3807-3809 S BUDLONG AVE 90037

Certificate Information: 3807-3809 S BUDLONG AVE 90037

Application / Permit
20010-10000-05080
Plan Check / Job No.
B20LA20651
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX WITH 4-CAR GARAGE AT 1ST FLOOR AT REAR OF LOT. (BUILDING B)
Permit Issued
Issued on 11/20/2023
Issuing Office
Metro
Current Status
CofO Issued on 10/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 YOUNG KIM
Corrections Issued 12/31/2020 YOUNG KIM
Quality Review Completed 1/6/2021 SAI KHUM
Building Plans Picked Up 1/11/2021 APPLICANT
Applicant returned to address corrections 4/30/2021 YOUNG KIM
Applicant returned to address corrections 5/3/2021 YOUNG KIM
Applicant returned to address corrections 6/18/2021 YOUNG KIM
Plan Check Approved 2/6/2023 YOUNG KIM
Issued 11/20/2023 APPLICANT
CofO in Progress 10/27/2025 SABAS ALONSO
No Progress 10/27/2025 DEROLD HAUFF
CofO in Progress 10/27/2025 DEROLD HAUFF
Permit Finaled 10/30/2025 DEROLD HAUFF
CofO Issued 10/30/2025 DEROLD HAUFF
Permit Finaled 10/30/2025 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 1/28/2021 JOHN KIM
Address approval Cleared 2/2/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 2/10/2021 CECILIO NAVARRO
Sewer availability Cleared 2/19/2021 CECILIO NAVARRO
Frnt yard landscape/Water mgmt Cleared 2/22/2021 RICHARD REASER
ZA Case Cleared 2/22/2021 RICHARD REASER
Hydrant and Access approval Cleared 3/11/2021 JOHN CONNEALLY
Low Impact Development Cleared 3/17/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 3/18/2021 CECILIO NAVARRO
Highway dedication Cleared 4/5/2021 CELINA MORENO
Permit Cleared 4/5/2021 CELINA MORENO
Green Code Cleared 6/21/2021 YOUNG KIM
ZI Cleared 1/26/2023 JASON CHAN

Contact Information

Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILLCREST MANOR      ROLLING HILLS ESTATES, CA 90274
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/13/2023 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 1/3/2024 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 1/3/2024 Approved SABAS ALONSO
Deputy Reinf. Concrete 1/10/2024 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/1/2024 No Access for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/2/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/20/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/7/2024 No Access for Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Approved SABAS ALONSO
ELECTRICAL-Rough 6/20/2024 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 6/20/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 1/29/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 1/29/2025 Approved SABAS ALONSO
PLUMBING-Rough 1/29/2025 Corrections Issued SABAS ALONSO
Verify Sprinkler Sign Off 1/29/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 2/5/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 2/5/2025 Approved SABAS ALONSO
Green Building Rough 2/5/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 2/5/2025 Partial Approval SABAS ALONSO
PLUMBING-Rough 2/5/2025 Approved SABAS ALONSO
Insulation 2/7/2025 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 2/19/2025 Approved SABAS ALONSO
Insulation 2/19/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 2/19/2025 Approved SABAS ALONSO
Shower Pan 2/19/2025 Not Ready for Inspection SABAS ALONSO
Shower Pan 2/26/2025 Approved SABAS ALONSO
Underground Mechanical 4/15/2025 Approved BARRY HACHE
ELECTRICAL-Final 9/3/2025 Approved SABAS ALONSO
PLUMBING-Final 9/3/2025 Approved SABAS ALONSO
Final 9/4/2025 Not Ready for Inspection SABAS ALONSO
Green Building Final 9/4/2025 Approved SABAS ALONSO
HVAC-Final 9/4/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/4/2025 SGSOV Approved SABAS ALONSO
Service/Power Release 9/4/2025 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 9/4/2025 Approved SABAS ALONSO
ELECTRICAL-Final 10/20/2025 Approved SABAS ALONSO
Final 10/20/2025 Corrections Issued SABAS ALONSO
HVAC-Final 10/20/2025 Approved SABAS ALONSO
PLUMBING-Final 10/20/2025 Approved SABAS ALONSO
Service/Power Release 10/20/2025 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 10/24/2025 Approved SABAS ALONSO
Final 10/24/2025 OK to Issue CofO SABAS ALONSO
Service/Power Release 10/24/2025 Approved SABAS ALONSO