4448 S DAWES AVE 90230

Certificate Information: 4448 S DAWES AVE 90230

Application / Permit
20010-10000-05076
Plan Check / Job No.
B20LA24092
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) GARAGE
Permit Issued
Issued on 7/19/2021
Issuing Office
Current Status
CofO Issued on 8/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 LAMAR DAVIS
Corrections Issued 2/2/2021 LAMAR DAVIS
Quality Review Completed 2/2/2021 GARO TELMI
Applicant returned to address corrections 6/4/2021 LAMAR DAVIS
Plan Check Approved 7/16/2021 LAMAR DAVIS
No Progress 7/16/2021 LAMAR DAVIS
Plan Check Approved 7/16/2021 LAMAR DAVIS
Issued 7/19/2021 APPLICANT
Building Plans Picked Up 7/22/2021 APPLICANT
CofO in Progress 8/12/2023 RICHARD STEINBACH
Permit Finaled 8/15/2023 DANIEL ORRANTE
CofO Issued 8/15/2023 DANIEL ORRANTE
Permit Finaled 8/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 2/16/2021 JOE LUCKEY
Specific Plan Cleared 2/23/2021 VALERIA CEJA
Eng Process Fee Ord 176,300 Cleared 3/8/2021 HISASHI KOBAYAKAWA
Low Impact Development Cleared 5/12/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 7/1/2021 HISASHI KOBAYAKAWA

Contact Information

Architect Hamilton,, John Patrick; Lic. No.: C28865 12240 VENICE BLVD SUITE 25      LOS ANGELES, CA 90066
Contractor Substrata Inc; Lic. No.: 1050826-B 222 N PACIFIC COAST HWY   SUITE 2000    EL SEGUNDO, CA 90245
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/30/2021 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 11/19/2021 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 11/23/2021 Approved ENRIQUE MIRELES
Deputy Wood Construction 1/20/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 2/11/2022 Approved ENRIQUE MIRELES
Wood Frame 2/11/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/1/2022 Approved ENRIQUE MIRELES
Drywall Nailing 3/31/2022 Approved PATRICK QUALEY
Green Building Rough 3/31/2022 Approved PATRICK QUALEY
Special/Order Compliance 3/31/2022 Partial Inspection MICHAEL PELHAM
BUILDING-Rough-Frame 2/28/2023 Approved JESUS RODRIGUEZ
Final 2/28/2023 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 2/28/2023 Approved JESUS RODRIGUEZ
Green Building Final 2/28/2023 Not Ready for Inspection JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Not Ready JESUS RODRIGUEZ
Service/Power Release 2/28/2023 Not Ready for Inspection JESUS RODRIGUEZ
Smoke Detectors 2/28/2023 Not Ready for Inspection JESUS RODRIGUEZ
Final 8/9/2023 Partial Approval JESUS RODRIGUEZ
Green Building Final 8/9/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/9/2023 SGSOV Not Required JESUS RODRIGUEZ