1343-1347 W 40TH PL 90037

Certificate Information: 1343-1347 W 40TH PL 90037

Application / Permit
20010-10000-04859
Plan Check / Job No.
B20LA23405
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED 2 STORY DUPLEX WITH ONE ADU PER ENGINEER DESIGN, NFPA 13D TRUOUT (ATTACHED ADU PER ORDINANCE, LAMC 12.22 A.33 (c) AND (e))
Permit Issued
Issued on 5/10/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2020 APPLICANT
Assigned to Plan Check Engineer 1/19/2021 AUNG SOE
Corrections Issued 1/21/2021 AUNG SOE
Quality Review Completed 1/26/2021 HERNAN ARREOLA
Building Plans Picked Up 2/16/2021 APPLICANT
Applicant returned to address corrections 7/29/2021 AUNG SOE
Applicant returned to address corrections 2/8/2022 AUNG SOE
Applicant returned to address corrections 2/17/2022 AUNG SOE
Applicant returned to address corrections 3/16/2022 AUNG SOE
Plan Check Approved 3/17/2022 AUNG SOE
Issued 5/10/2022 APPLICANT
CofO in Progress 3/18/2024 SABAS ALONSO
Permit Finaled 3/18/2024 DEROLD HAUFF
CofO Issued 3/18/2024 DEROLD HAUFF
Permit Finaled 3/18/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/21/2021 WALLIE JONG
Permit Cleared 9/21/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/22/2021 WALLIE JONG
Trees in Parkway Cleared 10/21/2021 ADALBERTO VERA
Hydrant and Access approval Cleared 11/10/2021 KURT CORRAL
Low Impact Development Cleared 1/6/2022 CHRIS PARK
Sewer availability Cleared 2/7/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 2/8/2022 WALLIE JONG

Contact Information

Contractor Meza Aurelio; Lic. No.: 1065516-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/13/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 8/18/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Partial Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 2/21/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/15/2023 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 3/15/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 4/7/2023 Approved SABAS ALONSO
Green Building Rough 4/7/2023 Approved SABAS ALONSO
HVAC-Rough 4/7/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 4/7/2023 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 4/11/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 4/11/2023 Approved SABAS ALONSO
Insulation 4/20/2023 Approved SABAS ALONSO
Drywall Nailing 4/27/2023 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 5/3/2023 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 5/10/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 5/10/2023 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 5/16/2023 Partial Approval SABAS ALONSO
Green Building Final 2/15/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 2/16/2024 Approved SABAS ALONSO
Green Building Final 2/16/2024 Approved SABAS ALONSO
HVAC-Final 2/16/2024 Approved SABAS ALONSO
PLUMBING-Final 2/16/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/16/2024 SGSOV Approved SABAS ALONSO
Service/Power Release 2/16/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 2/16/2024 Approved SABAS ALONSO
Final 3/7/2024 Corrections Issued SABAS ALONSO
Service/Power Release 3/7/2024 Not Ready for Inspection SABAS ALONSO
Final 3/15/2024 OK to Issue CofO SABAS ALONSO
Service/Power Release 3/15/2024 Approved SABAS ALONSO