5913 N ENCINO AVE 91316
Certificate Information: 5913 N ENCINO AVE 91316
- Application / Permit
- 20010-10000-04867
- Plan Check / Job No.
- B20LA23445
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-PLAN: New detached 2-story Accessory Dwelling Unit ** the LID clearance has been deferred. approval for LID requirements shall be obtained from LASAN prior to the issuance of CofO**
- Permit Issued
- Issued on 1/25/2022
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 1/25/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/3/2021 | HERNAN ARREOLA |
| Plan Check Approved | 1/22/2022 | ARSALAN SHABESTARI |
| Issued | 1/25/2022 | APPLICANT |
| CofO in Progress | 10/13/2022 | SEAN HAUPT |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
| CofO Issued | 3/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/3/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/4/2021 | JOHN TRIANTAFYLLOS |
| ZI | Cleared | 2/4/2021 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 3/10/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 9/22/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/22/2021 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 12/14/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | L E C Construction Inc; Lic. No.: 617150-B | 30831 OAKRIM DRIVE WESTLAKE VILLAGE, CA 91362 |
| Engineer | Adams,, Robert Charles; Lic. No.: NA21234 | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/10/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 3/10/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 3/10/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2022 | Approved | SEAN HAUPT |
| Sewer | 3/30/2022 | Not Ready for Inspection | SEAN HAUPT |
| Sewer | 5/9/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 6/3/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 6/3/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 6/3/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 6/3/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 6/3/2022 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 6/3/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 6/13/2022 | Approved | SEAN HAUPT |
| Shower Pan | 6/13/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 6/20/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 6/20/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 8/29/2022 | Approved | SEAN HAUPT |
| Final | 8/29/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 8/29/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 8/29/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 8/29/2022 | Not Ready for Inspection | SEAN HAUPT |
| Smoke Detectors | 8/29/2022 | Approved | SEAN HAUPT |
| Final | 10/12/2022 | Partial Inspection | JUSTIN HAWLEY |
| Service/Power Release | 10/12/2022 | Partial Approval | JUSTIN HAWLEY |
| Final | 10/13/2022 | OK to Issue CofO | SEAN HAUPT |
| Service/Power Release | 10/13/2022 | Approved | SEAN HAUPT |