13348 W WINGO ST 91331
Certificate Information: 13348 W WINGO ST 91331
- Application / Permit
- 20010-10000-04887
- Plan Check / Job No.
- B20LA23519
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **eplan** New ADU, 1200 sf at rear of property
- Permit Issued
- Issued on 2/2/2022
- Issuing Office
- Current Status
- CofO Issued on 7/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 1/26/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/3/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/7/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 12/8/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 1/8/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 1/18/2022 | ARSALAN SHABESTARI |
| Issued | 2/2/2022 | APPLICANT |
| CofO in Progress | 6/29/2023 | MICHEL ABAJAN |
| No Progress | 7/5/2023 | ROBERT GOLD |
| CofO in Progress | 7/19/2023 | MICHAEL SMITH |
| Permit Finaled | 7/19/2023 | MICHAEL SMITH |
| CofO Issued | 7/19/2023 | MICHAEL SMITH |
| Permit Finaled | 7/19/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 11/10/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 11/10/2021 | TA ANH |
| Sewer availability | Cleared | 11/16/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 11/17/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/3/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/12/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/12/2022 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 10/20/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/2/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/2/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/2/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 11/2/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/2/2022 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 11/2/2022 | Approved | MICHEL ABAJAN |
| Insulation | 11/4/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 11/4/2022 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 11/4/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 11/8/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 11/9/2022 | No Access for Inspection | DAVID MATSON |
| Interior/Exterior Lathing | 11/15/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 11/15/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/29/2022 | No Access for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 12/1/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/1/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/1/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 12/2/2022 | No Access for Inspection | ARAM AVEDISIAN |
| HVAC-Final | 12/5/2022 | Corrections Issued | MICHEL ABAJAN |
| Pre-Inspection | 12/5/2022 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 2/23/2023 | Approved | MICHEL ABAJAN |
| Final | 5/9/2023 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/9/2023 | Approved | MICHEL ABAJAN |
| Green Building Final | 5/9/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 5/9/2023 | Corrections Issued | MICHEL ABAJAN |
| Smoke Detectors | 5/9/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/22/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 5/22/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 5/22/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/22/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/22/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 5/22/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 5/26/2023 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/26/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 5/26/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/27/2023 | Approved | MICHEL ABAJAN |
| Final | 6/27/2023 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 6/27/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 6/27/2023 | Approved | MICHEL ABAJAN |
| Service/Power Release | 6/27/2023 | Approved | MICHEL ABAJAN |