2739 S OAKHURST AVE 90034
Certificate Information: 2739 S OAKHURST AVE 90034
- Application / Permit
- 20010-10000-05100
- Plan Check / Job No.
- B20LA24162
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE PER ENGINEER DESIGN (NFPA 13D THRUOUT)
- Permit Issued
- Issued on 7/15/2021
- Issuing Office
- Current Status
- CofO Issued on 3/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2021 | AUNG SOE |
| Corrections Issued | 1/25/2021 | AUNG SOE |
| Quality Review Completed | 1/26/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/28/2021 | AUNG SOE |
| Plan Check Approved | 6/30/2021 | AUNG SOE |
| Plan Check Approved | 7/15/2021 | AUNG SOE |
| Issued | 7/15/2021 | APPLICANT |
| Building Plans Picked Up | 7/19/2021 | APPLICANT |
| CofO in Progress | 2/23/2022 | OGANES TARAKHCHYAN |
| Permit Finaled | 3/7/2022 | DANIEL ORRANTE |
| CofO Issued | 3/7/2022 | DANIEL ORRANTE |
| Permit Finaled | 3/7/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 3/8/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 3/10/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 4/15/2021 | AUNG SOE |
| Hydrant and Access approval | Cleared | 4/29/2021 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 5/11/2021 | JOHN KIM |
| Low Impact Development | Cleared | 6/2/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/3/2021 | ANTHONY MAINEZ |
Contact Information
| Architect | Leishman,, Thomas Edward; Lic. No.: C15059 | 28100 RIDGEFERN COURT RANCHO PALOS VERDES, CA 90275 |
| Contractor | G M E Development; Lic. No.: 917664-B | 2731 S ROBERTSON BLVD LOS ANGELES, CA 90034 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/23/2021 | Partial Approval | KEVIN SARGSYAN |
| Sewer | 7/23/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Rough | 7/26/2021 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Subgrade | 7/26/2021 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/28/2021 | Corrections Issued | KEVIN SARGSYAN |
| METHANE-Barrier | 7/28/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Rough | 7/28/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 7/28/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/1/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Barrier | 9/1/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Subgrade | 9/1/2021 | Approved | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 9/2/2021 | No Result Entered | RONALD WEBER |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2021 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 11/3/2021 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 11/4/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 11/15/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/18/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/18/2021 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/22/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 11/22/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/22/2021 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Rough | 11/22/2021 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 11/22/2021 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 12/3/2021 | Approved | KEVIN SARGSYAN |
| Insulation | 12/3/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/3/2021 | Approved | KEVIN SARGSYAN |
| Shower Pan | 12/3/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 2/1/2022 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 2/1/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 2/1/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 2/1/2022 | Corrections Issued | KEVIN SARGSYAN |
| Smoke Detectors | 2/1/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 2/2/2022 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 2/2/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 2/2/2022 | Approved | KEVIN SARGSYAN |
| Final | 2/7/2022 | Corrections Issued | EVAN COOPER |
| Green Building Final | 2/7/2022 | Approved | EVAN COOPER |
| HVAC-Final | 2/7/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 2/7/2022 | Approved | EVAN COOPER |
| Service/Power Release | 2/11/2022 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 2/16/2022 | Not Required | JOHNNY MIRANDA |
| Final | 2/22/2022 | OK to Issue CofO | OGANES TARAKHCHYAN |