1411 N LAUREL WAY 90210
Certificate Information: 1411 N LAUREL WAY 90210
- Application / Permit
- 20010-10000-04984
- Plan Check / Job No.
- B20LA23773
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED 5-CAR GARAGE
- Permit Issued
- Issued on 8/8/2022
- Issuing Office
- Metro
- Current Status
- Issued on 8/8/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2021 | SINA KHOSRAVI |
| Corrections Issued | 2/16/2021 | SINA KHOSRAVI |
| Quality Review Completed | 3/9/2021 | STANLEY RAAP |
| Applicant returned to address corrections | 4/8/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 4/21/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 8/5/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 8/19/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 9/16/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 2/8/2022 | SINA KHOSRAVI |
| Applicant returned to address corrections | 2/25/2022 | SINA KHOSRAVI |
| Applicant returned to address corrections | 3/11/2022 | SINA KHOSRAVI |
| Plan Check Approved | 4/26/2022 | SINA KHOSRAVI |
| Building Plans Picked Up | 4/28/2022 | APPLICANT |
| Issued | 8/8/2022 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/19/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/19/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/19/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/19/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 4/19/2021 | DINAH GARIN |
| Permit | Cleared | 4/22/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2021 | DINAH GARIN |
| Sewer availability | Cleared | 4/23/2021 | DINAH GARIN |
| ZA Case | Cleared | 4/26/2021 | JASON CHAN |
| ZA Case | Cleared | 4/26/2021 | JASON CHAN |
| Hydrant and Access approval | Cleared | 5/21/2021 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 8/23/2021 | SINA KHOSRAVI |
| Low Impact Development | Cleared | 12/23/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/12/2022 | RAYMOND MUGAMBWA |
| Grading Pre-Inspection | Cleared | 3/11/2022 | SINA KHOSRAVI |
Contact Information
| Architect | Sun,, David Hao Chen; Lic. No.: C19374 | 1117 N SHERBOURNE DRIVE WEST HOLLYWOOD, CA 90069 |
| Contractor | Owner-Builder | , |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
| Geologist | Irvine,, Jon A; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/7/2024 | Partial Inspection | BRENDAN LOONEY |
| Pre-Inspection | 2/13/2024 | Approved | SEAN HAUPT |
| Piling/Pier/Caisson | 2/16/2024 | Partial Approval | SEAN HAUPT |
| Piling/Pier/Caisson | 3/1/2024 | Partial Approval | SEAN HAUPT |
| Deputy Grading | 3/4/2024 | Approved | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 3/5/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 3/7/2024 | Partial Approval | SEAN HAUPT |
| Deputy Grading | 3/27/2024 | Corrections Issued | VASIL MIHALEV |
| Deputy Grading | 4/1/2024 | Conditional Approval | MICHAEL PELHAM |
| Reinforced Concrete Frame | 4/10/2024 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/15/2024 | Partial Approval | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 4/19/2024 | Partial Approval | SEAN HAUPT |
| Piling/Pier/Caisson | 4/25/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 4/26/2024 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 5/8/2024 | Partial Approval | SEAN HAUPT |
| Piling/Pier/Caisson | 5/8/2024 | Partial Approval | SEAN HAUPT |
| Piling/Pier/Caisson | 7/1/2024 | Approved | SEAN HAUPT |
| Reinforced Concrete Frame | 7/8/2024 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 7/29/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 7/29/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 8/15/2024 | Partial Approval | SEAN HAUPT |
| Reinforced Concrete Frame | 8/15/2024 | Not Ready for Inspection | SEAN HAUPT |
| Footing/Foundation/Slab | 8/22/2024 | Partial Approval | SEAN HAUPT |
| Reinforced Concrete Frame | 8/29/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 9/12/2024 | Partial Approval | SEAN HAUPT |
| Reinforced Concrete Frame | 9/23/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Reinforced Concrete Frame | 9/26/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 10/4/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 10/18/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 10/31/2024 | Partial Approval | SEAN HAUPT |
| Sewer | 11/4/2024 | Approved | SEAN HAUPT |
| Reinforced Concrete Frame | 11/14/2024 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 11/15/2024 | Not Ready for Inspection | SEAN HAUPT |
| Footing/Foundation/Slab | 11/19/2024 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 11/19/2024 | Partial Approval | SEAN HAUPT |
| Reinforced Concrete Frame | 12/9/2024 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 12/18/2024 | Partial Approval | SEAN HAUPT |
| Underground Mechanical | 12/18/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 1/17/2025 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 2/19/2025 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/15/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 4/15/2025 | Partial Approval | SEAN HAUPT |
| Grounding or Bonding | 4/15/2025 | Partial Approval | SEAN HAUPT |
| Pool Piping | 4/15/2025 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 4/30/2025 | Partial Approval | SEAN HAUPT |
| Deputy Steel/Welding | 5/6/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 5/7/2025 | Partial Approval | SEAN HAUPT |
| Deputy Steel/Welding | 5/8/2025 | Partial Approval | SEAN HAUPT |
| Deputy Steel/Welding | 5/9/2025 | No Access for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 5/9/2025 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Steel/Welding | 5/27/2025 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 6/18/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 6/18/2025 | Partial Approval | SEAN HAUPT |
| Sewer | 7/3/2025 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 7/17/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 7/17/2025 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 7/25/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 7/25/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 8/14/2025 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 8/18/2025 | Partial Approval | SEAN HAUPT |
| Green Building Rough | 8/29/2025 | Not Ready for Inspection | SEAN HAUPT |
| Structural Steel Frame | 8/29/2025 | Corrections Issued | SEAN HAUPT |
| Verify Sprinkler Sign Off | 8/29/2025 | Not Ready for Inspection | SEAN HAUPT |
| Structural Steel Frame | 9/12/2025 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 3/9/2026 | Corrections Issued | CARLOS MATAMOROS |
| Reinforced Concrete Frame | 3/9/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2026 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2026 | Corrections Issued | CARLOS MATAMOROS |