2210 W RESERVOIR ST 90026

Certificate Information: 2210 W RESERVOIR ST 90026

Application / Permit
20010-10000-05058
Plan Check / Job No.
B20LA23995
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3 STORY S.F.D. WITH ATTACHED GARAGE AT MIDDLE OF LOT. 2 OF 3
Permit Issued
Issued on 5/5/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 CRYSTEL MAALOUF
Corrections Issued 1/22/2021 CRYSTEL MAALOUF
Quality Review Completed 2/11/2021 WING SUEN
Building Plans Picked Up 2/26/2021 APPLICANT
Applicant returned to address corrections 2/8/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 2/15/2022 CRYSTEL MAALOUF
Plan Check Approved 3/2/2022 CRYSTEL MAALOUF
Issued 5/5/2023 APPLICANT
CofO in Progress 2/13/2025 HAMIK HARTOUNIAN
Permit Finaled 2/14/2025 DEROLD HAUFF
CofO Issued 2/14/2025 DEROLD HAUFF
Permit Finaled 2/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/20/2021 RENZ SORIANO
Highway dedication Cleared 4/20/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 4/21/2021 RENZ SORIANO
Sewer availability Cleared 4/21/2021 RENZ SORIANO
Hydrant and Access approval Cleared 6/7/2021 JOHN CONNEALLY
Frnt yard landscape/Water mgmt Cleared 6/21/2021 ANACANY HURTADO
Miscellaneous Cleared 6/21/2021 ANACANY HURTADO
Low Impact Development Cleared 8/5/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 8/17/2021 JEANIE LAM
GPI Written Notices Cleared 3/2/2022 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 3/2/2022 CRYSTEL MAALOUF

Contact Information

Contractor Truebuilt Construction Inc; Lic. No.: 1052087-B 950 E KATELLA AVE STE 5      ORANGE, CA 92867
Engineer Nuno,, Arnulfo; Lic. No.: C88425 7057 DWIGHT WAY      SAN BERNARDINO, CA 92404

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/16/2023 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 6/21/2023 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 6/23/2023 Approved STUART CHAPMAN
Deputy Reinf. Concrete 6/26/2023 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 7/7/2023 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 8/3/2023 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 8/29/2023 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/8/2023 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Conditional Approval THOMAS LOGRASSO
HVAC-Rough 10/10/2023 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 10/23/2023 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 10/23/2023 Approved THOMAS LOGRASSO
Underground Mechanical 11/3/2023 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 11/9/2023 Approved THOMAS LOGRASSO
Deputy Wood Construction 11/14/2023 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 11/17/2023 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 12/27/2023 Approved THOMAS LOGRASSO
Green Building Rough 12/27/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 12/27/2023 Partial Approval THOMAS LOGRASSO
Verify Sprinkler Sign Off 12/27/2023 Approved THOMAS LOGRASSO
Insulation 12/29/2023 Conditional Approval THOMAS LOGRASSO
Drywall Nailing 1/12/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 1/29/2024 Approved JOSH MEISTER
Smoke Detectors 8/16/2024 Approved JOSH MEISTER
ELECTRICAL-Final 10/3/2024 Approved HAMIK HARTOUNIAN
Sewer 11/5/2024 Corrections Issued HAMIK HARTOUNIAN
Final 11/26/2024 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 11/26/2024 Approved LUIS CASTRO
Green Building Final 11/26/2024 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Approved LUIS CASTRO
Service/Power Release 11/26/2024 Corrections Issued LUIS CASTRO
Final 1/16/2025 Corrections Issued HAMIK HARTOUNIAN
Service/Power Release 1/16/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Final 1/27/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Service/Power Release 1/27/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Final 2/3/2025 Partial Inspection HAMIK HARTOUNIAN
Service/Power Release 2/3/2025 Not Required HAMIK HARTOUNIAN
Final 2/13/2025 OK to Issue CofO HAMIK HARTOUNIAN