|
Deputy Reinf. Concrete
|
5/3/2022
|
Conditional Approval
|
NICK DANERI
|
|
Piling/Pier/Caisson
|
5/3/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
5/4/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
5/5/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
5/6/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
5/9/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
5/10/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
5/11/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
5/12/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
5/13/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
5/17/2022
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/18/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
5/19/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
5/20/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
5/24/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Methane Barrier
|
8/24/2022
|
Conditional Approval
|
WINSTON DUNNING
|
|
Deputy Methane Barrier
|
8/26/2022
|
Conditional Approval
|
WINSTON DUNNING
|
|
Deputy Methane Barrier
|
9/1/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Methane Barrier
|
9/2/2022
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Methane Barrier
|
9/8/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
9/9/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
9/13/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Methane Barrier
|
9/14/2022
|
Conditional Approval
|
NICK DANERI
|
|
METHANE-Subgrade
|
9/14/2022
|
Partial Approval
|
NICK DANERI
|
|
Pre-Inspection
|
9/14/2022
|
Partial Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
9/27/2022
|
Partial Inspection
|
ERNESTO CORRAL
|
|
METHANE-Barrier
|
9/27/2022
|
Partial Inspection
|
ERNESTO CORRAL
|
|
METHANE-Subgrade
|
9/27/2022
|
Partial Inspection
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
10/3/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Methane Barrier
|
10/4/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Methane Barrier
|
10/14/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
10/20/2022
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
10/21/2022
|
Conditional Approval
|
TED RIES
|
|
Footing/Foundation/Slab
|
10/22/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
10/22/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
10/22/2022
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
10/24/2022
|
Off-Hour Fees Due
|
|
|
METHANE-Barrier
|
10/24/2022
|
Off-Hour Fees Due
|
|
|
METHANE-Subgrade
|
10/24/2022
|
Off-Hour Fees Due
|
|
|
Deputy Reinf. Concrete
|
10/25/2022
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
10/28/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
10/31/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
11/2/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
11/2/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
11/3/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Masonry Wall/Backfill
|
11/3/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
11/4/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
11/4/2022
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Rough
|
11/4/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Rough
|
11/4/2022
|
Approved
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
11/4/2022
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
11/4/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
11/7/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
11/7/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
11/9/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
11/9/2022
|
Conditional Approval
|
NICK DANERI
|
|
Piling/Pier/Caisson
|
11/9/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
11/16/2022
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
11/18/2022
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
11/18/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
METHANE-Barrier
|
11/18/2022
|
Approved
|
NICK DANERI
|
|
METHANE-Subgrade
|
11/18/2022
|
Approved
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
11/18/2022
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
11/18/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Rough
|
12/1/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
12/1/2022
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
12/1/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
12/7/2022
|
Conditional Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
12/19/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
12/19/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Structural Steel Frame
|
12/19/2022
|
Partial Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
12/19/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
12/21/2022
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
1/4/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
1/6/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Reinforced Concrete Frame
|
1/6/2023
|
Conditional Approval
|
DARRYL ARNOLD
|
|
Deputy Reinf. Concrete
|
1/9/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
1/11/2023
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Rough
|
1/11/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
1/11/2023
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
1/11/2023
|
Partial Inspection
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
1/19/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Pre-Stress Concrete
|
1/25/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
1/27/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Pre-Stress Concrete
|
1/30/2023
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Rough
|
1/30/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
1/30/2023
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
1/30/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Wall Anchors
|
1/30/2023
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Pre-Stress Concrete
|
2/8/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
2/14/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
2/15/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
2/15/2023
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
2/15/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Rough
|
3/13/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
3/13/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
3/13/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Pre-Stress Concrete
|
3/14/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Pre-Inspection
|
3/15/2023
|
Partial Approval
|
NICK DANERI
|
|
Deputy Pre-Stress Concrete
|
3/17/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
3/17/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Pre-Stress Concrete
|
3/20/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Light Gage Steel Frame
|
3/24/2023
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
3/31/2023
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Masonry Wall/Backfill
|
3/31/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Masonry
|
4/10/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
4/10/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
4/10/2023
|
Conditional Approval
|
NICK DANERI
|
|
Green Building Rough
|
4/10/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
4/10/2023
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
4/10/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
4/11/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Masonry
|
4/14/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
4/14/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
4/14/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
4/14/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
4/14/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
4/14/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
4/14/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Wood Construction
|
4/17/2023
|
Conditional Approval
|
NICK DANERI
|
|
Drywall Nailing
|
4/17/2023
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
4/18/2023
|
Conditional Approval
|
LARRY ARNICK
|
|
Reinforced Masonry Frame
|
4/18/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Steel/Welding
|
4/26/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
4/26/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
4/28/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/1/2023
|
Partial Approval
|
NICK DANERI
|
|
Structural Steel Frame
|
5/1/2023
|
Partial Inspection
|
NICK DANERI
|
|
Drywall Nailing
|
5/3/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
5/3/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
5/3/2023
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/5/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
5/5/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Steel/Welding
|
5/8/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Masonry Wall/Backfill
|
5/11/2023
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
5/16/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Special/Order Compliance
