8404 S RAMSGATE AVE 90045
Certificate Information: 8404 S RAMSGATE AVE 90045
- Application / Permit
- 20010-10000-04893
- Plan Check / Job No.
- B20LA23528
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* SECOND STORY ADDITION TO (E) GARAGE FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33 (c)-(d)
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- Issued on 12/2/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | LAMAR DAVIS |
| Corrections Issued | 1/22/2021 | LAMAR DAVIS |
| Quality Review Completed | 2/2/2021 | TU HUA |
| Applicant returned to address corrections | 4/8/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 10/27/2021 | LAMAR DAVIS |
| Plan Check Approved | 11/16/2021 | LAMAR DAVIS |
| Issued | 12/2/2021 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/24/2021 | BRIAN MILLER |
| Address approval | Cleared | 2/11/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 2/22/2021 | ERIK BEASLEY |
| Specific Plan | Cleared | 5/11/2021 | FREDDY GARCIA |
| Construction near power lines | Cleared | 6/9/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/9/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 9/30/2021 | YVAINNE GALSIM |
| GPI Written Notices | Cleared | 10/19/2021 | JONATHAN HOM |
| Roof/Waste drainage to street | Cleared | 11/5/2021 | SAUL GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/13/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 1/13/2022 | Approved | BOBBY KEY |
| Pre-Inspection | 1/13/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Partial Approval | BOBBY KEY |
| Green Building Rough | 2/17/2022 | Not Ready for Inspection | BOBBY KEY |
| Wood Frame | 2/17/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 3/23/2022 | Conditional Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 3/23/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/23/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Insulation | 3/29/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Shower Pan | 3/29/2022 | Approved | JESUS RODRIGUEZ |
| Wood Frame | 3/29/2022 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/6/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 4/6/2022 | Approved | BOBBY KEY |
| Green Building Rough | 4/6/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 4/6/2022 | Approved | BOBBY KEY |
| Insulation | 4/6/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/26/2022 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/6/2022 | Approved | JESUS RODRIGUEZ |
| Sewer | 6/6/2022 | Approved | BOBBY KEY |
| Special/Order Compliance | 3/31/2023 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 3/17/2026 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 3/27/2026 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 3/27/2026 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 3/27/2026 | Approved | ANTHONY EGSON |