13348 W WINGO ST 91331

Certificate Information: 13348 W WINGO ST 91331

Application / Permit
20010-10000-04887
Plan Check / Job No.
B20LA23519
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**eplan** New ADU, 1200 sf at rear of property
Permit Issued
Issued on 2/2/2022
Issuing Office
Current Status
CofO Issued on 7/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2020 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 ARSALAN SHABESTARI
Corrections Issued 1/26/2021 ARSALAN SHABESTARI
Quality Review Completed 2/3/2021 HERNAN ARREOLA
Applicant returned to address corrections 6/7/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 12/8/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 1/8/2022 ARSALAN SHABESTARI
Plan Check Approved 1/18/2022 ARSALAN SHABESTARI
Issued 2/2/2022 APPLICANT
CofO in Progress 6/29/2023 MICHEL ABAJAN
No Progress 7/5/2023 ROBERT GOLD
CofO in Progress 7/19/2023 MICHAEL SMITH
Permit Finaled 7/19/2023 MICHAEL SMITH
CofO Issued 7/19/2023 MICHAEL SMITH
Permit Finaled 7/19/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/24/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/1/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 11/10/2021 KURT CORRAL
Low Impact Development Cleared 11/10/2021 TA ANH
Sewer availability Cleared 11/16/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/17/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/3/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 10/12/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 10/12/2022 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 10/20/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 11/2/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 11/2/2022 Approved MICHEL ABAJAN
Green Building Rough 11/2/2022 Approved MICHEL ABAJAN
HVAC-Rough 11/2/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 11/2/2022 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 11/2/2022 Approved MICHEL ABAJAN
Insulation 11/4/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/4/2022 Approved MICHEL ABAJAN
METHANE-Rough 11/4/2022 Approved MICHEL ABAJAN
Drywall Nailing 11/8/2022 Approved MICHEL ABAJAN
Drywall Nailing 11/9/2022 No Access for Inspection DAVID MATSON
Interior/Exterior Lathing 11/15/2022 Approved MICHEL ABAJAN
Shower Pan 11/15/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 11/29/2022 No Access for Inspection MICHEL ABAJAN
ELECTRICAL-Final 12/1/2022 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 12/1/2022 Approved MICHEL ABAJAN
PLUMBING-Final 12/1/2022 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 12/2/2022 No Access for Inspection ARAM AVEDISIAN
HVAC-Final 12/5/2022 Corrections Issued MICHEL ABAJAN
Pre-Inspection 12/5/2022 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Final 2/23/2023 Approved MICHEL ABAJAN
Final 5/9/2023 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 5/9/2023 Approved MICHEL ABAJAN
Green Building Final 5/9/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 5/9/2023 Corrections Issued MICHEL ABAJAN
Smoke Detectors 5/9/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/22/2023 Corrections Issued JENNIFER RABUCHIN
Final 5/22/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 5/22/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 5/22/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/22/2023 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 5/22/2023 Corrections Issued JENNIFER RABUCHIN
Final 5/26/2023 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 5/26/2023 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 6/27/2023 Approved MICHEL ABAJAN
Final 6/27/2023 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 6/27/2023 Approved MICHEL ABAJAN
PLUMBING-Final 6/27/2023 Approved MICHEL ABAJAN
Service/Power Release 6/27/2023 Approved MICHEL ABAJAN