1609-1609 1/2 W 36TH PL 90018
Certificate Information: 1609-1609 1/2 W 36TH PL 90018
- Application / Permit
- 20010-10000-05086
- Plan Check / Job No.
- B20LA24125
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 4-STORY SINGLE FAMILY DWELLING BUILDING "A" WITH ATTACHED ACCESSORY DWELLING UNIT AT THE FIRST STORY PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/15/2021
- Issuing Office
- Current Status
- CofO Issued on 11/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | DANIEL YIP |
| Corrections Issued | 2/5/2021 | DANIEL YIP |
| Quality Review Completed | 2/5/2021 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 8/18/2021 | DANIEL YIP |
| Plan Check Approved | 9/1/2021 | DANIEL YIP |
| Issued | 9/15/2021 | APPLICANT |
| Building Plans Picked Up | 9/20/2021 | APPLICANT |
| CofO in Progress | 11/20/2023 | SABAS ALONSO |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
| CofO Issued | 11/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 4/24/2021 | ROBERT DUFF |
| Construction near power lines | Cleared | 4/30/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/2/2021 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 7/14/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/15/2021 | CECILIO NAVARRO |
| Frnt yard landscape/Water mgmt | Cleared | 8/20/2021 | JOE LUCKEY |
| Building over 36-ft | Cleared | 9/1/2021 | CALOSHA APPROVED |
Contact Information
| Contractor | Luban Z Construction Corp; Lic. No.: 1033129-B | 5695 SORREL HILLS AVE CHINO HILLS, CA 91709 |
| Engineer | Alvarado,, Carlos Humberto; Lic. No.: C19857 | 745 N WALNUTHAVEN DR WEST COVINA, CA 91790 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
| Geologist | Feucht,, Alex Thomas; Lic. No.: GEO4433 | 2443 EAGLE HARBOR DRIVE HENDERSON, NV 890527136 |
| Landscape Architect | Lee,, Cynthia; Lic. No.: LA2524 | 2029 VERDUGO BLVD STE 1020 MONTROSE, CA 91020 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/20/2022 | Partial Approval | SABAS ALONSO |
| Deputy Reinf. Concrete | 2/17/2022 | No Access for Inspection | HORACE FULTZ |
| Excavation/Setback/Form/Re-Bar | 2/17/2022 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 2/17/2022 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Barrier | 2/17/2022 | Approved | SABAS ALONSO |
| METHANE-Subgrade | 2/17/2022 | Approved | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 2/23/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 2/23/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 4/8/2022 | Conditional Approval | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2022 | Partial Approval | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 9/20/2022 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/21/2022 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/27/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 9/27/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 9/27/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 9/27/2022 | Approved | SABAS ALONSO |
| METHANE-Rough | 9/27/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 9/27/2022 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 9/27/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/30/2022 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/5/2022 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 10/5/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 10/11/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 10/21/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 10/27/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 3/17/2023 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Final | 3/17/2023 | Off-Hour Fees Due | |
| HVAC-Final | 3/17/2023 | Not Ready for Inspection | HORACE FULTZ |
| HVAC-Final | 3/17/2023 | Off-Hour Fees Due | |
| Service/Power Release | 3/17/2023 | Not Ready for Inspection | HORACE FULTZ |
| Service/Power Release | 3/17/2023 | Off-Hour Fees Due | |
| ELECTRICAL-Final | 4/4/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 4/4/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 6/13/2023 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 6/17/2023 | Off-Hour Fees Due | |
| Underground Mechanical | 6/20/2023 | Partial Approval | SABAS ALONSO |
| Gas Test | 6/30/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 6/30/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 7/13/2023 | Approved | SABAS ALONSO |
| Service/Power Release | 8/2/2023 | Not Ready for Inspection | SABAS ALONSO |
| Final | 9/13/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 9/13/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/13/2023 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 9/13/2023 | Approved | SABAS ALONSO |
| Smoke Detectors | 9/13/2023 | Approved | SABAS ALONSO |
| Final | 10/3/2023 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 10/3/2023 | SGSOV Approved | SABAS ALONSO |
| Final | 10/16/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Final | 10/20/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 10/26/2023 | Corrections Issued | SABAS ALONSO |
| Final | 11/8/2023 | Corrections Issued | SABAS ALONSO |
| Final | 11/17/2023 | OK to Issue CofO | SABAS ALONSO |