2210 W RESERVOIR ST 90026
Certificate Information: 2210 W RESERVOIR ST 90026
- Application / Permit
- 20010-10000-05058
- Plan Check / Job No.
- B20LA23995
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3 STORY S.F.D. WITH ATTACHED GARAGE AT MIDDLE OF LOT. 2 OF 3
- Permit Issued
- Issued on 5/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 1/22/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 2/11/2021 | WING SUEN |
| Building Plans Picked Up | 2/26/2021 | APPLICANT |
| Applicant returned to address corrections | 2/8/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 2/15/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 3/2/2022 | CRYSTEL MAALOUF |
| Issued | 5/5/2023 | APPLICANT |
| CofO in Progress | 2/13/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
| CofO Issued | 2/14/2025 | DEROLD HAUFF |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2021 | RENZ SORIANO |
| Highway dedication | Cleared | 4/20/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 4/21/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 6/7/2021 | JOHN CONNEALLY |
| Frnt yard landscape/Water mgmt | Cleared | 6/21/2021 | ANACANY HURTADO |
| Miscellaneous | Cleared | 6/21/2021 | ANACANY HURTADO |
| Low Impact Development | Cleared | 8/5/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 8/17/2021 | JEANIE LAM |
| GPI Written Notices | Cleared | 3/2/2022 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 3/2/2022 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Truebuilt Construction Inc; Lic. No.: 1052087-B | 950 E KATELLA AVE STE 5 ORANGE, CA 92867 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/16/2023 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 6/21/2023 | Corrections Issued | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 6/23/2023 | Approved | STUART CHAPMAN |
| Deputy Reinf. Concrete | 6/26/2023 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 7/7/2023 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2023 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/29/2023 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Conditional Approval | THOMAS LOGRASSO |
| HVAC-Rough | 10/10/2023 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/23/2023 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 10/23/2023 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 11/3/2023 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 11/9/2023 | Approved | THOMAS LOGRASSO |
| Deputy Wood Construction | 11/14/2023 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/17/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/27/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 12/27/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/27/2023 | Partial Approval | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 12/27/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 12/29/2023 | Conditional Approval | THOMAS LOGRASSO |
| Drywall Nailing | 1/12/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/29/2024 | Approved | JOSH MEISTER |
| Smoke Detectors | 8/16/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 10/3/2024 | Approved | HAMIK HARTOUNIAN |
| Sewer | 11/5/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 11/26/2024 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 11/26/2024 | Approved | LUIS CASTRO |
| Green Building Final | 11/26/2024 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 11/26/2024 | SGSOV Approved | LUIS CASTRO |
| Service/Power Release | 11/26/2024 | Corrections Issued | LUIS CASTRO |
| Final | 1/16/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Service/Power Release | 1/16/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 1/27/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Service/Power Release | 1/27/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 2/3/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Service/Power Release | 2/3/2025 | Not Required | HAMIK HARTOUNIAN |
| Final | 2/13/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |