206-206 1/2 E 87TH ST 90003

Certificate Information: 206-206 1/2 E 87TH ST 90003

Application / Permit
20010-10000-05072
Plan Check / Job No.
B20LA24058
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-STORY DUPLEX AT FRONT (2505 SF) WITH (N) ATTACHED GARAGE 140 SF
Permit Issued
Issued on 4/13/2021
Issuing Office
Current Status
CofO Issued on 6/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2020 APPLICANT
Assigned to Plan Check Engineer 1/25/2021 HANS SANTIAGO
Corrections Issued 1/26/2021 HANS SANTIAGO
Quality Review Completed 1/29/2021 ALLEN MANALANSAN
Plan Check Approved 3/23/2021 ANDREW SANTIAGO
Issued 4/13/2021 APPLICANT
Building Plans Picked Up 4/14/2021 APPLICANT
CofO in Progress 6/4/2022 ALEJANDRO DE ARTOLA
Permit Finaled 6/4/2022 DEROLD HAUFF
CofO Issued 6/4/2022 DEROLD HAUFF
Permit Finaled 6/4/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/1/2021 ELAINE LEI
Permit Cleared 2/1/2021 ELAINE LEI
Low Impact Development Cleared 2/10/2021 YVAINNE GALSIM
Eng Process Fee Ord 176,300 Cleared 2/11/2021 ELAINE LEI
Roof/Waste drainage to street Cleared 2/11/2021 ELAINE LEI
Sewer availability Cleared 2/11/2021 ELAINE LEI
Hydrant and Access approval Cleared 2/18/2021 MATTHEW CRAIG
Certificate of Compliance Cleared 2/22/2021 MARC WOERSCHING
Frnt yard landscape/Water mgmt Cleared 2/22/2021 RICHARD REASER
Trees in Parkway Cleared 3/23/2021 JOHN KIM

Contact Information

Contractor New World Construction; Lic. No.: 864461-B 838 E 93RD STREET      LOS ANGELES, CA 90002
Engineer Lee,, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/25/2021 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 7/6/2021 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/6/2021 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/16/2021 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 11/17/2021 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/1/2021 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/10/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 12/10/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/10/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/21/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 12/21/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/21/2021 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 12/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 12/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 12/23/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/28/2021 Approved ALEJANDRO DE ARTOLA
Green Building Rough 12/28/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 12/28/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/28/2021 Approved ALEJANDRO DE ARTOLA
Insulation 1/4/2022 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 1/4/2022 Partial Approval ALEJANDRO DE ARTOLA
Insulation 1/6/2022 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 1/7/2022 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 1/12/2022 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 1/18/2022 Approved ALEJANDRO DE ARTOLA
Sewer 2/25/2022 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 2/25/2022 Approved ALEJANDRO DE ARTOLA
Sewer 3/18/2022 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 3/18/2022 Approved ALEJANDRO DE ARTOLA
Final 3/22/2022 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 3/22/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/21/2022 Approved ALEJANDRO DE ARTOLA
Gas Test 4/21/2022 Approved ALEJANDRO DE ARTOLA
Green Building Final 4/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 4/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/21/2022 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 4/21/2022 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 4/21/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/25/2022 Corrections Issued STUART CHAPMAN
PLUMBING-Final 4/25/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 4/29/2022 Approved ALEJANDRO DE ARTOLA
Gas Test 4/29/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 4/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 4/29/2022 Approved ALEJANDRO DE ARTOLA
Final 5/4/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 5/4/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/4/2022 Approved ALEJANDRO DE ARTOLA
Final 5/26/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 6/3/2022 OK to Issue CofO ALEJANDRO DE ARTOLA