2171 W MELLON AVE 90039
Certificate Information: 2171 W MELLON AVE 90039
- Application / Permit
- 20010-10000-05046
- Plan Check / Job No.
- B20LA23947
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT WITH ATTACHED 2-CAR GARAGE PER LAMC 12.22.C.33 WITH ROOF DECK
- Permit Issued
- Issued on 3/8/2022
- Issuing Office
- Current Status
- CofO Issued on 6/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | DANIEL YIP |
| Corrections Issued | 1/25/2021 | DANIEL YIP |
| Quality Review Completed | 2/5/2021 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 5/5/2021 | DANIEL YIP |
| Plan Check Approved | 12/1/2021 | DANIEL YIP |
| Issued | 3/8/2022 | APPLICANT |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| CofO in Progress | 6/13/2023 | THOMAS LOGRASSO |
| No Progress | 6/21/2023 | DONALD CRICHLOW |
| CofO in Progress | 6/26/2023 | DONALD CRICHLOW |
| Permit Finaled | 6/27/2023 | DEROLD HAUFF |
| CofO Issued | 6/27/2023 | DEROLD HAUFF |
| Permit Finaled | 6/27/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2021 | THOMAS LANG |
| Permit | Cleared | 2/26/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2021 | THOMAS LANG |
| Sewer availability | Cleared | 3/12/2021 | THOMAS LANG |
| ZI | Cleared | 6/21/2021 | RICHARD REASER |
| Low Impact Development | Cleared | 8/27/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 9/10/2021 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 11/17/2021 | RUEL COLE |
Contact Information
| Contractor | Dcla Design Build Inc; Lic. No.: 1060451-B | 2241 FERNLEAF LOS ANGELES, CA 90031 |
| Engineer | Lin,, Jason K; Lic. No.: S6095 | 1529 W LONGHILL DR MONTEREY PARK, CA 91754 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/21/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/3/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/3/2022 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/9/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 5/16/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/20/2022 | Approved | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 5/23/2022 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2022 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 8/25/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 8/25/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/25/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/6/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/6/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 9/6/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 9/6/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 9/19/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/19/2022 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/23/2022 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 9/29/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 9/29/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/29/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/25/2023 | Approved | THOMAS LOGRASSO |
| Final | 5/25/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 5/25/2023 | Approved | THOMAS LOGRASSO |
| MERV13>=Final | 5/25/2023 | Approved | THOMAS LOGRASSO |
| MERV13>=Rough | 5/25/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 5/25/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 5/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 5/25/2023 | Partial Approval | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 5/25/2023 | Approved | THOMAS LOGRASSO |
| Final | 6/13/2023 | OK to Issue CofO | THOMAS LOGRASSO |
| Service/Power Release | 6/13/2023 | Approved | THOMAS LOGRASSO |
| Smoke Detectors | 6/13/2023 | Approved | THOMAS LOGRASSO |