1218 S ARAPAHOE ST 90006

Certificate Information: 1218 S ARAPAHOE ST 90006

Application / Permit
20010-10000-04907
Plan Check / Job No.
B20LA23615
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 4-STORY SFD WITH OPEN PARKING. 1 OF 3
Permit Issued
Issued on 9/9/2021
Issuing Office
Current Status
CofO Issued on 7/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 JOE VO
Corrections Issued 1/11/2021 JOE VO
Quality Review Completed 1/21/2021 KEN GILL
Applicant returned to address corrections 3/14/2021 JOE VO
Applicant returned to address corrections 4/26/2021 JOE VO
Plan Check Approved 8/23/2021 JOE VO
Issued 9/9/2021 APPLICANT
Building Plans Picked Up 9/15/2021 APPLICANT
CofO in Progress 6/30/2022 KATHRYN BUTTERWORTH
Permit Finaled 7/7/2022 DEROLD HAUFF
CofO Issued 7/7/2022 DEROLD HAUFF
Permit Finaled 7/7/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/5/2021 CELINA MORENO
Highway dedication Cleared 4/5/2021 CELINA MORENO
Permit Cleared 4/5/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/6/2021 CELINA MORENO
Sewer availability Cleared 4/6/2021 CELINA MORENO
Driveway location Cleared 4/22/2021 PETE EYRE
Hydrant and Access approval Cleared 4/22/2021 MATTHEW CRAIG
Trees in Parkway Cleared 7/8/2021 JOHN KIM
Construction near power lines Cleared 7/30/2021 RIDWAN HARDY
Low Impact Development Cleared 8/5/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/18/2021 CELINA MORENO
Building over 36-ft Cleared 8/23/2021 CALOSHA APPROVED
Green Code Cleared 8/23/2021 JOE VO

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/20/2021 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/20/2021 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 10/20/2021 Approved ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 10/25/2021 Conditional Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 10/26/2021 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/27/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/29/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 1/10/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 1/10/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/10/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/12/2022 Conditional Approval ALEJANDRO DE ARTOLA
HVAC-Rough 1/12/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/12/2022 Conditional Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/20/2022 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 1/20/2022 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 1/20/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Insulation 1/25/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Insulation 1/26/2022 Approved KATHRYN BUTTERWORTH
Drywall Nailing 2/3/2022 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 2/3/2022 Partial Approval KATHRYN BUTTERWORTH
Interior/Exterior Lathing 2/10/2022 Partial Approval KATHRYN BUTTERWORTH
Gas Test 2/16/2022 Partial Approval KATHRYN BUTTERWORTH
Shower Pan 2/16/2022 Approved KATHRYN BUTTERWORTH
Gas Test 3/15/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Sewer 3/15/2022 Approved KATHRYN BUTTERWORTH
Gas Test 3/30/2022 Partial Approval KATHRYN BUTTERWORTH
Underground Mechanical 3/30/2022 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Final 6/1/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Final 6/1/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 6/10/2022 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 6/10/2022 Approved KATHRYN BUTTERWORTH
Final 6/10/2022 Corrections Issued KATHRYN BUTTERWORTH
Gas Test 6/10/2022 Approved KATHRYN BUTTERWORTH
Green Building Final 6/10/2022 Approved KATHRYN BUTTERWORTH
HVAC-Final 6/10/2022 Approved KATHRYN BUTTERWORTH
PLUMBING-Final 6/10/2022 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 6/10/2022 SGSOV Approved KATHRYN BUTTERWORTH
Service/Power Release 6/10/2022 Approved KATHRYN BUTTERWORTH
Smoke Detectors 6/10/2022 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 6/10/2022 Approved KATHRYN BUTTERWORTH
Final 6/22/2022 OK to Issue CofO KATHRYN BUTTERWORTH