906-906 1/2 W 78TH ST 90044

Certificate Information: 906-906 1/2 W 78TH ST 90044

Application / Permit
20010-10000-05006
Plan Check / Job No.
B20LA23816
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 23'x48'6" 3-story duplex building with attached 4-car garage ground level at rear of lot. 2 of 2.
Permit Issued
Issued on 1/20/2022
Issuing Office
Current Status
CofO Issued on 7/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 TU HUA
Corrections Issued 2/10/2021 TU HUA
Quality Review Completed 2/24/2021 GARO TELMI
Applicant returned to address corrections 9/2/2021 TU HUA
Applicant returned to address corrections 9/30/2021 TU HUA
Plan Check Approved 10/6/2021 TU HUA
Issued 1/20/2022 APPLICANT
Building Plans Picked Up 2/10/2022 APPLICANT
CofO in Progress 7/1/2024 MICHAEL LEWIS
Permit Finaled 7/3/2024 DEROLD HAUFF
CofO Issued 7/3/2024 DEROLD HAUFF
Permit Finaled 7/3/2024 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/1/2021 KURT CORRAL
Address approval Cleared 4/22/2021 WALLIE JONG
Permit Cleared 4/22/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/18/2021 WALLIE JONG
Sewer availability Cleared 6/21/2021 WALLIE JONG
Low Impact Development Cleared 7/15/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/20/2021 WALLIE JONG
Trees in Parkway Cleared 8/11/2021 JOHN KIM

Contact Information

Contractor Vickers Construction Company Inc; Lic. No.: 1008338-B 952 E 116TH STREET      LOS ANGELES, CA 90059
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/2/2022 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 6/2/2022 Partial Approval JOAQUIN GREENOUGH
Special/Order Compliance 6/3/2022 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 10/21/2022 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 11/18/2022 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 11/22/2022 Approved LILIANA PORTILLO
HVAC-Rough 11/22/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 11/22/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 11/28/2022 Conditional Approval HORACE FULTZ
Green Building Rough 11/28/2022 Approved HORACE FULTZ
Verify Sprinkler Sign Off 11/28/2022 Not Ready for Inspection HORACE FULTZ
Wood Frame 11/28/2022 Conditional Approval HORACE FULTZ
BUILDING-Rough-Frame 12/1/2022 Conditional Approval LILIANA PORTILLO
HVAC-Rough 12/1/2022 Approved LILIANA PORTILLO
Insulation 12/1/2022 Corrections Issued LILIANA PORTILLO
Verify Sprinkler Sign Off 12/1/2022 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 12/6/2022 Partial Approval LILIANA PORTILLO
Drywall Nailing 12/21/2022 Conditional Approval LILIANA PORTILLO
Insulation 12/21/2022 Conditional Approval LILIANA PORTILLO
Gas Test 2/16/2023 Approved LILIANA PORTILLO
Underground Mechanical 2/16/2023 Partial Approval LILIANA PORTILLO
Underground Mechanical 3/13/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 8/18/2023 Approved MICHAEL LEWIS
Drywall Nailing 8/18/2023 Approved MICHAEL LEWIS
Final 8/18/2023 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 8/18/2023 Conditional Approval MICHAEL LEWIS
Green Building Final 8/18/2023 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Not Ready MICHAEL LEWIS
Service/Power Release 8/18/2023 Not Ready for Inspection MICHAEL LEWIS
Smoke Detectors 8/18/2023 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 8/18/2023 Approved MICHAEL LEWIS
Final 8/24/2023 Partial Inspection MICHAEL LEWIS
Footing/Foundation/Slab 8/24/2023 Approved MICHAEL LEWIS
Green Building Final 8/24/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Not Ready MICHAEL LEWIS
Service/Power Release 8/24/2023 Corrections Issued MICHAEL LEWIS
Final 9/8/2023 Conditional Approval MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/8/2023 SGSOV Approved MICHAEL LEWIS
Service/Power Release 9/8/2023 Approved MICHAEL LEWIS
Final 6/14/2024 Conditional Approval MICHAEL LEWIS
Final 6/21/2024 Corrections Issued MICHAEL LEWIS
Final 6/28/2024 OK to Issue CofO MICHAEL LEWIS