|
5/16/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Deputy Wood Construction
|
5/17/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/18/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
5/18/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
5/18/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
5/18/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
5/22/2023
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/22/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
5/30/2023
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
6/1/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
6/1/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Wood Frame
|
6/1/2023
|
Partial Approval
|
NICK DANERI
|
|
Deputy Wood Construction
|
6/2/2023
|
Conditional Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/2/2023
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/5/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
6/5/2023
|
Partial Approval
|
NICK DANERI
|
|
Deputy Wood Construction
|
6/7/2023
|
Conditional Approval
|
NICK DANERI
|
|
Insulation
|
6/7/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
6/9/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/13/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Wood Construction
|
6/14/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
6/14/2023
|
Conditional Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
6/14/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Wood Frame
|
6/14/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
6/16/2023
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/22/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/26/2023
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/30/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/3/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
7/5/2023
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
7/7/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/7/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Insulation
|
7/7/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Drywall Nailing
|
7/12/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Green Building Rough
|
7/12/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/14/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
7/18/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
7/18/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
7/26/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
7/26/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
7/26/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Drywall Nailing
|
7/27/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Insulation
|
7/31/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
8/3/2023
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
8/3/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Light Gage Steel Frame
|
8/4/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Insulation
|
8/8/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
8/10/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
8/24/2023
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
8/24/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
8/25/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
8/29/2023
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
9/1/2023
|
Partial Approval
|
NICK DANERI
|
|
Deputy Wood Construction
|
9/6/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/6/2023
|
Partial Approval
|
NICK DANERI
|
|
Insulation
|
9/6/2023
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
9/6/2023
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
9/14/2023
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/19/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Drywall Nailing
|
9/25/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
9/25/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Green Building Rough
|
9/28/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
9/28/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
9/28/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Insulation
|
9/29/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Interior/Exterior Lathing
|
10/4/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Drywall Nailing
|
10/6/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
10/10/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
10/10/2023
|
Corrections Issued
|
LARRY ARNICK
|
|
Insulation
|
10/12/2023
|
Partial Approval
|
NICK DANERI
|
|
Deputy Reinf. Masonry
|
10/13/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Insulation
|
10/16/2023
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
10/18/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Drywall Nailing
|
10/24/2023
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
10/24/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
10/25/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Rough
|
10/31/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
10/31/2023
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
10/31/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Rough
|
11/9/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
11/9/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
11/9/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Drywall Nailing
|
11/17/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
11/17/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
11/17/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Green Building Rough
|
11/22/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
11/22/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Wood Frame
|
11/22/2023
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
12/5/2023
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
12/5/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Pre-Inspection
|
12/7/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Drywall Nailing
|
1/29/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
1/29/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Light Gage Steel Frame
|
2/23/2024
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
4/17/2024
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
4/17/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
4/25/2024
|
Partial Inspection
|
NICK DANERI
|
|
Insulation
|
5/8/2024
|
Partial Approval
|
NICK DANERI
|
|
Light Gage Steel Frame
|
5/8/2024
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
5/13/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
5/13/2024
|
Partial Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
5/13/2024
|
Conditional Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
5/17/2024
|
Partial Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
5/21/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Insulation
|
5/28/2024
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/30/2024
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
6/4/2024
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
6/4/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Light Gage Steel Frame
|
6/11/2024
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
6/25/2024
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
6/25/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
7/17/2024
|
Partial Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
7/18/2024
|
Approved
|
RONALD JIMENEZ
|
|
Special/Order Compliance
|
7/19/2024
|
Partial Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
7/24/2024
|
Partial Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
8/15/2024
|
Partial Approval
|
NICK DANERI
|
|
Special/Order Compliance
|
8/27/2024
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
9/16/2024
|
Approved
|
NICK DANERI
|
|
Final
|
9/16/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
9/16/2024
|
Approved
|
NICK DANERI
|
|
Green Building Final
|
9/16/2024
|
Approved
|
NICK DANERI
|
|
Green Building Rough
|
9/16/2024
|
Approved
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
9/16/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
9/16/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
9/16/2024
|
SGSOV Not Ready
|
NICK DANERI
|
|
Smoke Detectors
|
9/16/2024
|
Approved
|
NICK DANERI
|
|
Special/Order Compliance
|
9/16/2024
|
Conditional Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
9/16/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Wood Frame
|
9/16/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Final
|
10/24/2024
|
Conditional Approval
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
10/24/2024
|
Approved
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
10/24/2024
|
Approved
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
10/24/2024
|
SGSOV Approved
|
NICK DANERI
|
|
Special/Order Compliance
|
10/24/2024
|
Conditional Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
10/24/2024
|
Approved
|
NICK DANERI
|
|
Wood Frame
|
10/24/2024
|
Approved
|
NICK DANERI
|
|
Final
|
1/7/2025
|
Conditional Approval
|
NICK DANERI
|