ST 90042
- Application / Permit
- 20010-10000-05124
- Plan Check / Job No.
- B20LA24244
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New construction of 2 ADU single story units of 1138 SF per State Law GCS 65852.2(e)(1) & LAMC 12.22 A.33(c)(d) and (g).
- Permit Issued
- Issued on 10/18/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2021 | ZAW HAN |
| Corrections Issued | 2/2/2021 | ZAW HAN |
| Quality Review Completed | 2/17/2021 | GARO TELMI |
| Building Plans Picked Up | 3/3/2021 | APPLICANT |
| Applicant returned to address corrections | 7/25/2022 | ZAW HAN |
| Applicant returned to address corrections | 8/15/2022 | ZAW HAN |
| Applicant returned to address corrections | 8/29/2022 | ZAW HAN |
| Plan Check Approved | 9/1/2022 | ZAW HAN |
| Issued | 10/18/2022 | APPLICANT |
| CofO in Progress | 2/28/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
| CofO Issued | 3/20/2025 | DEROLD HAUFF |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/11/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2021 | CINDY QI |
| Sewer availability | Cleared | 12/20/2021 | CINDY QI |
| Highway dedication | Cleared | 2/8/2022 | CINDY QI |
| Permit | Cleared | 2/8/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 3/8/2022 | CINDY JOSSELYN |
| Grading Pre-Inspection | Cleared | 3/16/2022 | VASIL MIHALEV |
| Tenant Habitability Plan | Cleared | 3/17/2022 | MICHAEL SOTO |
| HPOZ | Cleared | 3/21/2022 | MELISSA JONES |
| Hist. Property Cntrct Mgr Appr | Cleared | 3/21/2022 | MELISSA JONES |
| ZI | Cleared | 3/21/2022 | MELISSA JONES |
| Low Impact Development | Cleared | 6/17/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/21/2022 | CINDY QI |
| Specific Plan | Cleared | 7/14/2022 | NICOLE SANCHEZ |
| GPI Written Notices | Cleared | 7/25/2022 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chui,, Vincent Michael; Lic. No.: S5374 | 1234 S GARFIELD AVE STE 204 ALHAMBRA, CA 91801 |
| Engineer | Lee,, Jack C; Lic. No.: L8407 | 576 E LAMBERT RD BREA, CA 92821 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/22/2023 | Corrections Issued | OSVALDO PARAMO |
| Sewer | 5/22/2023 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/26/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Sewer | 6/26/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 6/30/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 6/30/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 7/21/2023 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/21/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2023 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 10/17/2023 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 10/17/2023 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Rough | 10/17/2023 | Not Ready for Inspection | ROY SPAULDING |
| Verify Sprinkler Sign Off | 10/17/2023 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 11/20/2023 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 11/20/2023 | Approved | SCOTT FINNILA |
| Green Building Rough | 11/20/2023 | Approved | SCOTT FINNILA |
| HVAC-Rough | 11/20/2023 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 11/20/2023 | Approved | SCOTT FINNILA |
| Insulation | 1/19/2024 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 1/19/2024 | Partial Approval | AMY COLIN |
| Drywall Nailing | 1/30/2024 | Approved | HAMIK HARTOUNIAN |
| Sewer | 7/26/2024 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 7/26/2024 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 8/5/2024 | Partial Approval | LILIANA PORTILLO |
| Service/Power Release | 10/10/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 11/6/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 11/15/2024 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Final | 1/16/2025 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Final | 1/16/2025 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 1/16/2025 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/20/2025 | Approved | THOMAS LOGRASSO |
| Final | 2/20/2025 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 2/20/2025 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 2/20/2025 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 2/20/2025 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 2/20/2025 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 2/27/2025 | Approved | NICHOLAS LOPEZ |
| Final | 2/27/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Service/Power Release | 2/27/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Final | 2/28/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Service/Power Release | 2/28/2025 | Approved | NICHOLAS LOPEZ |