951 S WILTON PL 90019

Certificate Information: 951 S WILTON PL 90019

Application / Permit
20010-10000-04935
Plan Check / Job No.
B20LA23703
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW EIGHT (8) UNIT THREE (3) STORY APARTMENT BUILDING. TWO STORIES TYPE VA RESIDENTIAL OVER ONE STORY OF TYPE 1A PARKING GARAGE
Permit Issued
Issued on 6/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 6/16/2022 MANUEL MONTUFAR
Issued 6/28/2022 APPLICANT
CofO in Progress 12/9/2024 EDWIN GREGORYONA
CofO Issued 12/12/2024 ADAM BURGESS
Permit Finaled 12/12/2024 ADAM BURGESS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/16/2021 RENZ SORIANO
Address approval Cleared 8/18/2021 RENZ SORIANO
Bicycle Parking Cleared 8/24/2021 JEREMY CHOK
Highway dedication Cleared 9/16/2021 RENZ SORIANO
Driveway location Cleared 9/30/2021 PETE EYRE
Construction near power lines Cleared 10/5/2021 RIDWAN HARDY
Sewer availability Cleared 10/7/2021 RENZ SORIANO
Permit Cleared 10/19/2021 RENZ SORIANO
Building over 36-ft Cleared 10/20/2021 CALOSHA APPROVED
Green Code Cleared 12/3/2021 MANUEL MONTUFAR
Trees in Parkway Cleared 12/9/2021 ADALBERTO VERA
Hydrant and Access approval Cleared 12/21/2021 ROBERT DUFF
Fire Marshal Fire Life Safety Cleared 3/3/2022 OSCAR SALGADO JR
Low Impact Development Cleared 3/17/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 3/22/2022 JEANETTE VONG
CPC Cleared 3/29/2022 AMANDA KAINER
HPOZ Cleared 3/29/2022 AMANDA KAINER
Frnt yard landscape/Water mgmt Cleared 4/6/2022 MAXFIELD VERMY
Opn space landscape/Water mgmt Cleared 4/6/2022 MAXFIELD VERMY
DAS Clearance Cleared 6/7/2022 ELIZABETH TOMS

Contact Information

Architect Kang,, Hyeung Seok; Lic. No.: C38323 3530 WILSHIRE BLVD #1830      LOS ANGELES, CA 90010
Contractor M T M Construction Inc; Lic. No.: 659142-B 16035 PHOENIX DR      CITY OF INDUSTRY, CA 91745
Engineer Kim,, Seung Su; Lic. No.: S5909 15808 APOLLO PLACE      GARDENA, CA 90249
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 1424 ROLLING HILLS DR      FULLERTON, CA 92835
Landscape Architect Kim,, Yunsoo; Lic. No.: LA5887 2629 FOOTHILL BLVD. #204      LA CRESCENTA, CA 91214

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 7/14/2022 Partial Approval NICK DANERI
Pre-Inspection 7/14/2022 Partial Inspection NICK DANERI
Excavation/Setback/Form/Re-Bar 7/20/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 8/10/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 8/11/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 8/11/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/12/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 8/22/2022 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 8/22/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 8/23/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Masonry 8/24/2022 Conditional Approval WINSTON DUNNING
Green Building Rough 8/25/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 8/25/2022 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 8/25/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 8/25/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Masonry 8/26/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Masonry 9/12/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 9/14/2022 Conditional Approval MICHAEL ROSENBERG
Reinforced Masonry Frame 9/14/2022 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 9/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 9/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 9/19/2022 Conditional Approval MICHAEL ROSENBERG
Reinforced Masonry Frame 9/20/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 10/31/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 10/31/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 11/1/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/12/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/22/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/6/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/9/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 1/11/2023 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 1/11/2023 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 1/11/2023 Not Ready for Inspection EDWIN GREGORYONA
Wall Anchors 1/11/2023 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 1/12/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/17/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/18/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 2/10/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 2/10/2023 Not Ready for Inspection EDWIN GREGORYONA
Wall Anchors 2/10/2023 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 2/10/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 2/13/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 3/7/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 3/9/2023 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 3/9/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 3/9/2023 Not Ready for Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 4/4/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/11/2023 Conditional Approval MICHAEL ROSENBERG
Reinforced Masonry Frame 4/19/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 5/2/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 5/4/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 5/23/2023 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 6/20/2023 Partial Approval GREGORY POMISH
Insulation 6/23/2023 Partial Approval GREGORY POMISH
Drywall Nailing 6/29/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/12/2023 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 7/14/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/21/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 8/29/2023 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 8/29/2023 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 9/5/2023 Approved EDWIN GREGORYONA
Drywall Nailing 9/15/2023 Partial Approval GREGORY POMISH
Pre-Inspection 1/25/2024 Approved EDWIN GREGORYONA
Deputy Drilled-In Anchors 2/12/2024 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 2/13/2024 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 2/13/2024 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 2/13/2024 Approved EDWIN GREGORYONA
Masonry Wall/Backfill 2/23/2024 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 2/23/2024 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 3/6/2024 Partial Approval EDWIN GREGORYONA
Final 4/4/2024 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 4/4/2024 Approved EDWIN GREGORYONA
Green Building Final 4/4/2024 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 4/4/2024 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 4/4/2024 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 4/4/2024 Approved EDWIN GREGORYONA
Final 5/31/2024 Partial Inspection EDWIN GREGORYONA
Green Building Final 5/31/2024 Approved EDWIN GREGORYONA
Smoke Detectors 5/31/2024 Approved EDWIN GREGORYONA
Final 6/26/2024 Partial Inspection EDWIN GREGORYONA
Final 7/17/2024 Not Ready for Inspection EDWIN GREGORYONA
Final 12/9/2024 OK to Issue CofO EDWIN GREGORYONA