19116 W MARILLA ST 91324

Certificate Information: 19116 W MARILLA ST 91324

Application / Permit
20010-10000-04835
Plan Check / Job No.
B20LA23289
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d)
Permit Issued
Issued on 11/24/2021
Issuing Office
Current Status
CofO Issued on 8/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 2/4/2021 LAMAR DAVIS
Corrections Issued 2/10/2021 LAMAR DAVIS
Quality Review Completed 2/21/2021 HERNAN ARREOLA
Applicant returned to address corrections 8/3/2021 LAMAR DAVIS
Applicant returned to address corrections 10/27/2021 LAMAR DAVIS
Plan Check Approved 11/4/2021 LAMAR DAVIS
Issued 11/24/2021 APPLICANT
CofO in Progress 10/16/2022 JOHN KIDWELL
CofO in Progress 10/16/2022 JOHN KIDWELL
CofO in Progress 8/21/2023 DAVID SCANTLIN
Permit Finaled 8/22/2023 JOHN JANSON
CofO Issued 8/22/2023 JOHN JANSON
Permit Finaled 8/22/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/20/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/20/2021 CARLOS AGUILERA
Sewer availability Cleared 7/21/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/11/2021 JOHN CONNEALLY
Low Impact Development Cleared 10/26/2021 TA ANH
Roof/Waste drainage to street Cleared 11/3/2021 CARLOS AGUILERA
Miscellaneous Cleared 11/4/2021 LAMAR DAVIS

Contact Information

Contractor Green Walls-Us Inc; Lic. No.: 798508-B 22955 MARIANO ST      WOODLAND HILLS, CA 91367

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
DAVID SCANTLIN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/9/2021 Approved JEFFREY PARD
Footing/Foundation/Slab 12/9/2021 Approved JEFFREY PARD
Pre-Inspection 12/9/2021 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 1/6/2022 Partial Approval JEFFREY PARD
Insulation 1/6/2022 Partial Approval JEFFREY PARD
PLUMBING-Rough 1/6/2022 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 1/19/2022 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 1/19/2022 Approved DAVID SCANTLIN
Green Building Rough 1/19/2022 Not Ready for Inspection DAVID SCANTLIN
Verify Sprinkler Sign Off 1/19/2022 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 1/20/2022 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 1/27/2022 Partial Approval JEFFREY PARD
Green Building Rough 1/27/2022 Approved JEFFREY PARD
Verify Sprinkler Sign Off 1/27/2022 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 2/1/2022 Partial Approval JEFFREY PARD
PLUMBING-Rough 2/1/2022 Approved JEFFREY PARD
Sewer 2/25/2022 Approved JEFFREY PARD
Insulation 3/21/2022 Not Ready for Inspection DAVID SCANTLIN
Shower Pan 3/21/2022 Approved DAVID SCANTLIN
Special/Order Compliance 3/21/2022 Approved DAVID SCANTLIN
Drywall Nailing 4/29/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 9/14/2022 Approved JEFFREY PARD
Final 9/14/2022 Corrections Issued JEFFREY PARD
Green Building Final 9/14/2022 Corrections Issued JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 9/14/2022 SGSOV Approved JEFFREY PARD
Service/Power Release 9/14/2022 Not Required JEFFREY PARD
Smoke Detectors 9/14/2022 Approved JEFFREY PARD
Verify Sprinkler Sign Off 9/14/2022 Approved JEFFREY PARD
Final 10/12/2022 Corrections Issued JOHN KIDWELL
Green Building Final 10/12/2022 Approved JOHN KIDWELL
Special/Order Compliance 12/22/2022 Corrections Issued JOHN KIDWELL
Final 12/29/2022 Not Ready for Inspection DAVID SCANTLIN
Final 8/18/2023 OK to Issue CofO DAVID SCANTLIN